§ 4-32. Siting Requirements
(a) General provisions.
(1) All transfer stations and intermodal solid waste container facilities shall be sited in accordance with the applicable provisions of the Zoning Resolution or as authorized by a variance granted by the New York City Board of Standards and Appeals.
(2) All buffer distance requirements specified in subdivision (b) of this section shall be measured from the boundary of the residential district, the property lines of a hospital, public park, school, or the site boundaries of another solid waste transfer station, to the site boundary of the transfer station, or if the building within which the dumping, loading, processing and storage of solid waste takes place is set back at least one hundred fifty feet from the site boundary, from the building.
(3) In addition to complying with the provisions of this subchapter, every person who owns, operates, maintains or otherwise controls a non-putrescible solid waste transfer station or a putrescible solid waste transfer station shall comply with the provisions in Subchapters A and B of this chapter, as applicable.
(4) In addition to complying with the provisions of paragraph (1) of this subdivision, every person who owns, operates, maintains or otherwise controls an intermodal solid waste container facility shall comply with the provisions of Subchapter D of this chapter, as applicable.
(b) In addition to complying with the siting restrictions contained in paragraph (1) of subdivision (a) of this section, all solid waste transfer stations shall comply with the following siting restrictions:
(1) Any transfer station located in a community district that contains less than four percent of the total number of existing, lawfully operating transfer stations, as calculated by the Department, shall be subject to the following siting restrictions:
(i) Any new transfer station shall be located at a site that is entirely within an M1, M2 and/or M3 district, provided that such new transfer station shall not be located in an M1 district if the M1 districts in such community district cumulatively contain three or more lawfully operating transfer stations.
(ii) Any new transfer station shall be at least 400 feet from a residential district, hospital, public park or school.
(iii) In addition to the above restrictions, no new transfer station shall be located less than 400 feet from another transfer station. This restriction shall not apply to a new transfer station that is located at or adjacent to a rail yard, rail spur, industrial track or vessel facility, provided that at least ninety percent of the solid waste received is subsequently transported from the transfer station by rail or vessel.
(iv) Any new transfer station shall provide space to accommodate truck queuing on site.
(v) Any transfer station that is lawfully operating may expand its site boundary, subject to Department review and approval, provided that such site expansion complies with the buffer distance requirements for a residential district, hospital, public park or school as set forth in subparagraph (ii) of this paragraph.
(vi) Any transfer station that is lawfully operating may increase its lawful daily permitted throughput capacity, subject to Department review and approval, provided that it is located at least 400 feet from a residential district, hospital, public park or school. This restriction shall not apply to a transfer station that is located at or adjacent to a rail yard, rail spur, industrial track or vessel facility, provided that at least ninety percent of the solid waste received is subsequently transported from the transfer station by rail or vessel.
(2) Any transfer station located in a community district that contains from four to less than eight percent of the total number of existing, lawfully operating transfer stations, as calculated by the Department, shall be subject to the following siting restrictions:
(i) Any new transfer station shall be located at a site that is entirely within an M1, M2 and/or M3 district, provided that such new transfer station shall not be located in an M1 district if the M1 districts in such community district cumulatively contain three or more lawfully operating transfer stations.
(ii) Any new transfer station shall be at least 500 feet from a residential district, hospital, public park or school.
(iii) In addition to the above restrictions, no new transfer station shall be located less than 400 feet from another transfer station. This restriction shall not apply to a new transfer station that is located at or adjacent to a rail yard, rail spur, industrial track or vessel facility, provided that at least ninety percent of the solid waste received is subsequently transported from the transfer station by rail or vessel.
(iv) Any new transfer station shall provide space to accommodate truck queuing on site.
(v) Any transfer station that is lawfully operating may expand its site boundary, subject to Department review and approval, provided that such site expansion complies with the buffer distance requirements for a residential district, hospital, public park or school as set forth in subparagraph (ii) of this paragraph.
(vi) Any transfer station that is lawfully operating may increase its lawful daily permitted throughput capacity, subject to Department review and approval, provided that it is located at least 500 feet from a residential district, hospital, public park or school. This restriction shall not apply to a transfer station that is located at or adjacent to a rail yard, rail spur, industrial track or vessel facility, provided that at least ninety percent of the solid waste received is subsequently transported from the transfer station by rail or vessel.
(3) Any transfer station located in a community district that contains from eight to less than twelve percent of the total number of existing, lawfully operating transfer stations, as calculated by the Department, shall be subject to the following siting restrictions:
(i) No new transfer stations shall be allowed in an M1 district.
(ii) Any new transfer station shall be located at a site that is entirely within an M2 and/or M3 district and shall be at least 600 feet from a residential district, hospital, public park or school.
(iii) In addition to the above restrictions, no new transfer station shall be located less than 400 feet from another transfer station. This restriction shall not apply to a new transfer station that is located at or adjacent to a rail yard, rail spur, industrial track or vessel facility, provided that at least ninety percent of the solid waste received is subsequently transported from the transfer station by rail or vessel.
