§ 24-501. Sewage disposal to protect water supply

Open this section

a. 1. The commissioner of environmental protection is authorized and empowered to enter into a contract or agreement, subject to the approval of the mayor, with the appropriate authorities of the following localities:

(a) The town board of any town and the municipal authorities of any village within the Croton watershed in the county of Westchester,

(b) The authorities of the town of Carmel, Putnam county,

(c) The municipal authorities of the village of Brewster, Putnam county, to provide for the disposal of the sewage of any town or village within the Croton watershed, of one or more villages or sewer districts within the town of Carmel, and of the village of Brewster, in the manner provided for in such agreement. The town board of any such town or the municipal authorities of any such village are likewise authorized and empowered to enter into such agreement. They may provide in such contract or agreement that all persons within the area affected owning buildings on streets where sewers are, or may hereafter be constructed or located under such agreement, or any modification thereof, shall connect with the sewer systems as provided in such contract or agreement.

2. In the event of the failure of any such person or persons to connect with any sewer system and the failure of the town board of any such town or the municipal authorities of any such village to compel such person or persons to connect with such sewer system within sixty days after notice and demand, the city shall have the right to cause such connection to be made at the expense of the owner failing or neglecting to connect with such sewer system. The expense of making any such connection may be recovered by the city in a suit in any court having competent jurisdiction.

3. With respect to the town of Carmel, such contract or agreement may authorize or require the construction, operation and maintenance of a sewage disposal plant, equipment and facilities for the disposition of the sewage of one or more villages or sewer districts in the town of Carmel or the extension, improvement, operation and maintenance of existing plants, if any, for such purpose. The town board of the town of Carmel is hereby authorized to contract between one or more sewer districts or between one or more villages and one or more sewer districts for any trunk sewer lines or laterals thereof to convey the sewage of such village, villages, district, or districts to a disposal plant operated by any district, village or municipality. The cost and expense of such trunk sewer, pumping station or appurtenant works shall be apportioned by the town board of the town of Carmel pro rata to the volume of sewage or population, or both, of the area benefited.

b. 1. The commissioner of environmental protection is authorized and empowered, subject to the approval of the mayor, to enter into contracts or agreements with the municipal authorities of any towns or incorporated villages within the Esopus and Schoharie watersheds, in the counties of Ulster, Delaware, Schoharie and Greene, to provide, maintain and operate systems and plants for the collection and disposal of sewage in any such town or village. The municipal authorities of any such village or the town board of any such town are likewise authorized and empowered to enter into such agreements with the city.

2. When a sewerage system shall have been constructed, the city shall lay and thereafter maintain such pipes as may be necessary from such sewerage system to the outside of the foundation walls of buildings containing water-using sanitary plumbing. The cost of such pipes shall be paid by the city and in all cases where such pipes are so laid the owner shall make no claim for damage for such entry on his or her property unless the city shall have failed to replace and leave the surface and all improvements in the same condition as they were before the laying of such pipes.

3. When the city shall have constructed a sewerage system and shall have laid the necessary pipes from such system to the outside of the foundation wall of any building containing water-using sanitary plumbing, the owner of such building shall cause the drainage and sewerage of such building to be connected with and discharged into such pipes.

4. Upon the approval of the state engineer of the plans for any system of sewerage and disposal works prepared pursuant to any agreement entered into under the provisions of paragraph one of this subdivision, and upon the filing of such plans in the office of the state commissioner of health and of the town clerks in the towns in which such sewers and disposal works are located, the city is granted the right to such reasonable use of the highways, roads, streets and other public property of any county, village or town through which such sewer may pass or in which any part thereof may be located as may be necessary to construct, maintain and operate such sewer and disposal works. Where the route of such sewer follows any state highway, county highway or town road, such highway or road shall be replaced and repaired by the city to the satisfaction of the department, body or official having jurisdiction thereover.

c. Notwithstanding any provision of any general, special or local law or of any charter, the commissioner of environmental protection is hereby authorized and empowered to enter into a contract or agreement, subject to the approval of the mayor, with the governing body of the county of Westchester, to provide for the disposal of the sewage of any municipality located in the county of Westchester wherein such disposal is required to protect the water supply of the city of New York. The governing body of the county of Westchester is likewise authorized and empowered to enter into such contract or agreement.

§ 24-502. Transfer of certain board of estimate lands in the borough of Brooklyn

Open this section

a. All of the board of estimate lands, within the lines of former West 8th street between Surf avenue and the public beach, shown eliminated as a street and laid out as a park addition on map W-1817 adopted by the board of estimate on September twenty-second, nineteen hundred sixty-six, (Cal. No. 41), and shown as being closed and discontinued on map V-1818 adopted by the board of estimate on September twenty-second, nineteen hundred sixty-six, Cal. No. 29 and filed in the office of the register in Kings county on October twenty-seventh, nineteen hundred sixty-six as map No. 3859, are hereby discontinued as board of estimate lands and shall become park lands of the city.

b. There are reserved to the department of environmental protection sewer rights for the maintenance, repair and reconstruction of existing sanitary sewer and storm water sewers in the bed of the discontinued West 8th street, and subject to the condition that no structure of a permanent nature shall be erected over any of the existing sewers.

§ 24-503. Drainage plan

Open this section

a. The commissioner of environmental protection shall devise and prepare a plan for the proper sewerage and drainage of the city, so far as the same has not already been done, for the purpose of thoroughly draining and carrying off water and other matter. He or she shall lay out the city into as many sewerage districts as he or she may deem necessary for such purpose, and shall determine and show, on suitable maps or plans:

1. The location, course, size and grade of each sewer and drain proposed for each of such districts;

2. The contemplated depth of such sewers and drains below the present surface and below the established grades of streets and avenues;

3. The proposed alterations and improvements in existing sewers;

4. Such other particulars as may be necessary for the purpose of exhibiting a complete plan of the proposed sewerage therein.

b. Such plan shall indicate the location and size of all sewage disposal works or plants, and the necessary appurtenances thereto, as determined by the department of environmental protection.

c. The commissioner of environmental protection shall submit such map or plan simultaneously to the department of health and mental hygiene, the director of city planning, each affected community board, the office of the appropriate borough president, the appropriate council member, and the appropriate senator and member of assembly. The department of health and mental hygiene shall review such map or plan with respect to the creation or abatement of any health hazard. Such department shall file a statement with the commissioner of environmental protection and the director of city planning, in relation to such map or plan, within fifteen days subsequent to such submission either approving or disapproving such map or plan.

d. The director of city planning shall review and determine the conformance of such map or plan with the city map, as adopted. Upon determination that such map or plan conforms with the city map, such director shall certify such determination to the commissioner of environmental protection. Unless the director shall file a statement with such commissioner in relation to such map or plan within thirty days subsequent to the submission of said map or plan, such map or plan shall be deemed to conform with the city map and shall constitute the certification thereof.

e. Copies of such map or plan as approved in accordance with the provisions of this section shall be filed by the commissioner of environmental protection in each county office of record, the community board for the community in which any portion of such map or plan is situated, the office of the borough president in which any portion of such map or plan is situated within the city of New York, the offices of the council member, senator and member of assembly representing a district in which any portion of such map or plan is situated within the city of New York, and in the offices of the department of transportation and department of health and mental hygiene of such city.

f.* The commissioner of environmental protection shall submit semiannual reports to the mayor and the speaker of the council regarding the inspection, maintenance and repair of catch basins within the jurisdiction of the commissioner, disaggregated by community district. The first semiannual report shall cover the period from July 1, 2016, through December 31, 2016. Such reports shall include the number of catch basins inspected, the number of clogged or malfunctioning catch basins identified, the number of catch basins unclogged or repaired, whether the inspection was in response to a complaint, and the response time for resolution of any complaint. The commissioner of environmental protection shall also ensure that such catch basins are inspected, at a minimum, once every year, and are unclogged or repaired within nine days after an inspection or the receipt of a complaint about a clogged or malfunctioning catch basin. Catch basins not unclogged or repaired within nine days after an inspection or the receipt of a complaint shall be identified in the semiannual report.

f.* The department of environmental protection shall inspect each catch basin under the jurisdiction of the commissioner of environmental protection in accordance with a multi-tiered inspection schedule based on the 10-year rainfall flood risk area map developed pursuant to section 24-809, any other stormwater flood maps maintained by such department, and performance history, including inspection data, maintenance records, and 311 complaints received, of such catch basins. The department of environmental protection shall evaluate such multi-tiered inspection schedule no less than once every 3 years.

* Editor's note: there are two subsections designated as f in this section.

g. The department of environmental protection shall resolve each clogged catch basin inspected pursuant to subdivision f of this section within 8 business days of the date on which such department received a complaint about such catch basin being clogged or the date on which such department identified, upon inspection, such catch basin as being clogged, whichever is earlier.

h. No later than September 17, 2026, and no later than every September 17 thereafter, the commissioner of environmental protection shall submit a report to the mayor, the speaker of the council, and the public advocate regarding the inspection, cleanup, and maintenance of catch basins, disaggregated by community district. Each such report shall include a description of the multi-tiered inspection schedule required pursuant to subdivision f of this section and an explanation of any changes made to such multi-tiered inspection schedule since the submission of the prior report. Each such report shall include a list of catch basins about which the department of environmental protection received a complaint of having been clogged or which such department identified, upon inspection, as being clogged, and did not resolve within the time period required by subdivision g of this section.

(Am. L.L. 2015/048, 6/2/2015, eff. 7/1/2016; Am. 2022 N.Y. Laws Ch. 790, 12/28/2022, eff. 6/26/2023; Am. 2023 N.Y. Laws Ch. 98, 3/3/2023, eff. 3/3/2023; Am. L.L. 2026/017, 1/17/2026, eff. 7/1/2026)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2015/048.

§ 24-503.1. Sewer backups

Open this section

a. As used in this section, the following terms have the following meanings:

Confirmed sewer backup. The term “confirmed sewer backup” means a determination by the department that, upon field investigation by the department, a sewer backup complaint is associated with a condition in a sewer system. Such conditions may include surcharging, temporary overtaxing, blockages, or collapses.

Sewer system. The term “sewer system” means all sewers, drains, pipes, and appurtenances used to convey sewage and under the jurisdiction of the commissioner of environmental protection.

Unconfirmed sewer backup. The term “unconfirmed sewer backup” means a determination by the department that, upon field investigation by the department, a sewer backup complaint is associated with a condition other than a condition in a sewer system.

b. Where a confirmed sewer backup occurs, the commissioner shall ensure that the sewer segment causing the confirmed sewer backup is identified, inspected, and cleaned as necessary within 10 calendar days of a confirmation by the department of such backup.

c. Within 30 calendar days of an unconfirmed sewer backup, the department shall provide notice of such unconfirmed sewer backup to the person who submitted to the department the sewer backup complaint and to the resident of the property about which the complaint was made. Such notice shall provide, but need not be limited to, the following:

1. The department’s determination that the sewer backup complaint was not associated with a condition in a sewer system;

2. A statement that a backup complaint may be related to an adverse condition in a privately owned sewer, pipe, or appurtenance and that if backups continue then such owner should consider conducting an inspection of such privately owned sewer, pipe, or appurtenance; and

3. An informational pamphlet regarding potential causes of adverse conditions in privately owned sewers, pipes, and appurtenances that are used to convey sewage from a private property to a sewer system.

(L.L. 2019/060, 3/31/2019, eff. 3/31/2019; Am. L.L. 2024/123, 12/18/2024, eff. 12/18/2024)

§ 24-503.2. Plan to prevent confirmed sewer backups for the sewer system

Open this section

a. As used in this section, the following terms have the following meanings:

Confirmed sewer backup. The term "confirmed sewer backup" means a sewer backup complaint that, upon field investigation by the department, is confirmed to be associated with a condition in a sewer system. Such conditions may include surcharging, temporary overtaxing, blockages, or collapses.

Sewer system. The term "sewer system" means all sewers, drains, pipes and appurtenances used to convey sewage and under the jurisdiction of the commissioner of environmental protection.

b. No later than June 30, 2025, and every 5 years thereafter, the commissioner of environmental protection shall submit to the mayor and the speaker of the council, and post on the department of environmental protection’s website, a plan to prevent confirmed sewer backups for the sewer system. Such plan shall include, but need not be limited to:

1. Confirmed sewer backup prevention and response measures;

2. Identifying areas with, on average, more than 1 confirmed sewer backup in a 12-month period;

3. Procedures targeting reductions in confirmed sewer backups in the portions of the sewer system most heavily impacted;

4. Procedures targeting reductions in recurring confirmed sewer backups;

5. A review of root control strategies of other municipalities; and following such review, the department may recommend root control strategies for private property owners;

6. A comprehensive grease management program including commercial establishments and residential households; and

7. Identifying areas where notices of claim filed with the comptroller during the preceding 5 years allege that a sewer backup has damaged persons or property, to the extent it is practicable for the department to review such notices.

(L.L. 2019/061, 3/31/2019, eff. 3/31/2019; Am. L.L. 2024/123, 12/18/2024, eff. 12/18/2024)

§ 24-503.3. Comprehensive stormwater plan and stormwater dashboard

Open this section

a. Definitions. As used in this section, the following terms have the following meanings:

Area of service. The term “area of service” means a geographic area of the city served by infrastructure owned or leased by the city to capture and divert rainfall and minimize street flooding, to be designated by the department.

Department. The term “department” means the department of environmental protection.

