NYC Administrative Code Title 28, Chapter 2 Enforcement, part 3 of 3
§ 28-219.6 to § 28-220.2.3: 7 sections.
§ 28-219.6. Other remedies not precluded
Nothing in this article shall be construed to limit the power of the commissioner to take any other action authorized by this code with respect to any unlawful use or condition.
(L.L. 2022/050, 1/15/2022, eff. 5/15/2022)
§ 28-220.1. Department penalty for sidewalk sheds occupying the public right-of-way for an extended period
Beginning with the second renewal, every renewal of a permit for a sidewalk shed installed in the public right-of-way issued after the effective date of the local law that added this section shall require the building owner to conduct work to address the condition for which the sidewalk shed permit was issued, as determined in accordance with the rules of the department, during the period of time for which such renewal of the permit is issued. Where work is not in progress during such period of time, the building owner may be liable for a penalty, as determined in accordance with this section, which shall be payable prior to the renewal of such permit. Penalties shall be assessed by the department as set forth in items 1 through 3.
1. Where a sidewalk shed is in existence for less than 3 years, the penalties shall be assessed at $10 per linear foot of sidewalk shed per month in which work was not in progress during the term of such renewal.
2. Where a sidewalk shed is in existence for 3 years but less than 4 years, the penalties shall be assessed at $100 per linear foot of sidewalk shed per month in which work was not in progress during the term of such renewal.
3. Where a sidewalk shed is in existence for 4 years or more, the penalties shall be assessed at $200 per linear foot of sidewalk shed per month in which work was not in progress during the term of such renewal, provided that penalties shall not exceed $6,000 per month.
Exception: Department penalties for sidewalk sheds in the public right-of-way shall not apply to one- or two-family homes or to sidewalk sheds that are installed in connection with new building, enlargement, or demolition work for which a permit has been issued.
(L.L. 2025/048, 4/17/2025, eff. 1/12/2026)
Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2025/048.
§ 28-220.1.1. Procedure
The department shall adopt rules setting forth procedures for the assessment of penalties pursuant to this section, which shall include notice and an opportunity to be heard.
(L.L. 2025/048, 4/17/2025, eff. 1/12/2026)
Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2025/048.
§ 28-220.2. Department penalty for failing to complete facade repairs in a timely manner
In addition to any other penalties that may be imposed under any other provision of law, the owner of a building subject to the requirements of article 302 of chapter 3 of this title may be subject to a penalty where facade repairs are not commenced and completed as required by this section.
(L.L. 2025/051, 4/17/2025, eff. 1/12/2026)
§ 28-220.2.1. Assessment of penalties for failing to complete facade repairs in a timely manner
Where an initial permit for the erection of a sidewalk shed in the public right-of-way is issued on or after the effective date of the local law that added this section, penalties for failure to timely complete facade repairs shall be assessed to the building owner by the department within the ranges set forth in items 1 through 3 of this section.
1. A penalty of not less than $5,000 nor more than $20,000 shall be imposed if complete construction documents to repair the unsafe condition of the facade of such building are not filed with the department within 5 months of the issuance of an initial permit for the erection of a sidewalk shed in the public right-of-way.
2. A penalty of not less than $5,000 nor more than $20,000 shall be imposed if an owner does not file a complete permit application for the repair of an unsafe facade and fails to diligently pursue such application, including but not limited to responding to objections in a timely manner to enable the department to issue such permit within 8 months of the issuance of an initial permit for the erection of a sidewalk shed in the public right-of-way.
3. A penalty of not less than $5,000 nor more than $20,000 shall be imposed if permitted work to repair an unsafe facade is not completed within 2 years of the issuance of an initial permit for the erection of a sidewalk shed in the public right-of-way, unless the department granted an extension pursuant to section 28-220.2.2.
Exception: Department penalties for failure to complete facade repairs in a timely manner shall not apply to sidewalk sheds installed in connection with permitted new building, enlargement, or demolition work.
(L.L. 2025/051, 4/17/2025, eff. 1/12/2026)
§ 28-220.2.2. Extensions of time to complete facade repairs
Upon request by the owner of a building subject to section 28-220.2, the commissioner may grant an extension of time to commence or complete facade repairs according to the timeline in section 28-220.2.1. Such request shall be made to the commissioner in writing, in a form and manner and within such period of time, as determined by the department. Such request shall toll the timeline in section 28-220.2.1 until a decision on such request is made. Such request shall include documentation explaining why such timelines cannot be met, and a contract indicating the scope of repairs and a timeline to complete those repairs. Upon submission of a contract indicating a timeline greater than 2 years, the owner may apply for a single extension, the duration of which shall be determined by the department based on factors such as the size of the building, the scope of necessary work, and the materials necessary to complete such work. The penalties outlined in section 28-220.2.1 may be imposed where facade repairs are not completed within such timeline. The department may charge a fee, to be determined by the department by rule, for each extension request submitted to the department.
(L.L. 2025/051, 4/17/2025, eff. 1/12/2026)
§ 28-220.2.3. Procedure
The department shall adopt rules setting forth procedures for the assessment of penalties pursuant to this section, which shall include notice and an opportunity to be heard.
(L.L. 2025/051, 4/17/2025, eff. 1/12/2026)