(iv) Any new transfer station shall provide space to accommodate truck queuing on site.
(v) Any transfer station that is lawfully operating may expand its site boundary, subject to Department review and approval, provided that such site expansion complies with the buffer distance requirements for a residential district, hospital, public park or school as set forth in subparagraph (ii) of this paragraph.
(vi) Any transfer station that is lawfully operating may increase its lawful daily permitted throughput capacity, subject to Department review and approval, provided that it is located at least 500 feet from a residential district, hospital, public park or school. This restriction shall not apply to a transfer station that is located at or adjacent to a rail yard, rail spur, industrial track or vessel facility, provided that at least ninety percent of the solid waste received is subsequently transported from the transfer station by rail or vessel.
(4) Any transfer station located in a community district that contains from twelve to less than sixteen percent of the total number of existing, lawfully operating transfer stations, as calculated by the Department, shall be subject to the following siting restrictions:
(i) The Department shall not authorize the operation of a new transfer station unless:
(A) the applicant obtains a corresponding reduction (offset) in the lawful daily permitted throughput capacity at a transfer station within the same community district at a rate of one ton for every new ton of capacity and such reduction (offset) is of the same type of solid waste (putrescible for putrescible, construction and demolition debris for construction and demolition debris, or fill material for fill material); or
(B) the application is for a new putrescible or construction and demolition debris transfer station located at or adjacent to a rail yard, rail spur, industrial track or vessel facility where at least ninety percent of the solid waste received is subsequently transported from the transfer station by rail or vessel, and the applicant obtains a corresponding reduction (offset) in the lawful daily permitted throughput capacity at a putrescible or construction and demolition debris transfer station within the same community district at a rate of one ton for every new ton of capacity.
(ii) No new transfer stations shall be allowed in an M1 district.
(iii) Any new transfer station shall be located at a site that is entirely within an M2 and/or M3 district and shall be at least 600 feet from a residential district, hospital, public park or school.
(iv) In addition to the above restrictions, no new transfer station shall be located less than 400 feet from another transfer station. This restriction shall not apply to a new transfer station that is located at or adjacent to a rail yard, rail spur, industrial track or vessel facility, provided that at least ninety percent of the solid waste received is subsequently transported from the transfer station by rail or vessel.
(v) Any new transfer station shall be entirely enclosed.
(vi) Any new transfer station shall provide space to accommodate truck queuing on site.
(vii) Any transfer station that is lawfully operating may expand its site boundary, subject to Department review and approval, provided that such site expansion complies with the buffer distance requirements for a residential district, hospital, public park or school as set forth in subparagraph (iii) of this paragraph.
(viii) Any transfer station that is lawfully operating and is located at least 500 feet from a residential district, hospital, public park or school may increase its lawful daily permitted throughput capacity if the owner/operator obtains a corresponding reduction (offset) in the lawful daily permitted throughput capacity at a transfer station located in the same community district at a rate of one ton for every new ton of capacity, and such reduction is of the same type of solid waste (putrescible for putrescible, construction and demolition debris for construction and demolition debris, or fill material for fill material).
(ix) Any putrescible or construction and demolition debris transfer station that is lawfully operating at or adjacent to a rail yard, rail spur, industrial track or vessel facility where at least ninety percent of the solid waste received is subsequently transported from the transfer station by rail or vessel, may increase its lawful daily permitted throughput capacity provided that the owner/operator obtains a corresponding reduction (offset) in the lawful daily permitted throughput capacity at a putrescible or construction and demolition debris transfer station within the same community district at a rate of one ton for every new ton of capacity.
(5) Any transfer station located in a community district that contains sixteen percent or more of the total number of existing, lawfully operating transfer stations, as calculated by the Department, shall be subject to the following siting restrictions:
(i) The Department shall not authorize the operation of a new transfer station unless:
(A) the applicant obtains a corresponding reduction (offset) in the lawful daily permitted throughput capacity at a transfer station within the same community district at a rate of one ton for every new ton of capacity and such reduction (offset) is of the same type of solid waste (putrescible for putrescible, construction and demolition debris for construction and demolition debris, or fill material for fill material); or
(B) the application is for a new putrescible or construction and demolition debris transfer station located at or adjacent to a rail yard, rail spur, industrial track or vessel facility where at least ninety percent of the solid waste received is subsequently transported from the transfer station by rail or vessel, and the applicant obtains a corresponding reduction (offset) in the lawful daily permitted throughput capacity at a putrescible or construction and demolition debris transfer station within the same community district at a rate of one ton for every new ton of capacity.
(ii) No new transfer stations shall be allowed in an M1 district.
(iii) Any new transfer station shall be located at a site that is entirely within an M2 and/or M3 district and shall be at least 700 feet from a residential district, hospital, public park or school.
(iv) In addition to the above restrictions, no new transfer station shall be located less than 400 feet from another transfer station. This restriction shall not apply to a new transfer station that is located at or adjacent to a rail yard, rail spur, industrial track or vessel facility, provided that at least ninety percent of the solid waste received is subsequently transported from the transfer station by rail or vessel.