Level of service. The term “level of service” means the expected performance of infrastructure owned or leased by the city to capture and divert rainfall and minimize street flooding.

b. Recommended levels of service. No later than July 1, 2026, the department shall designate areas of service that collectively encompass the entire city and recommend a level of service for each such area, provided that each such level shall be sufficient to mitigate expected flood risk in such area. In determining the recommended levels of service, the department shall consider plans, studies, and reports concerning stormwater flooding, including but not limited to the Southeast Queens flood mitigation plan required pursuant to section 24-530 and the environmental justice plan required pursuant to section 3-1003. After July 1, 2026, the department may revise the areas of service and recommended levels of service, provided that such levels, as revised, comply with this subdivision.

c. Technical progress reports. No later than July 1, 2027, and every 2 years thereafter until the department submits the comprehensive stormwater plan required pursuant to subdivision d of this section, the department shall publish a technical progress report on the development of such comprehensive stormwater plan. Each such technical progress report shall: provide an update on the status of such comprehensive stormwater plan; include a map of the areas of service designated by the department and indicate the recommended level of service for each such area, noting any revisions since the date of the previous technical progress report; provide an update on each project, policy, or other measure that the department has recommended, developed, or implemented to provide the recommended levels of service since the date of the previous technical progress report; recommend additional projects, policies, or other measures to provide the recommended levels of service, including measures that owners of private property could adopt to mitigate stormwater flooding, with priority given to such projects, policies, or other measures which address areas of the city most vulnerable to stormwater flooding; and indicate the department’s most recent estimate of the date by which the stormwater infrastructure of the city will achieve the recommended levels of service.

d. Comprehensive stormwater plan. No later than July 1, 2035, the department shall publish, in consultation with the office of long-term planning and sustainability, a comprehensive stormwater plan for the city. Such plan shall: include a map of the areas of service designated by the department; indicate the recommended level of service for each area of service; describe and provide an update on each project, policy, or other measure that the department has recommended, developed, or implemented to provide the recommended levels of service; recommend additional projects, policies, or other measures to provide the recommended levels of service, including measures that owners of private property could adopt to mitigate stormwater flooding, with priority given to such projects, policies, or other measures which address areas of the city most vulnerable to stormwater flooding; and provide a timeline for the expected implementation of such recommended projects, policies, or other measures and for the achievement of the recommended levels of service.

e. Stormwater dashboard.

1. No later than July 1, 2026, the department shall create and maintain a stormwater dashboard on the website of the department. Such dashboard shall: indicate the status of the comprehensive stormwater plan; describe the 10-year rainfall flood risk area or provide reference to the maps of such area created pursuant to section 24-809; include a map of the areas of service designated by the department; indicate the recommended level of service for each area of service; and indicate the status of each project, policy, or other measure that the department has recommended to provide the recommended levels of service. The department shall update such dashboard to include additional recommended projects, policies, or other measures and to reflect any revisions to the areas of service or recommended levels of service.

2. Upon publication of the comprehensive stormwater plan, such dashboard shall be updated to: include such comprehensive stormwater plan; indicate the status of each project, policy, or other measure recommended by such plan; and indicate the expected date of implementation of each such project, policy, or other measure. If the department determines that any such project, policy, or other measure shall no longer be recommended, or is otherwise not likely to be implemented, such project, policy, or other measure shall remain listed on such dashboard, with its status indicated as appropriate. If the department revises the areas of service or recommended levels of service after publication of the comprehensive stormwater plan, such department shall update the dashboard accordingly.

3. The department shall update such dashboard no less than once annually.

(L.L. 2025/070, 5/24/2025, eff. 5/24/2025)

§ 24-504. All sewers to be in accordance with general plan

Open this section

It shall be unlawful to construct any sewer, sewage disposal plant or drain in the city unless such sewer, sewage disposal plant or drain shall be in accordance with the general plan for the sewerage of the particular district in which such sewer or drain is proposed to be constructed.

§ 24-504.1. Medical debris in sewerage system study. [Repealed]

Open this section

(Repealed L.L. 2023/069, 5/29/2023, eff. 6/28/2023)

§ 24-504.2. Combined sewer overflow and floatables, including medical debris, study

Open this section

a. The department shall, within eight months of the effective date of this section, complete an analysis of the combined sewer outfall system and its relationship to floatables, including medical debris, discharged through the system, which are deposited on beaches and other shorelines throughout the city. This analysis shall include, but not be limited to, identifying, evaluating and providing:

1. The location of each combined sewer regulator and outfall within the city of New York;

2. A list identifying priority combined sewer regulators, specifically indicating those which discharge within five hundred feet of designated bathing areas;

3. The general composition and quantity of floatables, including medical debris, that are discharged from the combined sewer system, to be compiled from available data;

4. Environmental impacts of floatables, including medical debris, to be compiled from available data;

5. The long-term solutions to be advanced to reduce the discharge of floatables, including medical debris, from combined sewer systems onto beaches and shorelines throughout the city, and the costs associated with these efforts;

6. A quarterly report about the status of this debris, as evidenced by the city-wide floatables study, which shall include any short-term collection and containment methods discovered, which could be implemented in order to reduce the discharge of floatables from the combined sewer system onto beaches and shorelines throughout the city, and the proposed costs associated with these efforts.

b. The commissioner shall, within eight months of the effective date of this section, submit to the council a report on the findings of such analysis and any recommendations as to regulations or legislation necessary to implement the recommendations of the analysis.

§ 24-505. Raising of grade for drainage

Open this section

Whenever the commissioner of environmental protection shall determine that it is necessary to raise the grade of any street or streets for the proper sewage of the sewer district in which such street or streets, or parts of streets, are situated, he or she shall prepare a plan showing such proposed change of grade, and shall present the same to the board of estimate and notify the community board for the community district in which the land is located, the office of the appropriate borough president, and the council member, senator and member of assembly representing the district in which the land is located. The board of estimate shall refer such plan to the commissioner of transportation for report. Such board may change the grade of such street or streets, or parts of streets, so far as shall be necessary for the proper drainage thereof, in accordance with such plan, in the manner provided by section one hundred ninety-nine of the charter.

(Am. 2022 N.Y. Laws Ch. 790, 12/28/2022, eff. 6/26/2023; Am. 2023 N.Y. Laws Ch. 98, 3/3/2023, eff. 3/3/2023)

§ 24-506. Temporary sewers

Open this section

Whenever it shall become necessary to construct a sewer or drain to prevent damage to property or to abate a nuisance and it is impracticable to proceed immediately to the construction of the same in accordance with any plan already adopted, the commissioner of environmental protection, on the approval of the mayor, may construct a temporary sewer or drain in such manner as to avoid such damage or abate such nuisance.

§ 24-507. Private sewers and drains

Open this section

a. The commissioner of environmental protection may issue permits to persons to construct sewers or drains, or to connect with any sewers or drains built in any street, at their own expense. Such permission shall be granted only upon the agreement, in writing, of the persons applying therefor:

1. That they will comply with the provisions of sections 24-521, 3-508 and 3-509 and of subchapter one of chapter one of title nineteen of the code;

2. That they will indemnify the city for any damages or costs to which it may be put by reason of injuries resulting from neglect or carelessness in the performance of the work so permitted;

3. That they or their successors in interest will make no claim against the city if the work so permitted shall be taken up by the city.

b. The commissioner of environmental protection, at any time, may revoke such permit and direct such sewers or drains to be taken up or removed.

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 1993/104.

§ 24-508. Construction of sewers by the owners of private property

Open this section

a. The owners of private property at their cost and expense and in accordance with the provisions of section two hundred twenty-nine of the charter may construct sewers in the streets of the city by filing with the commissioner of environmental protection:

1. Plans and specifications of such sewer;

2. A duplicate copy of the contract for such construction, showing the cost thereof; and

3. A satisfactory guarantee to such commissioner of payment of the expense of supervision of such construction. Upon his or her approval of such plans, specifications and contract, the commissioner shall issue his or her permit for the construction of the proposed sewer.

b. The commissioner of environmental protection thereupon shall file copies of the documents listed in subdivision a with the department of city planning, which shall forward a copy within five days to the community board for the community district in which the property is located, to the appropriate borough board if the plans involve land located in two or more community districts, and to the council member, senator and member of assembly representing the district in which the property is located. Such commissioner shall apportion the cost of construction, according to actual benefit, between the several parcels of property abutting on each side of that part of the street through which the sewer is to be constructed.

c. Until title to such sewer vests in the city of New York, as hereinafter provided, the commissioner of environmental protection shall grant permits for connection with such sewer only to those owners or occupants of the property abutting on that part of the street in which such sewer has been laid who shall prove payment to the party or parties who constructed and paid for such sewer of their proportionate part of the cost and expense shall be paid without the addition of any interest charge. At such time as title to any such sewer shall vest in the city, owners or occupants of the property abutting on that part of the street in which such sewer has been laid who have not requested permission to connect with such sewer, and who have not made payment to the party or parties who constructed and paid for such sewer, shall have the right to connect with such sewer without payment of any part of the cost and expense of such sewer.

d. Except for the purpose of supervision, maintenance and use by the city in connection with its public sewer system, such sewer shall be deemed the private property of the parties or party who shall have paid for its construction. When the owners of all the property abutting on that part of the street in which any such sewer has been laid shall have paid their several shares of the cost of its construction, or when a period of seven years from the time of issuance of the permit pursuant to subdivision a hereof has elapsed, whichever is earlier, it shall be the property of the city. The city in no event shall be liable for any part of the cost and expense of construction of any such sewer.

e. It shall be unlawful for any person to represent to any prospective purchaser of property that a sewer constructed in any street is a city sewer unless such sewer shall have been constructed by the city in accordance with the legally adopted drainage plan of the city and/or accepted as a public sewer in accordance with the provisions of the code.

(Am. 2022 N.Y. Laws Ch. 790, 12/28/2022, eff. 6/26/2023; Am. 2023 N.Y. Laws Ch. 98, 3/3/2023, eff. 3/3/2023)

§ 24-509. Construction of sewers

Open this section

a. The commissioner of environmental protection shall prescribe the manner of opening sewers or drains and the form, size and material of which the connections therewith shall be composed.

b. It shall be unlawful to make a connection with any sewer or drain without the written permit of the commissioner of environmental protection, except that, in conjunction with the issuance of a permit for the construction or alteration of a structure within the curbline, the commissioner of buildings may issue a permit for connection with a sewer or drain. Such connection shall be in the manner prescribed by the commissioner of environmental protection. The commissioner issuing the permit shall require an applicant for such permit to demonstrate to his or her satisfaction that the proposed discharges to the sewer will be in compliance with section 24-523 of this chapter and the regulations promulgated pursuant to such section. For such purpose the commissioner issuing the permit may require the submission of plans, specifications and such other information as he or she may reasonably require.

c. When public sewers are made available, the individual on site private sewage disposal system or any other means of sewage disposal or discharge shall be abandoned in a manner prescribed by the commissioner of buildings. The building house sewer shall be connected to the available public sewer within six months of the date of notification that the sewer has been accepted to receive flow. As used in this subdivision the term "individual on site private sewage disposal system" shall mean a system of interconnected structures, units, pipes and devices, including a septic tank and an absorption area, which does not connect to the city sewer system, and which is used to collect, convey, treat and dispose water-flushed or water-carried domestic or commercial sewage on one tax lot.

d. Any person who violates subdivision c of this section, or any order issued by or rule promulgated by the commissioner pursuant thereto, shall be liable for a civil penalty in an amount not greater than five thousand dollars for each violation, which may be recovered in a proceeding before the environmental control board. A proceeding to recover any civil penalty authorized pursuant to this section shall be commenced by the service of a notice of violation returnable before the environmental control board, which shall have the power to impose the civil penalties prescribed herein.

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 1996/065.

§ 24-510. Fees for connections

Open this section

The fee paid to the commissioner of environmental protection for each permit for the initial connection made with any sewer or drain, either directly or indirectly, and for each plugging or unplugging, of a building house sewer or drain, shall be ninety dollars.

§ 24-512. Charge for sewer connection extending from curb line to sewer or sewer riser

Open this section

a. As used in this section:

1. The term "agency having jurisdiction" shall mean the department of environmental protection.

2. The term "curb-to-sewer connection" shall mean the connection from the curb line to the sewer or to a sewer riser constructed with the sewer.