(v) Any new transfer station shall be entirely enclosed.
(vi) Any new transfer station shall provide space to accommodate truck queuing on site.
(vii) Any transfer station that is lawfully operating may expand its site boundary, subject to Department review and approval, provided that such site expansion complies with the buffer distance requirements for a residential district, hospital, public park or school as set forth in subparagraph (iii) of this paragraph.
(viii) Any transfer station that is lawfully operating and is located at least 500 feet from a residential district, hospital, public park or school may increase its lawful daily permitted throughput capacity if the owner/operator obtains a corresponding reduction (offset) in the lawful daily permitted throughput capacity at a transfer station located in the same community district at a rate of one ton for every new ton of capacity, and such reduction is of the same type of solid waste (putrescible for putrescible, construction and demolition debris for construction and demolition debris, or fill material for fill material).
(ix) Any putrescible or construction and demolition debris transfer station that is lawfully operating at or adjacent to a rail yard, rail spur, industrial track or vessel facility where at least ninety percent of the solid waste received is subsequently transported from the transfer station by rail or vessel, may increase its lawful daily permitted throughput capacity provided that the owner/operator obtains a corresponding reduction (offset) in the lawful daily permitted throughput capacity at a putrescible or construction and demolition debris transfer station within the same community district at a rate of one ton for every new ton of capacity.
(c) For purposes of this section, a new transfer station shall mean a transfer station that is not lawfully operating on the effective date of this section.
(d) For purposes of the percentage calculations required by subdivision (b) of this section, the following shall apply:
(1) transfer stations lawfully operating at the same location with one or more written authorizations by the Department to operate a non-putrescible and/or putrescible solid waste transfer station shall be counted as one transfer station;
(2) the Department's marine transfer stations, when operational and handling solid waste for ultimate disposal, shall be included in the number used for the percentage calculations;
(3) the Department shall update the above percentage calculations continuously as new permits are issued; and
(4) such percentage calculations shall be published in the City Record and on the Department's website on or about the first day of January and on or about the first day of July of every calendar year, and shall be in the following format that corresponds with the rules set forth in subdivision (b) of this section:
Percentage of Existing, Lawfully Operating Transfer Stations in NYC Community Districts Buffer Distance to Residential Districts, Hospitals, Public Parks and Schools Buffer Distance Between Transfer Stations (A) Additional Requirements Zoning Requirements 16% or more 700 feet 400 feet (i) Facility enclosed; (ii) Queuing area on site; (iii) Offsets required (B), (C), (D), (E) M2 and/or M3 districts only From 12 to less than 16% 600 feet 400 feet (i) Facility enclosed; (ii) Queuing area on site; (iii) Offsets required (B), (C), (D), (E) M2 and/or M3 districts only From 8 to less than 12% 600 feet 400 feet Queuing area on site (F) M2 and/or M3 districts only From 4 to less than 8% 500 feet 400 feet Queuing area on site (F) M1, M2 and/or M3 allowed (F) Less than 4% 400 feet 400 feet Queuing area on site (G) M1, M2 and/or M3 allowed (H)
(A) This restriction shall not apply to a new transfer station that is located at or adjacent to a rail yard, rail spur, industrial track or vessel facility, provided that at least ninety percent of the solid waste received is subsequently transported from the transfer station by rail or vessel.
(B) Any new transfer stations operating a truck-to-truck facility must obtain a corresponding reduction (offset) in the lawful daily permitted throughput capacity at a transfer station within the same community district at a rate of one ton for every new ton of capacity. Such reduction must be of the same type of solid waste (putrescible for putrescible, construction and demolition debris for construction and demolition debris, or fill material for fill material).
(C) Any application for a new putrescible or construction and demolition debris transfer stations located at or adjacent to a rail yard, rail spur, industrial track or vessel facility, and where at least ninety percent of the solid waste received is subsequently transported from the transfer station by rail or vessel, must obtain a corresponding reduction (offset) in the lawful daily permitted throughput capacity at a putrescible or construction and demolition debris transfer station within the same community district at a rate of one ton for every new ton of capacity.
(D) Any transfer station that is lawfully operating that is located at least 500 feet from a residential district, hospital, public park or school may increase its lawful daily permitted throughput capacity only if such owner/operator obtains a corresponding reduction (offset) in the lawful daily permitted throughput capacity at a transfer station located in the same community district at a rate of one ton for every new ton of capacity. Such reduction must be of the same type of solid waste (putrescible for putrescible, construction and demolition debris for construction and demolition debris, or fill material for fill material).
(E) Any putrescible or construction and demolition debris transfer station that is lawfully operating at or adjacent to a rail yard, rail spur, industrial track or vessel facility where at least ninety percent of the solid waste received is subsequently transported from the transfer station by rail or vessel, may increase its lawful daily permitted throughput capacity provided that the owner/operator obtains a corresponding reduction (offset) in the lawful daily permitted throughput capacity at a putrescible or construction and demolition debris transfer station within the same community district at a rate of one ton for every new ton of capacity.
(F) Any transfer station that is lawfully operating may increase its lawful daily permitted throughput capacity, subject to Department review and approval, provided that it is located at least 500 feet from a residential district, hospital, public park or school. This restriction shall not apply to a transfer station that is located at or adjacent to a rail yard, rail spur, industrial track or vessel facility, provided that at least ninety percent of the solid waste received is subsequently transported from the transfer station by rail or vessel.
(G) Any transfer station that is lawfully operating may increase its lawful daily permitted throughput capacity, subject to Department review and approval, provided that it is located at least 400 feet from a residential district, hospital, public park or school. This restriction shall not apply to a transfer station that is located at or adjacent to a rail yard, rail spur, industrial track or vessel facility, provided that at least ninety percent of the solid waste received is subsequently transported from the transfer station by rail or vessel.
(H) Any new transfer station shall not be located in an M1 district if the M1 districts in such community district cumulatively contain three or more lawfully operating transfer stations.
§ 4-33. Hours of Operation
(a) Non-putrescible solid waste transfer stations located in an M1 district may not receive solid waste between 7 p.m. and 6 a.m.
(b) Putrescible solid waste transfer stations located in an M1 district may operate 24 hours per day, but may not receive solid waste between 4 a.m. and noon on Sundays.
(c) The Department may restrict the hours of operation for any transfer station, including further restricting the hours of operation for a transfer station covered by subdivision (a) or (b) of this section, as a condition of such transfer station receiving a permit pursuant to §§ 16-130 and 16-131 of the Administrative Code.
§ 4-34. Engineering Reports, Transportation Plans and Periodic Reviews of the City's Overall Waste Disposal Needs
(a) All transfer stations shall submit with each permit application a certified engineering report acceptable to the Department demonstrating that the transfer station complies with the applicable performance standards of the Zoning Resolution and the applicable provisions of the New York City Health Code.
(b) All transfer stations shall submit with each permit application truck transportation plans that specify the routes that truck transport vehicles will use when transporting solid waste or other material out of the facility for final disposal, reuse, or recycling. After reviewing the transportation plans, the Department may require as a permit condition that a transfer station establish a system to require such trucks exiting the transfer station to use specific transport routes.
(c) The Department shall conduct periodic reviews of transfer station capacity, in the context of the City's overall waste disposal needs, with the objective of minimizing the concentration or impacts of transfer stations, particularly in those communities with the largest number of transfer stations.
§ 4-35. Variances
(a) Unless otherwise precluded by law, the Department may grant a variance from one or more of the specific provisions of 16 RCNY §§ 4-32 and 4-33 in accordance with the provisions of this section. The Department shall be precluded from granting a variance that would authorize the operation of a solid waste transfer station at a site where such use is not authorized by the Zoning Resolution or by a variance granted by the Board of Standards and Appeals. In addition, the Department shall be precluded from granting a variance from the provisions of 16 RCNY § 4-34 and, for the siting of a new transfer station, from granting a variance from the applicable buffer distance requirements from a residential district, hospital, public park or school as set forth in 16 RCNY § 4-32.
(b) An applicant for a variance shall file a written application with the Department on a form prescribed by the Department. Every application for a variance shall identify the specific provision or provisions of this subchapter from which a variance is sought.
(c) The applicant shall promptly forward a copy of the application for a variance to:
(1) the Community Board of the community district in which the transfer station is located or is proposed to be located;
(2) the City Council Member in whose district the transfer station is located or is proposed to be located; and
(3) the Borough President of the borough in which the transfer station is located or is proposed to be located.
(d) Except as otherwise provided in subdivision (a) of this section, the Department may grant a variance to an existing, lawfully operating transfer station from one or more of the specific provisions of 16 RCNY §§ 4-32 and 4-33 only upon a determination that a proposed action requiring a variance will, when taken as a whole, result in an overall environmental benefit. An action requiring a variance may produce an overall environmental benefit if, in conjunction with the variance request, the applicant also proposes and agrees to implement measures that are more protective of the environment and exceed regulatory requirements for existing transfer stations. Such environmentally protective measures could include, but are not limited to, enclosing a non-putrescible or fill material transfer station; obtaining a reduction in the lawful daily permitted throughput capacity at a transfer station located in the same community district of an equal or greater amount; making provisions for queuing all trucks on site; and/or utilizing new technology to reduce air emissions from off-road vehicles or stationary sources used at a transfer station. In assessing the nature of the environmental benefit required for a variance, the Department will take into account unique topographic conditions that may exist in or around the transfer station that limit the potential environmental impacts of the facility.
(e) Except as otherwise provided in subdivision (a) of this section, the Department may grant a variance for a new transfer station only from the applicable buffer distance requirements from another transfer station and only if (1) the new transfer station is located in an M2 and/or M3 district; (2) the new transfer station proposes and agrees to implement measures that are protective of the environment and exceed regulatory requirements for new transfer stations. Such environmentally protective measures could include, but are not limited to, enclosing a non-putrescible or fill material transfer station if not otherwise lawfully required; obtaining a reduction in the lawful daily permitted throughput capacity at a transfer station located in the same community district of an equal or greater amount if not otherwise lawfully required; and/or utilizing new technology to reduce air emissions from off-road vehicles or stationary sources used at a transfer station; and (3) the action for which the variance is required will not result in any significant adverse environmental impact.