3. The term "cost" shall mean the actual cost of constructing each sewer-to-curb connection.

4. The term "curb line" shall mean the curb line determined pursuant to the resolution of the board of estimate establishing street and roadway widths.

b. The owner of any parcel of real property to be connected with the sewer system shall pay the cost of each curb-to-sewer connection serving such real property, if such curb-to-sewer connection was or shall be constructed in connection with the construction, reconstruction or replacement of a sewer duly authorized on or after January first, nineteen hundred sixty-two. Such cost shall become due and payable and shall constitute a lien against such property when the amount thereof shall have been computed by the agency having jurisdiction and an entry thereof shall have been made against such premises in the office of the city collector in the book in which charges for curb-to-sewer connections are to be entered. A notice thereof, stating the amount due and the nature of the charge shall be mailed by the city collector, within five days after such entry, to the last known address of the person whose name appears upon the records in the office of the city collector as being the person designated by the owner to receive tax bills or where no name appears, to the premises addressed to either the owner or the agent, together with a statement that if such charge is not paid within ninety days from the date of entry the amount thereof with interest thereon at the rate of seven percent per annum, to be calculated to the date of payment from the date of entry, will constitute, until paid, a lien against the premises which shall be prior and superior to every other lien or claim except the lien of an existing tax, water rent, sewer rent, sewer surcharge or local assessment. If such charge is not paid within ninety days from the date of entry, it shall be the duty of the city collector to collect and receive interest thereon at the rate of seven percent per annum, to be calculated to the date of payment from the date of entry. Such charge and the interest thereon shall continue to be, until paid, a lien on the premises served by such curb-to-sewer connection. Such charge and interest shall be calculated and the lien thereof may be foreclosed in the manner provided by law for the collection and foreclosure of the lien of taxes, sewer rents, sewer surcharges and water rents due and payable to the city, and the provisions of the code applicable to the collection and foreclosure of the lien of such taxes, sewer rents, sewer surcharges and water rents shall apply to such charge and the interest thereon and the lien thereof. Such lien shall be prior and superior to every other lien or claim except the lien of an existing tax, water rent, sewer rent, sewer surcharge, or local assessment. The provisions of section 11-307 of the code applicable to the payment of assessments shall also apply to the charge established pursuant to this section.

c. Nothing contained in this section shall affect, impair or diminish the duty, obligation and responsibility of the owner of real property connected with the sewer system at his or her own cost and expense: (1) to maintain any curb-to-sewer connection serving such real property; and (2) to repair, reconstruct or replace such curb-to-sewer connection except when the necessity for such repair, reconstruction or replacement is caused by the reconstruction or replacement of the sewer or by any other construction work performed by the city.

d. The cost of constructing a curb-to-sewer connection in connection with the construction, reconstruction, or replacement of a sewer duly authorized on or after July first, nineteen hundred sixty-two, shall be paid initially out of the real property fund upon the authorization of the board of estimate. All sums received or collected in reimbursement of such cost pursuant to this section, including interest and penalties thereon, shall be paid into the real property fund. This subdivision shall not apply to or affect the manner of financing the cost of repairing, reconstructing or replacing a curb-to-sewer connection when such repair, reconstruction or replacement is necessary because of the reconstruction or replacement of the sewer or because of any other construction work performed by the city.

§ 24-513. Constructors; license and bond

Open this section

a. All openings into any sewers or drains, for the purpose of making connection therewith, from any house, cellar, vault, yard or other premises, shall be made by persons to be licensed by the commissioner of environmental protection to perform such work. Before being so licensed, such persons shall execute a bond to the city in the sum of one thousand dollars, with one or more sureties to be approved by such commissioner, conditioned:

1. That they will make all openings into any sewer or drain carefully and in the manner prescribed by such commissioner without injuring the same;

2. That they will leave no obstruction of any description whatever in the connection made by them;

3. That they will properly close up the sewer or drain around such connection and make no opening into the arch of any sewer or drain;

4. That they will faithfully comply with the provisions of section eighty-six of the charter, subchapter one of chapter one of title nineteen and sections 3-508 and 3-509 of the code;

5. That they will be responsible for any damages or injuries that may accrue to persons, animals or property, by reason of any opening in any street made by them or those in their employ;

6. That they will properly refill and ram the earth, suitably restore the pavement taken up for excavating, and repave the same should it settle or become out of order within six months thereafter. In case any person so licensed shall neglect to repair the pavement aforesaid, within twenty-four hours after being notified, the commissioner of transportation may cause the same to be done and charge the expense thereof to such licensee.

b. [Repealed.]

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 1993/104.

§ 24-514. Sewer rents

Open this section

a. Sewer system, defined. As used in this section the term "sewer system" shall mean and include the sewers, manholes, intercepting sewers, sewage pumping, treatment and disposal works, and any other plants, works or equipment and accessories within the city, which are used or useful in connection with the collection, treatment or disposal of sewage and waste, and which are owned, operated or maintained by the city as part of the public sewer system.

b. Imposition and computation of sewer rent or charge.

1. In addition to any other fees or charges provided by law, the owner of any parcel of real property connected with the sewer system, including but not limited to real property connected with the sewer system by means of a private sewer or drain emptying into the sewer system, shall pay a sewer rent or charge for the use of the sewer system. Such rent or charge shall be based on the water supplied to any such real property as measured by the amount charged for such water, except as otherwise provided by this section. Such rent or charge shall be computed by the commissioner of environmental protection in accordance with the provisions of this section.

2. For any such property supplied with water from the municipal water supply system the sewer rent or charge shall be equal in amount to sixty percent of the charges for water supplied to such property from such system.

3. For any such property supplied with water by a private water company, the commissioner of environmental protection shall, by rule and regulation, subject to the approval of the board of estimate, fix the fraction of the charges for such water, which shall constitute the sewer rent for such property, so that the sewer rent or charge for such property shall, as nearly as possible, be equivalent to the sewer rent or charge imposed under paragraph two of this subdivision for property supplied with water from the municipal water supply system.

4. If any such property is supplied with river water or water from private wells, the sewer rent or charge for such property shall be equal in amount to sixty percent of the amount that would be charged for the quantity of water supplied from such sources if such water were supplied by the city at the rates charged for water supplied to metered premises. The commissioner of environmental protection shall estimate the quantity of water supplied from such sources and shall compute the sewer rent or charge, on the basis of such estimated quantity, in accordance with the provisions of this paragraph. However, if a water meter, approved by the commissioner of environmental protection, has been or shall be installed by the owner or occupant of the premises to measure the quantity of water supplied from such sources, the quantity of water measured by such meter shall constitute the basis for computing the sewer rent or charge in accordance with the provisions of this paragraph. In the event that such property supplied with river water or water from private wells is also supplied with water from the municipal water supply system or by a private water company, the sewer rent or charge for such property shall consist of the rent or charge computed pursuant to this paragraph and the rent or charges computed in accordance with paragraph two or three of this subdivision as the case may be.

5. The commissioner of environmental protection shall have the power to promulgate rules and regulations, subject to the approval of the board of estimate, prescribing reasonable sewer rents or charges for any such property which is used for an industrial or commercial purpose of such a nature that water supplied to it cannot be entirely discharged into the sewer system. The sewer rent or charges prescribed pursuant to this paragraph shall be based, as far as practicable, upon the amount of sewage discharged into the sewer system as estimated by the commissioner of environmental protection, or where an estimate of such amount is impracticable, upon any other basis bearing a reasonable relationship to the amount of sewage discharged into the sewer system.

c. Additional rule making powers. The commissioner of environmental protection shall have the power to make such additional rules and regulations as may be necessary to carry out the provisions of this section. Such rules and regulations shall be subject to approval by the board of estimate.

d. Cooperation by private persons, water companies, and public agencies. The commissioner of environmental protection may require every person who owns or occupies real property within the city, every private water company supplying water to property within the city, and all municipal agencies, officers, and employees to furnish him or her with such information as may be necessary to carry out the provisions of this section. Every such person, water company, or municipal agency, officer, or employee shall cooperate with the commissioner of environmental protection in carrying out the provisions of this section and shall comply with all rules and regulations promulgated pursuant to this section. Such commissioner shall have the power to hold such hearings and to subpoena such witnesses and direct the production of such books and papers as may be necessary to carry out the provisions of this section.

e. Exemptions from sewer rents or charges. Any real property which is entitled to an exemption from the payment of water rents or charges shall also be exempt from payment of the sewer rents or charges imposed hereunder.

f. Payment and enforcement of sewer rents or charges. All sewer rents or charges imposed hereunder shall be due and payable at the times and in the manner provided in chapters three and four of title eleven of the code. Such rents or charges shall constitute a lien upon the real property served by the sewer system and such lien shall be prior and superior to every other lien or claim except the lien of an existing tax, water rent or local assessment. Such rents or charges shall be collected and the liens thereof may be foreclosed in the manner provided in chapters three and four of title eleven of this code.

g. Sewer fund. The revenues derived from the sewer rentals imposed hereunder, including penalties and interest thereon, shall be kept in a separate and distinct fund to be known as the sewer fund. Such fund shall be used for the payment of the cost of the management, maintenance, operation and repair of the sewer system, the cost of administering and enforcing the provisions of this section and the cost of collection of the sewer rents or charges imposed pursuant to the provisions of this section, and any surplus in such fund shall be used for the payment of the interest and amortization on any debt which has been or shall be incurred for the construction of intercepting sewers and sewage treatment and disposal works, and for the enlargement, replacement, or addition of intercepting sewers or sewage treatment works. However, such funds shall not be used for the extension of sewers to serve unsewered areas.

§ 24-515. Overflow sewers; where discharged

Open this section

a. All overflow sewers deemed necessary for the relief of any main sewers may be discharged into the Gowanus canal or any other canal or inlet within, or water adjacent to, the city.

b. The city shall keep all canals free of any obstruction that may be occasioned by the discharge of such overflow sewers into them. For that purpose, the commissioner of environmental protection shall dredge the same from time to time.

§ 24-516. Newtown creek sewers

Open this section

All sewers emptying directly or indirectly into Newtown creek shall be closed and may be used only as tributaries to other sewers not emptying directly or indirectly into such creek; except that whenever, by reason of heavy rainfall or snow, the sewage and drainage emptying into the sewer in Johnson avenue, borough of Brooklyn, shall be more than such sewer or its extension will carry to the East river, the excess may be discharged into Newtown creek.

§ 24-517. Injury to sewers

Open this section

It shall be unlawful for any person to injure, break or remove any portion of a receiving basin, covering, flag, manhole, vent, sewer, sewage disposal plant or drain, to obstruct the mouth of a sewer or drain, or to place or deposit any substance exceeding one ton in weight upon any wharf or bulkhead through which a sewer or drain has been laid or upon or over any sewer or drain where the same shall be within three feet of the surface of the street.

§ 24-518. Obstructing substances

Open this section

It shall be unlawful for any person to permit any substance to flow or pass into any sewer, drain or receiving basin, connecting with a public sewer, if such substance may form a deposit tending to choke such sewer, drain or basin.

§ 24-518.1. Food waste disposals

Open this section

a. The following terms, as used in this section, shall have the following meanings:

1. A "dwelling" is any building or structure or portion thereof which is occupied in whole or in part as the home, residence or sleeping place of one or more human beings.

2. A "private dwelling" is any building or structure designed and occupied for residential purposes by not more than two families. Private dwellings shall also be deemed to include a series of one-family or two-family dwelling units each of which faces or is accessible to a legal street or public thoroughfare, if each such dwelling unit is equipped as a separate dwelling unit with all essential services, and if each such unit is arranged so that it may be approved as a legal one-family or two-family dwelling.

3. A "multiple dwelling" is a dwelling which is either rented, leased, let or hired out, to be occupied, or is occupied, as the residence or home of three or more families living independently of each other. A multiple dwelling shall also include residential quarters for members of personnel of any hospital staff which are not located in any building used primarily for hospital use, but any building which was erected, altered or converted prior to July first, nineteen hundred fifty-five, to be occupied by such members or personnel or is so occupied on such date shall not be subject to the requirements of the housing maintenance code only so long as it continues to be so occupied if there are local laws applicable to such building and such building is in compliance with such local laws. A multiple dwelling does not include (i) a hospital, convent, monastery, asylum or public institution; or (ii) a fireproof building used wholly for commercial purposes except for not more than one janitor's apartment and not more than one penthouse occupied by not more than two families.

4. The term "putrescible solid waste" shall mean solid waste containing organic matter having the tendency to decompose with the formation of malodorous by-products.

b. Food waste disposals for the discharge of putrescible food wastes from dwelling units may be installed in private dwellings and multiple dwellings, provided that:

1. all putrescible food wastes discharged to a sanitary sewer or to a combined storm and sanitary sewer are discharged in fluid form and at a reasonably uniform rate so as to prevent clogging or stoppage of the drain line, sanitary sewer or combined storm and sanitary sewer;

2. the installation of such food waste disposals is approved by the department of buildings and is in compliance with applicable provisions of the administrative code.

(Am. L.L. 2023/067, 5/29/2023, eff. 6/28/2023)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 1995/074 and L.L. 1997/071.

§ 24-519. Volatile, flammable liquids

Open this section

It shall be unlawful to use any connection with, opening into, or gutter leading into, any sewer or drain, either public or private, for the conveyance or discharge, directly or indirectly, into such sewer or drain, of any volatile flammable liquid, gas or vapor. A volatile, flammable liquid is any liquid that will emit a flammable vapor at a temperature specified in rules of the department.

(Am. L.L. 2017/097, 5/30/2017, eff. 6/29/2017)

§ 24-520. Steam and hot water

Open this section

a. It shall be unlawful to discharge waste water into any sewer at a temperature higher than that prescribed by the commissioner of environmental protection.

b. It shall be unlawful to use a connection with or opening into any sewer or drain for the conveyance or discharge of steam or hot water at a temperature above that prescribed by such commissioner into such sewer or drain, or to discharge steam, or permit it to escape into any sewer, drain, or public street, from any stopcock, valve or other opening in any steam pipe or main.

c. The commissioner of environmental protection, upon the expiration of five days after notice, shall discontinue the discharge of steam or hot water from any connection, cancel the permit for such connection and close up and remove the same, if the discharge of steam or hot water therefrom shall not have been discontinued.

§ 24-520.1. Non-stormwater discharges prohibited

Open this section

a. For purposes of this section, the following terms have the following meanings:

Allowable runoff. The term "allowable runoff" means runoff authorized by the rules of the department of environmental protection to enter storm sewers, provided that such rules shall be consistent with the proper maintenance and purpose of such storm sewers and with the state pollutant discharge elimination system (SPDES) permit for municipal separate storm sewer systems of New York city, SPDES No. NY-0287890 or its successor.