§ 4-36. Interim Siting Restrictions for New or Expanded Construction and Demolition Debris Transfer Stations
(a) Notwithstanding the provisions of 16 RCNY § 4-05, no new permit or authorization to operate shall be issued by the Department during the period from March twenty-first, two thousand three through October twentieth, two thousand four, for a construction and demolition debris transfer station, as defined in 16 RCNY § 4-01, that was not lawfully operating on March twenty-first, two thousand three, nor may any construction and demolition debris transfer station be authorized during such period to increase its lawful permitted capacity.
(b) Notwithstanding subdivision (a) of this section, the Department may issue to a construction and demolition debris transfer station that was lawfully operating on March twenty-first, two thousand three a permit to convert some or all of its lawful permitted capacity to putrescible solid waste.
(c) Notwithstanding subdivision (a) of this section, the Department may authorize the operation of a new intermodal solid waste container facility that handles construction and demolition debris, provided that (1) such new facility is located at or adjacent to a rail yard, rail spur, industrial track or vessel facility, (2) the construction and demolition debris at such facility is in closed, leak-proof containers at all times, including during receipt, storage and removal, (3) the containers are acceptable to the Department and maintained in a safe, nuisance-free manner, and (4) the containers are removed by rail or vessel.
(d) This section shall expire on the twentieth day of October, two thousand four, provided that if permanent siting rules promulgated pursuant to subdivision (b) of § 16-131 of the administrative code of the city of New York take effect before such date, then this section shall expire on the date such permanent siting rules take effect.
§ 4-37. Interim Siting Restrictions for New or Expanded Fill Material Transfer Stations
(a) Notwithstanding the provisions of 16 RCNY § 4-07, no new permit or authorization to operate shall be issued by the Department during the period from March twenty-first, two thousand three through October twentieth, two thousand four, for a fill material transfer station, as defined in 16 RCNY § 4-01, that was not lawfully operating on March twenty-first, two thousand three, nor may any fill material transfer station be authorized during such period to increase its lawful permitted capacity.
(b) This section shall expire on the twentieth day of October, two thousand four, provided that if permanent siting rules promulgated pursuant to subdivision (b) of § 16-131 of the administrative code of the city of New York take effect before such date, then this section shall expire on the date such permanent siting rules take effect.
§ 4-38. Interim Siting Restrictions for New or Expanded Putrescible Solid Waste Transfer Stations
(a) Notwithstanding the provisions of 16 RCNY § 4-14, no new permit or authorization to operate shall be issued by the Department during the period from March twenty-first, two thousand three through October twentieth, two thousand four, for a putrescible solid waste transfer station, as defined in 16 RCNY § 4-11, that was not lawfully operating on March twenty-first, two thousand three.
(b) 1) During the period from March twenty-first, two thousand three through October twentieth, two thousand four, the Department may authorize a putrescible solid waste transfer station that is not located in either Brooklyn Community District 1 or Bronx Community District 2 and that was lawfully operating on March twenty-first, two thousand three, to increase its lawful permitted capacity.
(2) Notwithstanding the provisions of 16 RCNY § 4-14, during the period from March twenty-first, two thousand three through October twentieth, two thousand four, the Department shall not authorize the owner/operator of a putrescible solid waste transfer station that is located in either Brooklyn Community District 1 or Bronx Community District 2 to increase its lawful permitted capacity, provided that the Department may authorize the owner/operator of any such transfer station that was lawfully operating on March twenty-first, two thousand three to increase its lawful permitted capacity where such owner/operator reduces or obtains a reduction in the lawful permitted capacity at another putrescible or non-putrescible solid waste transfer station within the same community district by an equal or greater amount.
(c) Notwithstanding subdivisions (a) and (b) of this section, the Department may (1) authorize the operation of a new intermodal solid waste container facility that handles putrescible solid waste, provided that (i) such new facility is located at or adjacent to a rail yard, rail spur, industrial track or vessel facility, (ii) the putrescible solid waste at such facility is in closed, leak-proof containers at all times, including during receipt, storage and removal, (iii) the containers are acceptable to the Department and maintained in a safe, nuisance-free manner, and (iv) the containers are removed by rail or vessel; or (2) issue a new permit to a putrescible solid waste transfer station that receives putrescible solid waste, provided that (i) such new transfer station is located at or adjacent to a rail yard, rail spur, industrial track or vessel facility, and (ii) the putrescible solid waste received is subsequently transported from the transfer station by rail or vessel.
(d) During the period from March twenty-first, two thousand three through October twentieth, two thousand four, each putrescible solid waste transfer station that is located in either Brooklyn Community District 1 or Bronx Community District 2 that is permitted to operate under subdivision (c)(2) of this section, shall be required to reduce or obtain a reduction in the lawful permitted capacity at another putrescible or non-putrescible solid waste transfer station within the same community district by an equal or greater amount.
(e) This section shall expire on the twentieth day of October, two thousand four, provided that if permanent siting rules promulgated pursuant to subdivision (b) of § 16-131 of the administrative code of the city of New York take effect before such date, then this section shall expire on the date such permanent siting rules take effect.
§ 4-39. Definitions
When used in this subchapter:
Commissioner. "Commissioner" shall mean Commissioner of Sanitation or his or her representative.
Construction and demolition debris. "Construction and demolition debris" shall mean non-putrescible solid waste resulting from any excavation, or any construction, demolition, alteration, repair, or renovation of any structure, building or premises.
Equipment. "Equipment" shall mean all implements used in the operation of the intermodal solid waste container facility, including but not limited to motor-driven machinery.
Intermodal container. "Intermodal container" shall mean a container meeting the specification requirements of 16 RCNY § 4-43 that is used for the transport of solid waste to or from an intermodal solid waste container facility.
Intermodal solid waste container facility. "Intermodal solid waste container facility" shall mean a facility or premises served by rail or vessel at which intermodal containers are transferred from transport vehicle to transport vehicle for the purpose of consolidating intermodal containers for shipment by rail or vessel to an authorized disposal or treatment facility, where the contents of each container remain in their closed containers during the transfer between transport vehicles, and storage remains incidental to transport at the location where the containers are consolidated.
Non-putrescible solid waste. "Non-putrescible solid waste" shall mean solid waste that does not contain organic matter having the tendency to decompose with the formation of malodorous by-products, including but not limited to dirt, earth, plaster, concrete, rock, rubble, slag, ashes, waste timber, lumber, plexiglass, fiberglass, ceramic tiles, asphalt, sheetrock, tar paper, tree stumps, wood, window frames, metal, steel, glass, plastic pipes and tubes, rubber hoses and tubes, electric wires and cables, paper and cardboard.
Person. "Person" shall mean any individual, corporation, partnership, association, firm, trust, estate or any other legal entity whatsoever.
Putrescible solid waste. "Putrescible solid waste" shall mean solid waste containing organic matter having the tendency to decompose with the formation of malodorous by-products.
Solid waste. "Solid waste" shall mean all putrescible and non-putrescible materials or substances, other than those materials or substances described in subdivision (b) of this definition, that are discarded or rejected, including but not limited to, garbage, refuse, waste collected by any person required to be licensed or permitted pursuant to Subchapter 18 of Chapter 2 of Title 20 of the Administrative Code of the City of New York, rubbish, tires, ashes, contained gaseous material, incinerator residue, construction and demolition debris, discarded automobiles and offal. Such term shall include recyclable materials, as defined in § 16-303 of Title 16 of the Administrative Code of the City of New York.
(a) A material is discarded or rejected if it is:
(1) spent, useless, worthless or in excess to the owners at the time of such discard or rejection;
(2) disposed of;
(3) burned or incinerated, including material burned as a fuel for the purpose of recovering usable energy; or
(4) accumulated, stored or physically, chemically or biologically treated (other than burned or incinerated) instead of or before being disposed of.
(b) The following are not solid waste for the purpose of this section:
(1) domestic sewage;
(2) any mixture of domestic sewage and other wastes that passes through a sewer system to a publicly owned treatment works for treatment, except any material that is introduced into such system in order to avoid the provisions of this subchapter, 24 RCNY Health Code Article 157, Title 16 of the Administrative Code of the City of New York, or of State regulations promulgated to regulate solid waste management facilities;
(3) industrial wastewater discharges that are actual point source discharges subject to permits under article seventeen of the environmental conservation law; provided that industrial wastewaters while they are being collected, stored or treated before discharge and sludges that are generated by industrial wastewater treatment are solid wastes;
(4) irrigation return flows;
(5) radioactive materials that are source, special nuclear, or by-product material under the federal Atomic Energy Act of 1954, as amended, 42 U.S.C. §§ 2011 et seq.;
(6) materials subject to in-situ mining techniques that are not removed from the ground as part of the extraction process;
(7) hazardous waste as defined in § 27-0901 of the Environmental Conservation Law, including material containing hazardous waste; and
(8) regulated medical waste as defined in Title 15 of Article 27 of the New York State Environmental Conservation Law, in Title 13 of Article 13 of the New York State Public Health Law or in § 16-120.1 of the Administrative Code of the City of New York or any rules promulgated pursuant to such provisions of law.
Transport vehicle. "Transport vehicle" shall mean any motor vehicle, rail car, vessel, or other means of transportation used to deliver intermodal containers into, or to remove intermodal containers from, an intermodal solid waste container facility.
Vessel. "Vessel" shall mean any barge, ship, boat, or other floating craft used for transportation in or on a waterway.
§ 4-40. Compliance with Federal, State and Local Laws
Every person who owns, operates, maintains or otherwise controls an intermodal solid waste container facility regulated by this subchapter shall comply fully with all applicable federal, state and local laws, rules and regulations.