Storm sewer. The term "storm sewer" means a sewer, the primary purpose of which is to carry stormwater.

b. No person shall discharge or cause to be discharged, directly or indirectly, into any storm sewer any substance other than stormwater or allowable runoff. Rules governing allowable runoff may require practices and procedures related to such discharges in furtherance of this section. Such rules may also require approval by the department of such discharges.

c. For purposes of this section, indirect discharges include but are not limited to discharges to any street, gutter, or other conveyance that could reasonably lead to a storm sewer.

(L.L. 2017/097, 5/30/2017, eff. 6/29/2017)

§ 24-521. Excavations for public works

Open this section

a. Notice to public service corporations. Whenever any sewer, culvert, water main or pipe is to be constructed, altered or repaired in any street in which the pipes, mains or conduits of public service corporations are laid, the contractor therefor shall give notice thereof in writing to such corporations, at least forty-eight hours before breaking ground therefor. Such provision shall be included in every contract for constructing, altering or repairing any sewer or culvert, water main or pipe, in any street in which the pipes, mains or conduits of public service corporations shall be laid at the time of making such contract.

b. Public service corporations shall protect their property. Public service corporations whose pipes, mains or conduits are about to be disturbed by the constructing, altering or repairing of any sewer, culvert, water main or pipe, shall, on the receipt of the notice provided for in the preceding subdivision, remove or otherwise protect and replace their pipes, mains and conduits, and all fixtures and appliances connected therewith or attached thereto, where necessary, under the direction of the commissioner of design and construction in accordance with chapter fifty-five of the charter, unless otherwise directed by the mayor pursuant to such chapter.

c. The enforcement of subdivisions a and b hereof shall be pursuant to sections 19-149, 19-150 and 19-151 of the code.

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 1993/104 and L.L. 1995/077.

§ 24-522. Maintenance of private sewers or drains located in public property or in private or public streets and emptying into the public sewer system

Open this section

a. As used in this section:

1. The term "private sewer or drain" shall mean any private sewer or drain located in public property or in any public or private street or streets and emptying into the public sewer system, but shall not include a curb-to-sewer connection as defined in section 24-512 of the code or a house sewer connection.

2. The term "private street" shall mean a privately owned street in which the public has a right of user not subject to revocation by the owner thereof.

b. Notwithstanding any other provision of law, it shall be the duty of the department of environmental protection to control, maintain, supervise and repair, and to inspect periodically, private sewers or drains as defined in subdivision a hereof, provided, however, that the department shall have no obligation or duty to replace or reconstruct any such sewer or drain. The cost of such control, maintenance, supervision, repair and inspection shall be borne by the city, within the amounts duly appropriated therefor.

c. Right of entry.

1. The commissioner of environmental protection, his or her deputies and any other officers and employees of the department of environmental protection, when authorized by such commissioner, may enter upon public or private property and bring in necessary equipment at reasonable hours, for the purpose of exercising the powers or performing the duties of the department under this section. Refusal to permit such entry or equipment shall be punishable as provided in section 24-524 of this chapter.

2. The owner of any parcel of real property connected to the public sewer system, as a condition precedent to the continuance of such connection, and the owner of any parcel of real property who makes application or causes an application to be made on his or her behalf for connection with the public sewer system, as a condition precedent to the granting of permission for such connection, shall be deemed to have consented and agreed that the commissioner of environmental protection and his or her deputies and such other officers or employees of the department of environmental protection as are authorized by such commissioner may, without fee or hindrance, enter the premises connected with the sewer system, or any part thereof and bring in any necessary equipment at proper or reasonable hours for the purpose of exercising the powers and duties of such department prescribed by this section.

§ 24-523. Industrial waste; sewer surcharges

Open this section

a. Definitions. As used in this section, the following terms shall mean:

1. Commissioner. Commissioner of environmental protection.

2. Sewer system. The sewers, manholes, intercepting sewers, sewage pumping, treatment and disposal works, and any other plants, works or equipment and accessories within the city, which are used or useful in connection with the collection, treatment or disposal of sewage and waste, and which are owned, operated or maintained by the city as part of the public sewer system.

3. Sewage. The water-carried human or animal wastes from residences, buildings, industrial establishments, or other places, together with such ground water infiltration and surface water as may be present. The admixture with sewage as above defined by industrial waste or other wastes as hereafter defined, also shall be considered "sewage" within the meaning of this section.

4. Industrial waste. Any liquid, gaseous or solid substance or a combination thereof resulting from any process of industry, manufacturing, trade or business or from the development or recovery of any natural resources.

5. Other wastes. Garbage, refuse, decayed wood, sawdust, shavings, bark, sand, lime, cinders, ashes, and all other discarded matter not sewage or industrial waste.

6. B.O.D. (Denoting biochemical oxygen demand). The laboratory determination of the quantity of oxygen utilized in the biochemical oxidation of organic matter in a given time and at a specified temperature. It is expressed in parts per million (p.p.m) or (mg/liter) of oxygen used in a period of five days at twenty degrees C.

7. S.S. (Denoting suspended solids). The laboratory determination of the dry weight expressed in parts per million (p.p.m) or (mg/liter) of solids that either float on the surface or are in suspension in sewage and can be removed from sewage by filtration.

8. pH. The logarithm of the reciprocal of the hydrogen ion concentration. It indicates the intensity scale of acidity and alkalinity expressed in terms of pH scale running from 0. to 14. A pH value of 7.0 the midpoint of the scale, represents exact neutrality. Values above 7.0 indicate alkalinity and those below 7.0 acidity.

9. Chlorine demand. The amount of chlorine expressed in milligrams per liter which will complete the normal reactions with all chemicals and materials in the waste leaving an excess of 0.1 milligrams per liter after thirty minutes contact time at room temperature.

10. Normal Sewage. Sewage, industrial waste or other wastes having all of the following characteristics:

B.O.D. 1,667 lbs. per million gallons (200 parts per million) or less Chlorine Demand 208 lbs. per million gallons (25 parts per million) or less S.S. 1,667 lbs. per million gallons (200 parts per million) or less Ether soluble materials 417 lbs. per million gallons (50 parts per million) or less pH not less than 5.0 and not more than 9.5

11. Receivable Industrial Waste. Sewage, industrial waste or other wastes having all of the following characteristics:

B.O.D. 2,500 lbs. per million gallons (300 parts per million) or less Chlorine Demand 208 lbs. per million gallons (25 parts per million) or less S.S. 2,916 lbs. per million gallons (350 parts per million) or less Ether soluble materials 417 lbs. per million gallons (50 parts per million) or less pH not less than 5.0 and not more than 9.5;

and such other characteristics as may be specified by the commissioner by rules and regulations promulgated pursuant to the provisions of subdivision e of this section.

12. Pollutants. Substances which may be present in sewage, industrial waste or other waste, whether gaseous, liquid or solid, the amounts of which, for the purposes of this section, shall be determined by the sum of the B.O.D. and the S.S. present therein.

13. Toxic substances. Any substance on the list of toxic pollutants or combination of pollutants published by the administrator of the federal environmental protection agency pursuant to section 307(a)(1) of the federal water pollution control act, commonly referred to as the clean water act, as amended, or any substance whether gaseous, liquid or solid, which when discharged to the sewer system may tend to (i) interfere with or inhibit any sewage treatment plant process or disposal operations, or (ii) be detrimental to the health of human beings or animals or to aquatic life.

14. Cost per pound of removing pollutants from sewage discharged into the sewer system. An amount certified annually by the commissioner which shall be determined by dividing the total costs of removing pollutants from the sewage discharged into the sewer system during the calendar year immediately preceding the date of certification (including the interest and amortization paid in such year upon indebtedness for capital improvements in connection therewith other than original plant construction or expansion) as computed by the commissioner, by the total number of pounds of pollutants removed in such year as computed by the commissioner. The amount so certified shall be filed in the department of public works on July first of each year and shall be used in computing the surcharges hereunder for the use of the sewer system during the one year period commencing on such July first.

15. Laboratory determination. The measurements, tests and analyses of the characteristics of waters and wastes in accordance with the methods contained in the latest edition at the time of any such measurement test or analysis, of "Standard Methods for Examination of Water and Sewage" a joint publication of the American public health association, the American waterworks association and the water pollution control federation or in accordance with any other method prescribed by the commissioner by rules and regulations promulgated pursuant to this section.

b. Imposition and computation of sewer surcharge.

1. In addition to any other fees, charges or sewer rents provided by section 24-514 of the code or any other law, the owner of any parcel of real property connected with the sewer system, including but not limited to real property connected with the sewer system by means of a private sewer or drain emptying into the sewer system, shall pay a surcharge for the use of the sewer system for discharging any sewage, industrial waste or other waste, accepted for admission thereto in which the characteristics resulting from pollutants contained therein exceed the maximum values of such characteristics in receivable industrial waste as defined in subdivision a of this section and the rules and regulations of the commissioner adopted pursuant to this section.

2. i. Such charge shall be computed by the commissioner in accordance with the following formula: The amount of the surcharge shall equal the product of: (A) the cost per pound of removing pollutants from the sewage in the sewer system, (B) a conversion factor and (C) the volume of sewage, industrial waste or other wastes discharged into the sewer system, multiplied by the sum of (A) the average concentration in parts per million by weight of suspended solids for sewage, industrial waste or other wastes discharged into the sewer system, in excess of three hundred fifty parts per million, and (B) the average concentration in parts per million by weight of the biochemical oxygen demand for sewage, industrial waste, or other wastes discharged into the sewer system in excess of three hundred parts per million. Such formula expressed in symbols shall be as follows:

Ds = C × F × V × [(S.S. - 350) + (B.O.D. - 300)]

where Ds = amount of surcharge, in dollars; C = cost per pound (in dollars) of removing pollutants from the sewage discharged into the sewer system expressed to the nearest tenth of a cent; F = 62.41,000,000, i.e., the factor for converting parts per million by weight to pounds per million cubic feet; V = volume, in cubic feet of sewage, industrial waste or other wastes discharged from such premises into the sewer system; S.S. = parts per million by weight of suspended solids in sewage, industrial waste or other wastes discharged from such premises into the sewer system; 350 = maximum parts per million by weight of S.S. allowable in receivable industrial waste; B.O.D. = parts per million by weight of B.O.D. in the sewage, industrial waste or other wastes discharged from such premises into the sewer system; 300 = maximum parts per million by weight of B.O.D. allowable in receivable industrial waste.

ii. In applying such formula the commissioner may use, as the figure representing the number of cubic feet of sewage discharged into the sewer system, (A) the amount of water supplied to the premises by the city or a private water company as shown upon the water meter if the premises are metered, or (B) if the premises are supplied with river water or water from private wells, the amount of water supplied from such sources as estimated by the commissioner, pursuant to paragraph four of subdivision b of section 24-514 of this chapter, or (C) if such premises are used for an industrial or commercial purpose of such a nature that the water supplied to the premises cannot be entirely discharged into the sewer system, the estimate of the amount of sewage discharged into the sewer system made by the commissioner, pursuant to the provisions of paragraph five of subdivision b of section 24-514 of the code, or (D) the number of cubic feet of sewage discharged into the sewer system as determined by measurements and samples taken at a manhole installed by the owner of the property served by the sewer system at his or her own expense in accordance with the terms and conditions of the permit issued by the commissioner pursuant to this method, or (E) a figure determined by the commissioner by any combination of the foregoing or by any other equitable method.

c. 1. The commissioner may require that a permit be obtained for the discharge whether direct or indirect into the sewer system or into any private sewer or drain emptying into the sewer system, of sewage, industrial wastes or other wastes, the characteristics of which do not conform to the characteristics prescribed for normal sewage in accordance with the provisions of paragraph ten of subdivision a of this section or for the discharge of any toxic substance or any other objectionable material or substance specified by the rules and regulations promulgated pursuant to subdivision e of this section. The commissioner, in his or her discretion, may require a permit for all such discharges or for any class or category of such discharges. Any discharge pursuant to such permit shall be upon such terms and conditions as may be established by the commissioner in the issuance of such permit. Such terms and conditions may include requirements of a limitation upon the volume of sewage and the rate of flow permitted from the premises which are the subject of the permit, the installation and maintenance by the permittee at his or her own expense of facilities or equipment for intermittent or continuous measurement of sewage, industrial waste or other wastes discharged into the sewer system from such premises, the installation and maintenance by the permittee, at his or her own expense, of detention tanks or other facilities or equipment for reducing the maximum rates of discharge of sewage to such percentage of the twenty-four hour rate as may be required by the commissioner, the installation and maintenance by the permittee, at his or her own expense of such preliminary treatment facilities as may be required by the commissioner, the installation and maintenance by the permittee, at his or her own expense, of a suitable control manhole in the house sewer, if any, carrying such sewage; the submission to and approval by the commissioner of the plans for any of the facilities or equipment required to be installed and maintained by the permittee pursuant to such terms and conditions; and such other terms and conditions as may be necessary to protect the sewer system and carry out the provisions of this section. Such terms and conditions may also provide that subsequent to the commencement of operation of any preliminary treatment facilities required by the commissioner, periodic reports shall be made by the permittee to the commissioner, setting forth adequate data upon which the acceptability of the sewage, industrial waste or other wastes, after treatment, may be determined. A violation by the permittee of any term or condition of the permit shall constitute cause for revocation or suspension of the permit.

2. Whenever required to carry out the provisions of this section and the regulations promulgated pursuant to this section, the commissioner may require any person discharging directly or indirectly into the sewer system or into any private sewer or drain emptying into the sewer system to (i) establish and maintain such records, (ii) make such reports, (iii) install, use and maintain such monitoring equipment or methods (including where appropriate biological monitoring methods) (iv) sample such effluents (in accordance with such methods, at such locations, at such intervals and in such manner as the commissioner shall prescribe) and (v) provide such other information as he or she may reasonably require.