§ 4-41. Registration Required
(a) No person other than the Department of Sanitation may conduct, operate or use any pier or part thereof, or any piece or parcel of land or land under water within the City of New York as an intermodal solid waste container facility, unless, in addition to any other permit or authorization required by law, such person obtains a registration from the Commissioner as required by this subchapter.
(b) Registration of an intermodal solid waste container facility is a ministerial action for purposes of the State Environmental Quality Review Act, Article 8 of the Environmental Conservation Law and 6 NYCRR Part 617, and the City Environmental Quality Review procedures.
§ 4-42. Registration for Intermodal Solid Waste Container Facilities
An application for the registration of an intermodal solid waste container facility shall include:
(1) A site plan, including the name of the facility, with block and lot numbers, street address, zoning district, borough, property boundaries, including a metes and bounds description of the property, proof of ownership or other authorization to use the property, location of fences, gates, entrances and exits, parking spaces and area where transport vehicles may wait prior to delivery or removal of intermodal containers; and the location and dimensions of each area where intermodal containers shall be received and stored prior to transfer to a transport vehicle;
(2) A copy of all permits or other authorizations to construct or operate required under federal, state or local laws, rules or regulations;
(3) A description of proposed intermodal solid waste container facility operations, including descriptions of storage area, transfer operations, site improvements, type of solid waste accepted, type of containers accepted, and period of time intermodal containers would be stored on site;
(4) A map describing not less than one square mile of the area surrounding the proposed facility, clearly marking the lawful truck routes where transport vehicles may transport intermodal containers to and from the facility, and connecting roadways permitted to be used by transport vehicles, as certified by a registered architect or licensed professional engineer;
(5) The estimated number and type of transport vehicles to be used to deliver intermodal containers into, or to remove intermodal containers from, the facility, including an estimate of the daily, weekly and monthly arrivals and departures;
(6) A certification from a title insurance corporation, as such corporation is defined in § 6401 of the Insurance Law, or from a duly authorized agent thereof, establishing the ownership of the property upon which the intermodal solid waste container facility is sited or proposed to be sited;
(7) The registrant's business address and telephone number;
(8) An estimate of both the average and the maximum number and volume of intermodal containers to be located at the facility at one time; and
(9) A signed and notarized affidavit acknowledging the registrant's liability to the City for the removal, if necessary for public health and safety reasons, of intermodal containers from the intermodal solid waste container facility.
(10) The annual fee to cover the cost of inspection for a registration issued pursuant to this subchapter shall be seven thousand dollars ($7,000).
§ 4-43. Intermodal Container Specification Requirements
(a) For purposes of this section, "container" shall mean an intermodal container.
(b) All transportation of solid waste to and from intermodal solid waste container facilities shall be in containers meeting the specification requirements set forth in subdivision (c) of this section.
(c) Each container shall meet the following specification requirements: (1) each container shall be designed, constructed, loaded, secured and maintained so as (i) to prevent the escape of wastes or liquids; and (ii) to prevent the loss or spillage of wastes or liquids in the event of an accident; (2) each container shall be completely enclosed, rigid, and constructed of nonpermeable material, provided that rigid top-loaded intermodal containers containing construction and demolition debris and no putrescible waste may be enclosed with a non-rigid cover acceptable to the Commissioner; and (3) each container shall meet all applicable U.S. Department of Transportation specifications and generally accepted industry standards.
§ 4-44. Operation and Maintenance
(a) For purposes of this section, "facility" shall mean an intermodal solid waste container facility.
(b) The facility shall be located at or adjacent to a rail yard, rail spur, industrial track or vessel facility.
(c) The handling of intermodal containers shall be conducted in a safe and sanitary manner so as to avoid any nuisance or other condition that could pose a danger to public health or safety.
(d) The facility shall handle intermodal containers in a manner consistent with the site plan and operating information submitted with the registration.
(e) There shall be sufficient space at the facility for transport vehicles to enter and exit safely.
(f) Trucks shall enter and exit the facility via lawful truck routes.
(g) All solid waste received at the facility for transport must be in intermodal containers at all times, including during receipt, storage and removal.
(h) All intermodal containers must meet the specification requirements set forth in 16 RCNY § 4-43.
(i) (1) The facility, to the extent practicable, shall keep the following records for each intermodal container received and transported out of the facility:
(i) description of the solid waste in the intermodal container;
(ii) volume of the solid waste contained in the intermodal container;
(iii) the name of the solid waste management facility where the solid waste was loaded into the intermodal container; and
(iv) the destination of the intermodal container after it leaves the facility.
(2) Such records shall be maintained for a period of not less than three years and be readily available for inspection by a representative from the Department of Sanitation.
(j) All intermodal containers containing putrescible solid waste shall be removed within seventy-two hours of receipt.
(k) All intermodal containers must be removed from the facility by rail or vessel.
(l) Equipment used in the handling of intermodal containers shall be contained within the property line, and under no circumstances shall such equipment be stored on city streets.