3. Any person discharging directly or indirectly into the sewer system or into any private sewer or drain emptying into the sewer system, shall be deemed to have consented and agreed that the commissioner or his or her deputies or such other officers or employees as are authorized by the commissioner may enter on the premises from which such discharge is emitted or in which any records required to be maintained under paragraph two are located and may at reasonable times have access to and copy any records, inspect any monitoring equipment or method required under paragraph two and sample any effluents discharged from the premises to the sewer system.

4. It shall be unlawful to make any false statement, representation or certification in any application, record, report, plan, or other document filed with or required to be maintained by the commissioner or to falsify, tamper with or knowingly render inaccurate any monitoring device or method required to be maintained by the commissioner.

d. Sampling of industrial wastes. Whenever sewage, industrial waste or other waste which has characteristics which do not conform to the characteristics prescribed for normal sewage or receivable industrial waste pursuant to paragraphs ten and eleven of subdivision a of this section, or which contains toxic substances or other material or substance excluded from the sewer system by the commissioner pursuant to this section is discharged into the sewer system from any premises, the commissioner shall have the power to take such samples and tests as may be necessary to determine the nature and concentration of such wastes, and shall have the power to reassess his or her findings by taking such additional samples or tests at any time or by periodic rechecks without notice to the owner or person discharging such wastes. Samples shall be taken and flow measurements made, whenever possible, at a common manhole into which all flows of sewage, industrial waste or other waste from such premises are combined. Such manhole shall be constructed by the owner of such premises, at his or her own expense, when directed by order of the commissioner. Whenever the installation of such a manhole is impossible or impracticable, the owner of such premises shall construct and maintain at his or her own expense, any additional manholes required by order of the commissioner, for accurate measurement of all flow of sewage, industrial waste or other wastes discharged from such premises into the sewer system. Failure to comply with an order of the commissioner issued pursuant to this subdivision may subject the premises to temporary termination of water supply in accordance with the provisions of section 11-314 of the code.

e. Rules and regulations.

1. The commissioner shall have the power to promulgate rules and regulations:

(a) identifying toxic substances and regulating, restricting or prohibiting the discharge of such substances into the sewer system in amounts or concentrations which may cause any of the adverse effects described in paragraph thirteen of subdivision a of this section;

(b) regulating, restricting or prohibiting the discharge into the sewer system of any material or substance which is or may be detrimental or destructive to the sewer system or the treatment processes thereof or to the public health or welfare;

(c) specifying the characteristics and the minimum and maximum amounts thereof, in addition to those specified in paragraph eleven of subdivision a hereof, for receivable industrial waste;

(d) such additional rules and regulations as may be necessary to protect personnel, the sewer system and the treatment process thereof and the receiving waters; and

(e) regulating the amount and concentration of substances contained in industrial waste discharged directly or indirectly into the sewer system to achieve compliance with effluent limitations imposed upon city discharges to receiving waters by federal or state law or regulation or a discharge permit issued pursuant thereto.

2. The commissioner shall by rule or regulation adopt the standards, prohibitions and requirements promulgated under the federal water pollution control act, commonly referred to as the clean water act, as amended, except where such standards, prohibitions and requirements are less stringent than those which are established by the commissioner pursuant to paragraph one or three of this subdivision.

3. Notwithstanding any inconsistent provision of paragraphs one and two of this subdivision, the commissioner may order any person discharging a toxic substance directly or indirectly into the sewer system or into any private sewer or drain emptying into the sewer system to reduce the amount or concentration of such toxic substance to a level which the commissioner determines to be economically achievable by the discharger notwithstanding that such level is lower than that which is prescribed in the regulations adopted pursuant to paragraph one or two or that the discharge is not regulated under such provision. Within twenty days after the issuance of an order by the commissioner, any person affected by such order may request a hearing before the commissioner. The commissioner may suspend, revoke or modify the order.

f. Cooperation by private persons, water companies and public agencies. The commissioner may require every person who owns or occupies real property within the city and every private water company supplying water to property within the city, to furnish him or her with such information as may be necessary to carry out the provisions of this section. The commissioner shall have the power to hold hearings and to subpoena any such persons or company, or any officer, employee or agent of any such company, and direct the production of books and papers in order to carry out the provisions of this section. Every such person, water company or public official or municipal agency, officer or employee shall cooperate with the commissioner in carrying out the provisions of this section and shall comply with all rules and regulations promulgated pursuant to this section.

g. Payment and enforcement of sewer surcharges. All surcharges imposed hereunder shall be due and payable at the times and in the manner provided in chapters three and four of title eleven of the code with respect to the payment of sewer rents based upon the metered supply of water. Such sewer surcharges shall constitute a lien upon the real property served by the sewage system and such lien shall be prior and superior to every other lien or claim except the lien of an existing tax, water rent, sewer rent or local assessment. Such sewer surcharges shall be collected and the liens thereof may be foreclosed in the manner provided in chapters three and four of title eleven of the code. The revenues derived from the sewer surcharges imposed hereunder, including penalties and interest thereon shall be paid into the sewer fund established pursuant to section 24-514 of the code and shall be used in the manner and for the purposes provided therein.

§ 24-524. Enforcement and penalties

Open this section

a. Orders. Notwithstanding any other provision of law, the commissioner of environmental protection, and the environmental control board within the office of administrative trials and hearings, shall enforce the provisions of subdivisions b and b-1 of section 1403 of the charter and sections 24-504 through 24-523 of this chapter and the rules promulgated pursuant thereto. Such commissioner and board shall have the power to issue such orders as may be provided for therein and such additional orders as may be necessary for the enforcement of such provisions. The department of environmental protection shall promulgate rules governing the appeal of orders issued by the commissioner.

b. Commissioner's cease and desist orders.

1. Whenever the commissioner of environmental protection has reasonable cause to believe that: (i) a discharge has occurred in violation of the provisions of subdivision b or b-1 of section 1403 of the charter or sections 24-504 through 24-523 of this chapter or of any order or rule issued by the board or commissioner pursuant to such provisions or to subdivision a of this section in furtherance of such provisions or in violation of the conditions of any permit issued pursuant to such provisions and (ii) that such discharge creates or may create an imminent danger to the sewer system or to the public health or to the life or safety of persons, such commissioner may issue a cease and desist order requiring any person who owns, leases, operates, controls or supervises any building, structure, facility or installation from which the unlawful discharge is emitted to take such action as may be necessary to halt or prevent such discharge.

2. If service of the order cannot be made personally because such person cannot be located at such time then service may be made by delivering a copy to a person of suitable age and discretion at the residence or place of business of the person sought to be served. If service cannot be made personally or by such delivery to a person of suitable age and discretion because of inability to locate or to obtain the name or address of such person at such time, service may be made by conspicuously posting a copy of such order upon the property to which it relates and mailing the order to the most recent residential or business address of record of the person sought to be served. The posting and mailing of such order shall be sufficient notice of such order to all persons having a duty in relation thereto under the provisions of this subdivision.

3. If the order is not complied with or so far complied with as such commissioner may regard as reasonable, within the time specified therein such commissioner may act to halt or prevent such discharge by:

i. sealing, blocking or otherwise inactivating any equipment, facility, or device;

ii. terminating the water supply to the premises;

iii. sealing, blocking or otherwise inactivating any private sewer or drain emptying directly or indirectly into the sewer system; or

iv. any other means or method that is reasonable under the circumstances.

For such purpose, in accordance with applicable law, the commissioner of environmental protection or his or her deputies or such other officers or employees as are designated by the commissioner may enter on any public or private property.

4. Any person affected by such an order may make written application to the environmental control board within the office of administrative trials and hearings for a hearing. Such hearing shall be provided, pursuant to the rules of such board within such office, and shall be held within two business days after the receipt of such application. The board may suspend, modify or terminate such order.

c. [Reserved.]

d. Environmental control board cease and desist orders.

1. In the case of any continued or knowing violation of any of the provisions of subdivision b or b-1 of section 1403 of the charter or sections 24-504 through 24-523 of this chapter or any order or rule issued by the environmental control board within the office of administrative trials and hearings or commissioner of environmental protection pursuant to such provisions or subdivision a of this section in furtherance of such provisions or of the conditions of any permit issued pursuant to such provisions or where the board finds that the violation of any of such provisions or of the conditions of any such permit presents or may present a danger to the environment or threatens to interfere with the operation of the sewer system, the board after notice and the opportunity for a hearing in accordance with the rules of such board within such office, may issue a cease and desist order requiring any person who owns, leases, operates, controls or supervises any building, structure, facility or installation to cease and desist from any activity or process which causes or is conducted so as to cause such violation within the time specified in such order.

2. Such order may provide that if the order is not complied with or so far complied with as the commissioner of environmental protection may regard as reasonable within the time specified therein, such commissioner may take such action as shall be specified therein, including but not limited to:

i. sealing, blocking or inactivating any equipment, facility or device;

ii. terminating the water supply to the premises;

iii. sealing, blocking or inactivating any private sewer or drain emptying directly or indirectly into the sewer system; or

iv. any other means or method that is reasonable under the circumstances.

For such purpose, in accordance with applicable law, the commissioner of environmental protection or his or her deputies or such other officers or employees as are designated by such commissioner may enter on any public or private property.

e. Action by corporation counsel. If the respondent fails to comply with any order issued by the environmental control board within the office of administrative trials and hearings or commissioner of environmental protection or with the conditions of any permit, or such board or commissioner otherwise deems it necessary, the corporation counsel, acting in the name of the city, may maintain an action or proceeding in a court of competent jurisdiction to compel compliance with or restrain by injunction the violation of any order or permit issued by such board or commissioner.

f. Civil penalties. Any person who violates or fails to comply with any of the provisions of subdivision b or b-1 of section 1403 of the charter or section 24-504 through 24-523 of this chapter or any order or of any rule issued by the environmental control board within the office of administrative trials and hearings or commissioner of environmental protection pursuant to such provisions or subdivision a of this section in furtherance of such provisions or with the conditions of any permit issued pursuant thereto shall be liable for a civil penalty not exceeding ten thousand dollars for each violation, provided that this subdivision shall not apply to subdivision c of section 24-509 or subdivisions a and b of section 24-521, and provided that the penalty for the removal of a manhole cover in violation of section 24-517 shall be not less than two thousand five hundred dollars. In the case of a continuing violation each day's continuance shall be a separate and distinct offense. The office of administrative trials and hearings, pursuant to section 1049-a of the charter, shall have the power to impose such civil penalties. A proceeding to impose such penalties shall be commenced by the service of a notice of violation returnable to such office. Such office, after a hearing provided in accordance with applicable law and rules, shall have the power to enforce its final decisions and orders imposing such civil penalties as if they were money judgments pursuant to subdivision d of section 1049-a of the charter. A civil penalty imposed by such office may also be collected in an action brought in the name of the city in any court of competent jurisdiction. The environmental control board within the office of administrative trials and hearings, in its discretion, may, within the limits set forth in this subdivision, establish a schedule of civil penalties indicating the minimum and maximum penalty for each separate offense or may use a schedule adopted by the department of environmental protection.

g. Criminal penalties. In addition to the civil penalties set forth in subdivision f of this section, any person who knowingly violates or fails to comply with any provision of subdivision b or b-1 of section 1403 of the charter or sections 24-504 through 24-523 of this chapter or any order or rule issued by the environmental control board within the office of administrative trials and hearings or commission of environmental protection pursuant to such provisions or subdivision a of this section in furtherance of such provisions or with the conditions of any permit issued pursuant thereto shall be guilty of a misdemeanor and, upon conviction thereof, shall be punished by a fine of not less than two hundred fifty nor more than ten thousand dollars, or by imprisonment not exceeding thirty days, or both for each offense, provided that this subdivision shall not apply to subdivision c of section 24-509 or subdivisions a and b of section 24-521, and provided that the punishment for the removal of a manhole cover in violation of section 24-517 shall be a fine of not less than five hundred dollars nor more than ten thousand dollars, or imprisonment not exceeding thirty days, or both for each offense. In the case of a continuing violation each day's continuance shall be a separate and distinct offense. In addition to its application to any other person, the fine provided for in this paragraph shall be deemed a special fine for a corporation within the meaning of section 80.10 of the penal law of the state of New York.

h. Liability to the city. Any person who violates or fails to comply with any of the provisions of subdivision b or b-1 of section 1403 of the charter or sections 24-504 through 24-523 of this chapter or any order or of any rule issued pursuant to such provisions or subdivision a of this section in furtherance of such provisions or with the conditions of any permit issued pursuant thereto shall be liable to the city for any expense, including but not limited to costs for response, remediation and emergency services or any other loss or damage suffered by the city by reason of such violation.

i. Service. Unless otherwise provided in this section, service of any notice or order required by this section may be made either personally or by mail.

j. Issuance. Officers and employees of the department of environmental protection and of other city agencies designated by the commissioner of environmental protection shall have the power to issue summonses, appearance tickets, orders and notices of violation based upon violations of this chapter or rules of the department promulgated hereunder.

k. Entry and inspection. An authorized representative of the department of environmental protection may enter on any property, consistent with applicable law and in accordance with rules of the department related to such entry and inspection, to inspect for compliance with this chapter and rules of the department promulgated hereunder.

(Am. L.L. 2017/097, 5/30/2017, eff. 6/29/2017)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2008/035.

§ 24-525. Permits

Open this section

In all cases where provision is made by law that the consent of the commissioner shall be obtained to authorize any act to be done, he or she may grant a permit therefor, subject to the restrictions of all laws in relation thereto. Upon granting any such permit, he or she may exact such cash deposit or bond, or both, as he or she may deem necessary to safeguard the interests of the city.

§ 24-526. Conveyance of storm water from developments and lots and certain adjacent paved areas to off-site disposal points

Open this section

(a) Definitions. As used in this section:

(1) "Building combined sewer" means a building sewer intended to convey all types of wastewater, subject to certain restrictions;

(2) "Building sewer" means a sewer consisting of the part of the horizontal piping of a drainage system that extends from the end of a building house drain, as defined in section P100.00 of reference standard RS-16 of this code, to a street sewer or to another point of disposal. Building combined sewers and building storm sewers are types of building sewers;

(3) "Building storm sewer" means the part of the horizontal piping of a storm water drainage system that extends from a building house storm drain, as defined in section P100.00 of reference standard RS-16 of this code, to a street storm sewer, a street combined sewer or another point of disposal;

(4) "Catch basin" means a storm sewer inlet connected to a storm sewer or a combined sewer;

(5) "Development" means a tract of land which has been subdivided into two or more lots, whether or not such tract has been developed as by the installation of any utilities or the construction of any streets or buildings or other structures;

(6) "Lot" means a portion or parcel of land considered as a unit; a zoning lot;

(7) "Owner" means a person in whom legal or equitable title to property or premises is vested, a mortgagee or vendee in possession of premises, as assignee of rents, a receiver of premises, or a person listed as owner or agent for an owner on the records as to real property ownership maintained by the bureau of city collections of the department of finance unless such person establishes that such records are erroneous or, if claiming that he or she is an agent of the owner, furnishes the identity of the owner;

(8) "Person" means a natural person, company, partnership, corporation, association, governmental body or other legal entity, including any individual or entity acting in a representative capacity;

(9) "Private" means not public;

(10) "Public" means owned by the city and intended for use by the public, subject to restrictions which the city or agencies thereof may impose;

(11) "Storm water" means rainwater or surface water;

(12) "Street combined sewer" means a street sewer which is intended to receive the discharge of all types of wastewater, subject to certain restrictions, from one or more building sewers and catch basins and to convey such wastewater to an intercepting sewer, a private sewage disposal system or some other point of disposal;

(13) "Street sewer" means a sewer located in the bed of a street or elsewhere which is intended to receive the discharge of all or certain types of wastewater from one or more building sewers and, in some cases, from catch basins, and to convey such wastewater to points of disposal. Street combined sewers and street storm sewers are types of street sewers;

(14) "Street storm sewer" means a street sewer which is intended to receive the discharge of storm water from one or more building storm sewers and catch basins and to convey such storm water to a point of disposal; and

(15) "Tidal creek" means any creek where the level of water rises and falls with tidal action, or would do so if not impeded by artificial structures including but not limited to tide gates.

(b) Required conveyance of storm water for off-site disposal when public sewers into which discharge is feasible are located within five hundred feet of property. If the commissioner determines that a public street storm sewer or a public street combined sewer is located within five hundred feet, measured along a street, alley or right-of-way, from any point on the boundary of a development or of a lot which is not within a development into which it would be feasible, as described in subdivision (g) of this section, to discharge storm water from such development or lot:

(1) An owner of a lot within such a development or of such a lot not within a development, who is constructing or causing to be constructed on such a lot a single one-family or two-family detached or semidetached building, may dispose of the storm water falling or coming to rest within such lot which is required, by paragraph two of subdivision (b) of section P110.2 of reference standard RS-16 of this code, to be conveyed to a boundary of such lot abutting a street for off-site disposal, by causing such storm water to be discharged through an under-the-sidewalk drain or across a sidewalk onto a paved street improved in accordance with the requirements of the department of transportation and containing curbs; provided that catch basins adequate to receive such storm water are located, or are installed in accordance with the requirements of this code and of the department, within five hundred feet from the farthest point of storm water discharge onto such street; provided further that the commissioner determines that such means of storm water disposal is feasible, as described in subdivision (g) of this section, and also provided that the commissioner of buildings agrees with such determination.

(2) An owner of a lot within such a development or of such a lot not within a development who is constructing or causing to be constructed a building on such lot shall dispose of the storm water falling or coming to rest on such lot which is required, by paragraph three of subdivision (b) of section P110.2 of reference standard RS-16 of this code, to be conveyed to a boundary of such lot abutting a street for off-site disposal, except as provided in paragraph one of this subdivision, by conveying such storm water, together with all storm water falling or coming to rest on all streets and other paved areas outside of such lot constructed or altered in connection with the construction of such building for the primary purpose of improving vehicular or pedestrian access thereto, by sewers, constructed in accordance with requirements in subdivision (e) of this section and elsewhere in this code and of the department, to such public sewer; provided that no sewage shall be discharged into any such public street storm sewer. If installation of a controlled flow storm water system, in accordance with the requirements of section P110.6 of this reference standard, is necessary to make it feasible to discharge such storm water into such public sewer, the owner of the lot shall install such a system.

(c) Required conveyance of storm water for off-site disposal, prior to January first, nineteen hundred ninety-four, when no public sewers into which discharge is feasible are located within five hundred feet of property. The requirements set forth in this subdivision shall apply to the construction of all new buildings for which new building permits have been filed prior to January first, nineteen hundred ninety-four. If the commissioner determines that no public street storm sewer or public street combined sewer is located within five hundred feet, measured along a street, alley or right-of-way, from any point on the boundary of a development or of a lot not contained in a development into which it would be feasible to discharge storm water from such development or such lot:

(1) An owner of a lot within such a development or of such a lot not within a development who is constructing or causing to be constructed on such lot a one-family, two-family or three-family building, where more than thirty percent of the area being developed, exclusive of streets, shall have no structures and shall be unpaved, but which area may have not more than twenty percent of the floor area of all the structures in the development devoted to nonresidential uses, may dispose of all or some of the storm water falling or coming to rest on such lot which, pursuant to paragraph three of subdivision (c) of section P110.2 of reference standard RS-16 of this code, is conveyed to a boundary of the lot abutting a street, by discharging such storm water through an under-the-sidewalk drain or across a sidewalk onto a paved street improved in accordance with the requirements of the department of transportation and containing curbs, provided that:

(A) such person provides for the installation of all street storm sewers or street combined sewers and catch basins, constructed in accordance with the requirements in subdivision (e) of this section and elsewhere in this code and of the department, such that a catch basin adequate to receive such storm water, together with all storm water falling or coming to rest on all streets and other paved areas outside of such lot constructed or altered in connection with the construction of such building for the primary purpose of improving vehicular or pedestrian access thereto, shall be located within five hundred feet from the farthest point of storm water discharge onto such street, and such that the street storm sewers or street combined sewers extend from such catch basin to a point of disposal described in paragraph three of this subdivision; the requirements of this subparagraph shall not apply if private catch basins and sewers meeting all the requirements of this subparagraph are already present; and

(B) the commissioner determines that such means of storm sewer disposal is feasible, as described in subdivision (g) of this section, and the commissioner of buildings agrees with such determination.

(2) An owner of a development which shall only contain buildings described in paragraph four of subdivision (c) of section P110.2 of reference standard RS-16 of this code who conveys storm water falling or coming to rest within such development to a boundary of such development, pursuant to such paragraph, or an owner of a lot, whether or not within a development, who is constructing or causing to be constructed on such lot a new building and who is required to convey storm water falling or coming to rest within such lot to a boundary of such lot abutting a street, pursuant to paragraph five of subdivision (c) of section P110.2 of reference standard RS-16 of this code, shall convey such storm water, together with storm water falling or coming to rest on all streets and other paved areas outside of such development or lot which are constructed or altered in connection with the construction of such buildings or building for the primary purpose of improving vehicular or pedestrian access thereto, from such boundary by sewers, constructed in accordance with the requirements in subdivision (e) of this section and elsewhere in this code and of the department, to a point of disposal described in paragraph three of this subdivision.

(3) Points of disposal for storm water disposed of pursuant to this subdivision are:

(A) the New York Harbor, or a point on a tidal creek acceptable to the commissioner as an adequate storm water outlet; provided that only building storm sewers and, if necessary, street storm sewers are constructed and that no sewage is discharged at such a point of disposal; and provided that such outlets shall only be used in compliance with applicable provisions of law;

(B) a public street storm sewer or public street combined sewer, regardless of its distance from the property, to which the commissioner determines that conveyance of storm water is feasible, as described in subdivision (g) of this section, provided that no sewage shall be discharged into a street storm sewer; or

(C) an existing private street storm sewer or private street combined sewer to which the commissioner determines that conveyance of storm water is feasible, as described in subdivision (g) of this section; provided that such street sewer connects with a public street sewer or, if it is a private storm sewer, discharges directly into the New York harbor, or into a point on a tidal creek acceptable to the commissioner as an adequate storm water outlet, in accordance with applicable provisions of law; and provided further that no sewage shall be discharged into a street storm sewer.

(d) Required conveyance of storm water for off-site disposal, on or after January first, nineteen hundred ninety-four, when no public sewers into which discharge is feasible are located within five hundred feet of property. The requirements set forth in this subdivision shall apply to the construction of all new buildings for which new building permits have been filed on or after January first, nineteen hundred ninety-four. If the commissioner determines that no public street storm sewer or public street combined sewer is located within five hundred feet, measured along a street, alley or right-of-way, from any point on the boundary of a development or of a lot not contained in a development into which it would be feasible to discharge storm water from such development or such lot, an owner of a lot within such a development or of such a lot not within a development who is constructing or causing to be constructed a building on such lot shall dispose of storm water falling or coming to rest within such lot, together with storm water falling or coming to rest on all streets and other paved areas outside of such lot which are constructed or altered in connection with the construction of such building for the primary purpose of improving vehicular or pedestrian access thereto, by means acceptable to the commissioner and the commissioner of buildings, including but not limited to those set forth in section P110.13 of this reference standard; provided, however, that such persons shall not be required to construct street storm sewers or street combined sewers for distances greater than seven hundred fifty feet.

(e) Maximum required capacity for street storm sewers or street combined sewers required by this section. The commissioner may require an owner of a lot or a development who is required by this section to construct street storm sewers or street combined sewers to construct such sewers with a capacity not to exceed twenty-five percent above and beyond the capacity which the commissioner determines is needed for the disposal of storm water falling or coming to rest on such property together with storm water falling or coming to rest on all streets and other paved areas outside of such property which are constructed or altered in connection with the construction of a building or buildings on such property for the primary purpose of improving vehicular or pedestrian access thereto. The department reserves the right to construct catch basins connected to such sewers at the cost and expense of the city, to alleviate flooding or ponding conditions, provided that the commissioner determines that the capacity of such sewers shall not be exceeded.

(f) Repair of defects in catch basins and sewers required. Any owner of property who causes any catch basin or any sewer which shall lie outside of such property to be constructed pursuant to subdivision (b), (c) or (d) of this section shall cause all defects in such catch basin or sewer and all faults in its installation to be repaired for a period of two years after it has been installed, immediately after the department orders such person to do so.

(g) Feasibility of discharging storm water into a street storm sewer or a street combined sewer. The commissioner shall determine that the discharge of storm water into a street storm sewer or a street combined sewer pursuant to this section is feasible if he or she finds that:

(1) the sewer is of adequate capacity to receive all such storm water or would be adequate to receive it if the owner of property installed controlled flow storm water systems, in accordance with the requirements of section P110.6 of reference standard RS-16 of this code, to restrict the maximum anticipated storm water flow to a level set by the commissioner;

(2) the sewer is in adequate physical condition to receive such storm water;

(3) no physical obstacle which would make conveyance of such storm water to the sewer impracticable exists between the sewer and the boundaries of the development or lot from which such storm water shall be discharged;

(4) conveyance of such storm water to the sewer is not impracticable because of the elevation of the sewer in relation to the development or lot from which such storm water shall be discharged;

(5) the sewer is located in the same drainage area as all or most of the development or lot from which such storm water shall be discharged; and

(6) no other factor reasonably related to the conveyance of such storm water from such development or lot to the sewer would make the discharge of such storm water into the sewer impracticable or undesirable as a proper means of storm water disposal.

(h) Time by which construction of the part of the storm water drainage system required by this section shall be completed. The part of the storm water drainage system for property required by this section shall be completed prior to the issuance of a certificate of occupancy by the department of buildings for, and actual occupancy of, the building in connection with which such storm water drainage system is being constructed.

(i) Performance bond, license and insurance required. If an owner of property is required to construct or repair defects in catch basins or sewers which shall lie outside of such property, in connection with the construction of a new building pursuant to this section, he or she shall provide the department with:

(1) a performance bond or other security satisfactory to the department and approved as to form by the law department of the city for the full cost, as estimated by the department, of performing all such construction and repair work;

(2) any license or other written instrument which the commissioner or the law department of the city may reasonably request which gives the department, its agents and contractors and the surety for a performance bond described in paragraph one of this subdivision the legal right to enter private property to perform such construction and repair work, pursuant to the terms of the performance bond or in accordance with the conditions of acceptance of other security described in paragraph one of this subdivision, and the legal right to connect to, to extend or to discharge storm water into any private sewer authorized as a point of disposal pursuant to paragraph three of subdivision (c) of this section, in the event that the owner of property fails to do so as required by this section; and

(3) insurance of a kind and in an amount which the commissioner and the law department of the city deem satisfactory to insure the city fully for all risks of loss, damage to property or injury to or death of persons to whomever occurring arising out of or in connection with the performance of such sewer construction and repair work.

(j) Contractual obligations of the city not abrogated. The provisions of this section shall not be construed to abrogate or contravene any contractual obligation of the city to construct storm water drainage systems or parts thereof. The requirements of subdivisions (b), (c), (d), (f) and (i) of this section shall be inapplicable to an owner of property insofar as they relate to any construction work required to be performed by the city pursuant to such a contractual obligation.

(k) Determination by the board of standards and appeals. Any determination made by the board of standards and appeals with reference to the disposal of storm water, pursuant to the provisions of section 27-160 and section P110.2 of reference standard RS-16 of this code, shall be binding upon the department for the purposes of the enforcement and administration of this section.

§ 24-526.1. Sustainable stormwater management. [Repealed]

Open this section

(Am. L.L. 2023/069, 5/29/2023, eff. 6/28/2023; repealed L.L. 2025/070, 5/24/2025, eff. 5/24/2025)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2008/005.

§ 24-527. Watershed protection plan for the watershed / sewershed of Jamaica bay

Open this section

a. No later than October 1, 2007, the commissioner shall complete a watershed protection plan for the watershed / sewershed of Jamaica bay, which shall, among other things, include measures the city can implement to help protect Jamaica bay. The overall goal of such plan shall be to restore and maintain the water quality and ecological integrity of Jamaica bay.

b. The commissioner shall assess the technical, legal, environmental and economical feasibility of including the following measures, at minimum, in the plan prepared pursuant to subdivision a of this section:

(1) best management practices for the minimization and control of soil erosion and stormwater runoff and reduction of both point and non-point source pollution, including, but not limited to, the promotion of development practices such as the on-site detention and infiltration of stormwater runoff, the minimization of impervious surfaces and the creation of natural systems to control and minimize stormwater runoff;

(2) measures to address threats to aquatic habitat, including, but not limited to, stabilizing and restoring salt marshes, wetlands, soils and other natural areas, strengthening ecological buffers, restoring natural features to the Jamaica bay watershed / sewershed shoreline, and reestablishing water flows;

(3) land acquisition and land use planning practices and opportunities, including, but not limited to, incentives, such as expedited permitting and property tax relief, for infill, brownfield redevelopment and other environmentally beneficial development, and disincentives, such as stricter development guidelines, for development that may adversely impact Jamaica bay;

(4) a protocol for coordination with appropriate federal, state and city governmental entities that have jurisdiction over the Jamaica bay area, with respect to, but not limited to, efforts to restore and maintain the water quality and ecological integrity of Jamaica bay and notification regarding proposed development projects within the Jamaica bay watershed / sewershed that may adversely impact Jamaica bay;

(5) a protocol for coordination with the office of operations that ensures that environmental assessments and reviews of projects within the Jamaica bay watershed / sewershed address potential impacts to Jamaica bay and are conducted pursuant to all applicable federal, state and city environmental quality review laws and regulations;

(6) a public education program, including, but not limited to, programs for schools, developers, commercial facilities, civic groups and other local organizations and entities to increase awareness about the ecological significance and degradation of Jamaica bay; potential threats to Jamaica bay; restoration and watershed stewardship activities undertaken by the department and others involving Jamaica bay; and methods and practices to reduce pollution in Jamaica bay; and

(7) a program to target enforcement efforts that will help reduce polluting behaviors and operations that may adversely impact Jamaica bay.

c. The watershed protection plan prepared pursuant to subdivision a of this section, as it may be revised pursuant to subdivision h of this section, shall contain the following:

(1) specific goals related to restoring and maintaining the water quality and ecological integrity of Jamaica bay;

(2) the geographic boundaries of the watershed / sewershed of Jamaica bay for the purpose of achieving the goals of such plan and an explanation for the selection of such boundaries;

(3) the assessments the commissioner completed for each measure considered for inclusion in such plan;

(4) for any final recommendation of the Jamaica bay watershed protection plan advisory committee established pursuant to subdivision j of this section that was not assessed for inclusion or incorporated in such plan, an explanation for such omission; and

(5) a schedule, including interim and final milestones, for implementing the measures and achieving the specific goals included in such plan and methods of monitoring progress towards achieving such milestones and goals.

d. No later than October 1, 2006, the commissioner shall complete an interim report on the preparation of the watershed protection plan required pursuant to subdivision a of this section, which shall include, at minimum, the following elements:

(1) a description of the current status of the plan preparation, including, but not limited to, the status of all feasibility assessments of measures conducted pursuant to subdivision b of this section; and

(2) for each preliminary recommendation of the Jamaica bay watershed protection plan advisory committee provided to the commissioner pursuant to paragraph four of subdivision j of this section, the commissioner shall state whether:

i. the recommendation will be incorporated into the plan required pursuant to subdivision a of this section;

ii. the recommendation will not be incorporated into such plan, in which case the commissioner shall provide a detailed explanation of the basis for any such omission; or

iii. the recommendation will be further assessed for inclusion in such plan, in which case the commissioner shall provide a detailed explanation of the reason for such further assessment, including a timeline for such assessment's completion.

e. No later than March 1, 2007, the commissioner shall complete a draft of the watershed protection plan for the watershed / sewershed of Jamaica bay required pursuant to subdivision a of this section.

f. The commissioner shall implement the plan prepared pursuant to subdivision a of this section, as it may from time to time be revised pursuant to subdivision h of this section, in accordance with its provisions.

g. The commissioner shall submit to the mayor and the speaker of the council the watershed protection plan, draft of such plan and interim report prepared pursuant to subdivisions a, d and e of this section, or any revised plan prepared pursuant to subdivision h of this section, no later than five business days after its completion.

h. The watershed protection plan prepared pursuant to subdivision a of this section shall be reviewed and revised as necessary to achieve its goals, but in no event shall such review occur less often than once every two years.

i. No later than October 1, 2008, and no later than October 1 of every second year thereafter, the commissioner shall submit a report to the mayor and the speaker of the council, which shall include, but not be limited to:

(1) the implementation status of the measures included in the watershed protection plan prepared pursuant to subdivision a of this section, as it may have been revised pursuant to subdivision h of this section; and

(2) where the plan has been reviewed in accordance with subdivision h of this section and the commissioner determines that no revisions are required, such determination and the reasons for it.

j. (1) A Jamaica bay watershed protection plan advisory committee shall be established, which shall provide advice to the commissioner for the duration of its term and provide preliminary and final recommendations to the commissioner and the speaker of the council on the watershed protection plan required pursuant to subdivision a of this section regarding:

i. the specific goals of such plan related to restoring and maintaining the water quality and ecological integrity of Jamaica bay;

ii. the geographic boundaries of the watershed / sewershed of Jamaica bay to be included in such plan;

iii. any measures that should be assessed by the commissioner for inclusion in such plan, in addition to those listed in subdivision b of this section;

iv. the assessment of the technical, legal, environmental and economical feasibility of including in such plan the measures listed in subdivision b of this section and any additional measures; and

v. a schedule, including interim and final milestones, for implementing the measures and achieving the specific goals to be included in such plan and methods of monitoring progress towards achieving such milestones and goals.

(2) Such advisory committee shall be comprised of seven members, three of whom shall be appointed by the speaker of the council and four by the mayor. The members shall be appointed within forty-five days after the effective date of this section and shall serve without compensation. The chairperson(s) shall be elected from amongst the members. Any vacancy shall be filled in the same manner as the original appointment for the remainder of the unexpired term. The commissioner may provide staff to assist the advisory committee.

(3) Such members of the advisory committee shall serve until three months after the date upon which the commissioner completes the watershed protection plan prepared pursuant to subdivision a of this section, after which time the committee shall cease to exist.

(4) No later than July 1, 2006, the chairperson(s) of such committee shall submit a report containing the committee's preliminary recommendations regarding the watershed protection plan required pursuant to subdivision a of this section to the commissioner and the speaker of the council.

(5) No later than June 1, 2007, the chairperson(s) of such committee shall submit a report containing the committee's final recommendations regarding the watershed protection plan required pursuant to subdivision a of this section to the commissioner and the speaker of the council.

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2005/071 and L.L. 2008/017.

§ 24-527.1. New York City Jamaica Bay task force

Open this section

a. As used in this section the term "Jamaica Bay clean-up and resiliency project" means the cleanup of marine debris, management of combined sewer overflows and storm flows for the bay consistent with the Jamaica Bay watershed protection plan and taking into account the impacts of sea level rise.

b. There shall be a Jamaica Bay task force, which, during its term, shall provide advice and recommendations in a biannual report to the city with respect to the Jamaica bay clean-up and resiliency project. Such report shall be transmitted to the mayor, the speaker of the city council, the Jamaica Bay Science and Resilience Institute and other relevant entities in a form and manner to be determined by such task force.

c. The task force shall provide advice and recommendations on matters relating to or impacting the ongoing Jamaica Bay clean-up and resiliency project including but not limited to:

1. Review of measures proposed to restore and maintain the water quality and ecological integrity of the bay; and

2. Analysis of the impacts of sea-level rise on Jamaica Bay and the surrounding watershed including the underground aquifer and groundwater service area.

d. The task force shall be comprised of eleven members, five of whom will be appointed by the speaker of the council and six members by the mayor. The members shall include a representative from each community board in the Jamaica Bay Watershed as well as at least two representatives from the communities that adjoin Jamaica Bay. The members shall also include persons with relevant expertise and experience in the fields of hydrology, biology, geology and oceanography. Members shall be appointed within 180 days after the effective date of this section and shall serve without compensation. A chairperson shall be elected from amongst the members. Members shall serve five-year terms. Any vacancy shall be filled in the same manner as the original appointment for the remainder of the unexpired term. The commissioner may provide administrative assistance to the task force.

(L.L. 2018/179, 10/27/2018, eff. 10/27/2018)

§ 24-528. New York city comprehensive wetlands study and protection strategy

Open this section

a. Definitions.

1. "City" shall mean the geographic area constituting the city of New York, including wetlands, shorelines and underwater lands.

2. "Office" shall mean the mayor's office of long-term planning and sustainability.

3. "Wetlands" shall mean those areas that are inundated or saturated by surface or ground water at a frequency and duration sufficient to support, and that under normal circumstances do support, a prevalence of vegetation typically adapted for life in saturated soil conditions. Wetlands generally include swamps, marshes, bogs and similar areas.

b. Preliminary satellite or aerial imagery survey. No later than September 1, 2010, the office shall submit to the mayor and the speaker of the council a preliminary survey of likely wetland areas based upon satellite or aerial imagery. The preliminary satellite or aerial imagery survey shall be for the purpose of indicating the overall size and location of remaining wetlands within the city and therefore to inform the development of an overall strategy for wetlands in the city.

c. Development of a comprehensive wetlands strategy. The office shall complete a preliminary wetlands protection strategy the overall goals of which shall be to (1) conserve, protect, enhance, stabilize, restore and expand wetlands and associated buffer areas in the city; (2) avoid and minimize wetlands losses and achieve no net loss of wetlands in the city; (3) standardize and improve the management of wetlands and associated buffer areas and (4) balance the needs for wetlands protection with other, competing land uses that are in the public interest, such as the construction of schools or affordable housing. Such strategy shall consider (1) the ecological, hydrological, economic, aesthetic and habitat functions of wetlands including, but not limited to future protection from storm surges and other effects of rising sea levels; (2) the current condition and protections afforded wetlands in the city, including wetlands smaller than 12.4 acres in size; and (3) the wetlands policies, laws, rules and regulations that have been adopted by other municipalities in New York state.

d. (1) No later than December 31, 2011, the office shall submit a preliminary comprehensive wetlands protection strategy that meets the requirements of this subdivision to the mayor, the speaker of the council and the public for review and comment. Access to the public shall include posting such preliminary strategy on the city's website and such other measures as the office deems appropriate to increase notice.

(2) No later than March 1, 2012, the office shall submit a final comprehensive wetlands protection strategy that meets the requirements of this subdivision to the mayor, the speaker of the council and the public. Submission to the public may include posting such final strategy on the city's website and such other measures as the office deems appropriate to increase notice.

(3) The comprehensive wetlands protection strategy shall include, but not be limited to, the following:

(i) appropriate legal requirements, management mechanisms, funding mechanisms, enforcement mechanisms and incentives to conserve, protect, enhance, restore, stabilize and expand wetlands and associated buffer areas in the city, whether publicly or privately owned;

(ii) appropriate legal requirements, management mechanisms, funding mechanisms, enforcement mechanisms and incentives regarding management of wetlands in the city by public and private owners to ensure their consistency and best practices;

(iii) land acquisition and land use planning practices and opportunities to provide for wetlands retreat;

(iv) strategies for adaptation to sea level rise that involve wetlands to the extent not provided for in any other planning or management initiatives undertaken by or on behalf of the city;

(v) opportunities to improve the implementation of wetlands mitigation and creation activities;

(vi) a protocol for coordination with appropriate federal, state and city governmental entities that have jurisdiction over or other property interest in wetlands or associated buffer areas including, but not limited to, coordination in the development of a comprehensive list of wetland mitigation opportunities and notification procedures regarding proposed development projects that may adversely impact wetlands or associated buffer areas;

(vii) reporting mechanisms for wetlands indicators; and

(viii) a public education program to increase awareness about the ecological, economic, aesthetic and other values of wetlands and their associated buffer areas, which shall include information presented on the city's website and such other means as the office deems appropriate.

(4) The comprehensive wetlands protection strategy shall include a schedule and milestones for implementing the strategy and achieving its goals.

(5) To the extent that any element of the comprehensive wetlands protection strategy is provided for in any other planning or management initiative undertaken by or on behalf of the city, such element may be incorporated by reference.

e. The comprehensive wetlands protection strategy developed pursuant to this section shall be reviewed and revised as necessary to achieve its goals, the first such review to be undertaken within three years and thereafter no less often than every four years. No later than April 22, 2015 and no later than every fourth year thereafter, the commissioner shall submit a report to the mayor and the speaker of the council that provides an update on the comprehensive wetlands protection strategy developed pursuant to this section which shall include, but not be limited to:

(1) the implementation status of the measures included in such strategy, as it may have been revised pursuant to this subdivision; and

(2) specific progress towards each of the strategy's goals.

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2009/031.

§ 24-529. Car wash, standards

Open this section

a. Definitions. For purposes of this section:

Applicant. The term "applicant" means any individual, partnership, corporation, limited liability company, joint venture, association or other business entity that seeks a license or renewal of a license to engage in the operation of a car wash.

Car wash. The term "car wash" means any individual, partnership, corporation, limited liability company, joint venture, association, or other business entity that engages in the cleaning of vehicles, including washing, detailing, drying, polishing, vacuuming or otherwise providing cosmetic care to vehicles. "Car wash" shall not include:

1. any business entity that is engaged in selling, leasing, renting or repairing motor vehicles, where car washing is ancillary to the primary business of such entity;

2. any self-service facility for washing vehicles, where the facility's employees do not provide assistance to customers in the cleaning of vehicles, such as washing, detailing, drying, polishing, vacuuming or otherwise providing cosmetic care to vehicles, including businesses such as convenience stores, gas stations and oil change facilities, where car washing is ancillary to the primary business of the facility;

3. any person that engages in the cleaning of vehicles on an intermittent basis to raise funds for a not-for-profit organization; or

4. any federal, state or local governmental agency.

b. Prior to filing an application for a license or renewal of a license to operate a car wash pursuant to subchapter 33 of chapter 2 of title 20 of this code, an applicant shall certify to the commissioner that the following information, in a form and method prescribed by the commissioner, will be maintained by the applicant at its principal place of business for a minimum of three years, and such information shall be made available to the department or the department of consumer and worker protection upon request:

1. The source from which the applicant draws or will draw its water, whether from the public water supply, well water or other source;

2. For renewal applicants, the amount of water drawn from public sources each month since the applicant last filed an application;

3. Construction drawings and as-built plans, meaning the final set of drawings produced at the completion of construction, of any oil/water separator system or sand interceptor, attesting to the volume of the system and to the maximum flow of wastewater that the system can filter and otherwise clarify efficiently;

4. Written certification that the applicant has regularly removed, in accordance with the respective manufacturer's specifications, oil, sediment and other residues that may be regulated by the commissioner pursuant to department rules regarding sewer use from its oil/water separator system and sand interceptor, as well as the method or methods used to remove and dispose of such oil, sediment and other residues, and for renewal applicants, the frequency of such removal and disposal since the applicant last filed an application;

5. Written certification that the applicant has complied with the rules of the department regarding testing and reporting with respect to all backflow prevention devices;

6. A logbook of monitoring and inspection results and repair and maintenance activities with regard to oil/water separators, sand interceptors and other pretreatment devices or systems, and backflow prevention devices, since the applicant last filed an application, provided that an applicant for a new car wash shall begin maintaining such information between sixty and ninety days of commencement of operations after receiving a license from the department of consumer and worker protection pursuant to section 20-541 of this code; and

7. Material safety data sheets or safety data sheets that indicate the chemicals used in the operation of the car wash, where such material safety data sheets or safety data sheets are required by federal, state or local law, rule or regulation.

(L.L. 2015/062, 6/29/2015, eff. 12/26/201; Am. L.L. 2020/080, 8/28/2020, eff. 8/28/2020)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2015/062 and L.L. 2020/080.

§ 24-530. Southeast Queens flood mitigation plan

Open this section

a. By no later than one year after the effective date of the local law that added this section, the department of environmental protection shall submit to the mayor and speaker of the council, and make publicly available online, a plan for mitigating flooding in Queens community districts 12 and 13. Such plan shall include, but not be limited to, a timeline for implementation of the plan, annual performance milestones and a description of funds anticipated to be expended by or on behalf of the city in connection with such flood mitigation, including, but not limited to, funds committed in fiscal year 2016 for such purposes.

b. By no later than 6 months after the end of each fiscal year, beginning with the first fiscal year that commences more than 1 year after the effective date of the local law that added this section, the department of environmental protection shall submit to the mayor and the speaker of the council a report on progress in implementing the plan required by subdivision a of this section during the prior fiscal year. Each such report shall include, but not be limited to, a description of any changes to such plan, a description of any changes in funds committed by or on behalf of the city in furtherance of such plan, a description of all funds expended by or on behalf of the city in furtherance of such plan, and an update on progress made in any studies in which the department of environmental protection is participating related to groundwater levels and flooding in Queens community districts 12 and 13.

c. This section expires 15 years after the effective date of the local law that added this section.

(L.L. 2017/056, 3/21/2017, eff. 3/21/2017; Am. L.L. 2025/087, 6/27/2025, eff. 12/24/2025)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2025/087.

§ 24-530.1. Southeast Queens flooding adaptation assistance task force

Open this section

a. Definitions. For purposes of this section, the term “southeast Queens” means Queens community districts 8, 10, 12, and 13.

b. There shall be an interagency task force to recommend changes to the laws, regulations, and policies that could facilitate the implementation of measures to mitigate vulnerability to flooding of real property in southeast Queens.

c. The task force shall consist of the following members:

1. The commissioner of buildings, or such commissioner’s designee;

2. The commissioner of environmental protection, or such commissioner’s designee;

3. The commissioner of housing preservation and development, or such commissioner’s designee;

4. One member appointed by the public advocate; and

5. Three members appointed by the speaker of the council.

d. The chair of such task force shall be the commissioner of environmental protection or such commissioner’s designee.

e The task force shall invite representatives from relevant city and state agencies, elected officials and advocacy organizations, as identified by the task force, to provide feedback on measures that mitigate vulnerability to flooding of real property in southeast Queens.

f. All members of the task force appointed by the public advocate and by the speaker of the council shall be appointed within 60 days of the effective date of the local law that added this section. Such members shall serve without compensation, except that each such member shall be allowed actual and necessary expenses to be audited in the same manner as other city expenses. Any vacancy shall be filled in the same manner as the original appointment.

g. The task force shall meet at least 2 times per year and shall convene an annual public hearing in southeast Queens.

h. No later than 1 year after the appointment of the final member of the task force, and annually thereafter, the task force shall issue a report to the mayor and the speaker of the council detailing its activities and recommendations, which shall be made publicly available on the department of environmental protection’s website.

(L.L. 2025/087, 6/27/2025, eff. 12/24/2025)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2025/087.

§ 24-531. Wastewater testing program

Open this section

a. Definitions. For the purposes of this section, the following terms have the following meanings:

PCR using N1 Primer. The term "PCR using N1 Primer" means the measurement of the copies of the targeted viral RNA segment in a wastewater sample using a polymerase chain reaction based method.

SARS-CoV-2. The term "SARS-CoV-2" means severe acute respiratory syndrome coronavirus 2, which is the strain of coronavirus that causes the disease COVID-19.

Wastewater-based epidemiology. The term "wastewater-based epidemiology" means the chemical analysis of pollutants, viruses and biomarkers in raw wastewater to obtain qualitative and quantitative data on disease activity among inhabitants within a given wastewater catchment.

b. The commissioner, in consultation with the commissioner of health and mental hygiene, shall establish a pilot sampling program to quantify the levels of SARS-CoV-2 RNA in sewage at each city wastewater treatment plant in accordance with this section. Such sampling program shall occur on a frequency of no less than twice per week and shall include, but not be limited to, the measurement of the number of copies of SARS-CoV-2 RNA through the PCR using N1 Primer testing method or another testing method that reflects industry best practices.

c. The duration of such pilot sampling program shall be no less than six months and the commissioner, in consultation with the commissioner of health and mental hygiene, shall collect sewage samples in an amount necessary to measure the copies of SARS-CoV-2 RNA.

d. No later than January 31, 2022, the commissioner shall submit to the mayor and speaker of the council a report, which shall include, but not be limited to the following:

1. Results of sampling, disaggregated by the site where the sample was collected, date sample was collected, and date sample was tested, in order to monitor the leading indicators of increases or decreases in COVID-19 presence in each drainage area throughout the study;

2. The total cost of such pilot program;

3. Analysis of the effectiveness of the pilot program in testing for SARS-CoV-2;

4. Recommendations to expand the pilot program to include sampling at manhole sites and pumping stations if wastewater-based epidemiology detects SARS-CoV-2 in an amount, as determined by the commissioner of health and mental hygiene, that indicates a localized concentration of COVID-19;

5. Recommendations to extend the pilot program for up to an additional six months if more testing is necessary, as determined by the commissioner, in consultation with the commissioner of health and mental hygiene;

6. A plan for weekly testing at each city wastewater treatment plant if the commissioner of health and mental hygiene or state commissioner of health declares that the incidence of SARS-CoV-2 is appropriate for such action or if the centers for disease control and prevention issues a SARS-CoV-2 pandemic declaration;

7. Recommendations to use a sequencing testing method other than PCR using N1 Primer to test samples, if the commissioner determines that such additional testing method is beneficial; and

8. Recommendations for making the pilot program permanent.

e. The information required by paragraph 1 of subdivision d of this section shall be maintained on the website of the city.

(L.L. 2021/028, 3/14/2021, eff. 3/14/2021)

§ 24-532. Backwater valves

Open this section

a. Backwater valve study and report. Not later than December 1, 2024, the department, or an agency or office headed by a mayoral appointee, as designated by the mayor, shall complete a study evaluating the benefits of installing backwater valves, as defined in section 202 of the New York city plumbing code, for the purpose of mitigating damage caused by backflow, as defined in section 202 of the New York city plumbing code, during severe weather events. Upon the completion of the study, a report summarizing the results of the study shall be submitted to the mayor and the speaker of the council and posted on the department's website.

b. Backwater valve program. Subject to appropriation, not later than April 1, 2025, the department, or another agency or office headed by a mayoral appointee, as designated by the mayor, shall establish a program to provide financial assistance to owners of certain real property that would reduce the cost of purchasing and installing a backwater valve. Such program shall be based on the results of the study described in subdivision a of this section, provided that: (i) a program to reimburse, or provide a discount to, owners of real property for the installation of backwater valves, has not been established by the New York city water board, as described by section 1045-f of the public authorities law; and (ii) a program to provide financial assistance to owners of such real property for the installation of backwater valves, has not been established by any public entity, or any entity acting on behalf of such public entity. Such program shall, at a minimum:

1. Prioritize neighborhoods, locations, or types of real property that regularly suffer damage caused by backflow during severe weather events and for which the installation of a backwater valve would serve the greatest public purpose, as determined by the department, agency or office, as designated by the mayor; and

2. Conduct outreach and education to owners of such real property to inform such owners about the benefits of backwater valves and the responsibilities related to maintaining such valves. Such outreach and education shall be in the designated citywide languages, as defined in section 23-1101.

(L.L. 2023/001, 1/7/2023, eff. 1/7/2023)

§ 24-533. Green roof map

Open this section

a. The commissioner, in collaboration with the department of buildings, shall publish on the green infrastructure program map, or on another map on the department’s website, the location of every green roof using the best information available.

b. For each green roof indicated on such map, the map shall provide at a minimum, based on the best information available, the following information:

1. The occupancy group of the building or structure;

2. The area of the roof in square feet;

3. The area of the portion of the roof covered by the green roof system in square feet;

4. The estimated amount of water such green roof has the capacity to absorb; and

5. Any functions of the green roof, which may include, but need not be limited to, aesthetic, water retention, recreational, farming, or any other function designated by the department.

c. Definitions. For purposes of this section, the term “green roof” means a living vegetative system partially or wholly covering a roof.

(L.L. 2023/154, 11/19/2023, eff. 3/18/2024; Am. L.L. 2025/070, 5/24/2025, eff. 5/24/2025)

§ 24-534. Flooding adaptation assistance partnership program

Open this section

a. Definitions. For purposes of this section, the following terms have the following meanings:

Department. The term “department” means the department of environmental protection.

Flooding adaptation assistance. The term “flooding adaptation assistance” means measures that mitigate the risk of repetitive flood damage to real property.

Homeowner. The term “homeowner” has the same meaning as set forth in subdivision a of section 1807 of the charter.

Partner organization. The term “partner organization” means any organization providing flooding adaptation assistance programs to homeowners.

b. The department shall develop and administer a voluntary flood adaptation assistance partnership program to facilitate information sharing between the department and partner organizations. As part of such program, unless otherwise proscribed by law and pursuant to a request for information or data, the department shall share with a participating partner organization such information or data responsive to such request, including but not limited to, sewer drainage plans, water and sewer maps, sewer as-built drawings, tap and sewer cards, groundwater table levels, and any other such information responsive to such request to facilitate the administration of such partner organization’s flood adaptation assistance program.

c. The department shall prescribe by rule the criteria and process for a partner organization to apply to such partnership program, and any other requirements for participating in such program. Such requirements for participation may include, but are not limited to: the provision of certain information; or the signing of certain agreements, such as a non-disclosure agreement, before sharing certain information with any such partner organization.

d. Nothing in this section shall alter any rights or privileges under article 6 of the public officers law, and nothing in this section shall be construed as requiring the disclosure of any plan, map, drawing, or information that would not otherwise be required to be disclosed under article 6 of the public officers law.

(L.L. 2025/087, 6/27/2025, eff. 12/24/2025)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2025/087.