(m) No transport vehicle required to be licensed or permitted pursuant to Title 20 of the Administrative Code of the City of New York shall deliver an intermodal container to a facility unless such transport vehicle is appropriately licensed or permitted.
(n) The Commissioner may waive one or more requirements of this section if he or she reasonably determines that such waiver would not be inconsistent with the purposes of this subchapter, and provided that such waiver is not otherwise contrary to law.
§ 4-45. Suspension and Revocation
The Department of Sanitation specifically reserves the right, to the extent that it is not inconsistent with applicable federal, state or local laws, rules or regulations, to suspend such registration temporarily or to revoke it permanently after adequate notice, when the Commissioner or his/her designee has found that the holder of such registration has violated the terms of this subchapter.
§ 4-46. Severability
The provisions of this subchapter shall be severable and if any phrase, clause, sentence, paragraph, subdivision or section of this subchapter, or the applicability thereof to any person or circumstance, shall be held invalid, the remainder of this subchapter and the application thereof shall not be affected thereby.
§ 4-51. Definitions
As used in this subchapter, the following terms have the following meanings:
Commissioner. The term "Commissioner" means the commissioner of sanitation.
Department. The term "Department" means the department of sanitation.
Department-marked item. The term "Department-marked item" means any refrigerant-containing item that: (i) has written upon it a Department service identification number that has been provided to the property owner by a 311 or Department representative, or (ii) has affixed upon it an official decal or sticker indicating that such item is designated for future servicing of refrigerant removal by the Department, or (iii) has affixed upon it an official decal or sticker indicating that such item has already been serviced for refrigerant removal by the Department.
ECB. The term "ECB" means the environmental control board.
Ferrous. The term "ferrous" means metals and alloys that contain iron, such as mild steel, carbon steel, stainless steel, cast iron, and wrought iron.
Non-ferrous. The term "non-ferrous" means metals and alloys that do not contain iron, such as aluminum, brass, copper, nickel, tin, lead, zinc, and precious metals including gold and silver.
Not-for-profit corporation. The term "not-for-profit corporation" means a not-for-profit corporation as defined in subparagraph five or subparagraph seven of subdivision a of section 102 of the New York state not-for-profit corporation law.
Organic Waste. The term "organic waste" shall have the same meaning as set forth in § 16-303 of the Administrative Code of the city of New York, except that organic waste shall not include food that is donated to a third party, food that is sold to farmers for feedstock, and meat by-products that are sold to a rendering company.
Person. The term "person" means any individual, corporation, partnership, association, firm, trust, estate or any other legal entity whatsoever.
Recyclable material. The term "recyclable material" means material that may be separated, collected, processed, marketed and returned to the economy in the form of raw materials or products, including but not limited to, ferrous or non-ferrous metal, glass, paper, cardboard, rigid plastic, food waste, tires and yard waste.
Recycling processing facility. The term "recycling processing facility" means a facility that is registered or permitted by the New York state department of environmental conservation and/or the Department where recyclable materials, other than organic waste, are delivered separately from solid waste or where source-separated recyclable materials, other than organic waste, are processed for the purpose of reuse or sale. This term also includes scrap metal processors licensed by the department of consumer affairs.
Refrigerant. The term "refrigerant" means any substance consisting in whole or in part of a class I or class II ozone-depleting substance, which is used for heat transfer purposes and provides a cooling effect, including, but not limited to, chlorofluorocarbons, hydro-chlorofluorocarbons, or any other substitute substance as may be defined by the United States environmental protection agency. A class I or class II ozone-depleting substance shall be those substances as defined by the United States environmental protection agency in section 602 of the United States clean air act. A substitute substance shall be any environmental protection agency approved replacement for a class I or II ozone-depleting substance in a refrigeration or air-conditioning end-use.
Refrigerant-containing item. The term "refrigerant-containing item" means any recyclable material that uses a refrigerant that must be removed prior to disposal, including, but not limited to, any air conditioner, refrigerator, water cooler, or freezer.
Scrap metal. The term "scrap metal" means ferrous or non-ferrous metal that is used for the production of raw material for remelting purposes for steel mills, foundries, smelters, refiners, and similar users.
Scrap metal processor. The term "scrap metal processor" means an establishment that purchases, sells, accepts, stores or processes scrap metal destined for recycling, but shall not include a redemption center, dealer or distributor as defined in section 27-1003 of the New York state environmental conservation law, or an electronic waste collection site, electronic waste consolidation facility or electronic waste recycling facility as defined in section 27-2601 of the New York state environmental conservation law.
(Added City Record 9/23/2016, eff. 10/23/2016)
§ 4-52. Registration of Recycling Processing Facilities
(a) No person shall operate a recycling processing facility within the city of New York, unless, in addition to any other permit or authorization required by law, such person obtains a registration from the Commissioner as required by this subchapter.
(b) Within 90 days of the effective date of this rule, any recycling processing facility that is currently in operation must register with the Department using a form prescribed by the Department.
(c) Any recycling processing facility that commences operations after the effective date of this rule must register with the Department using a form prescribed by the Department no less than 30 days prior to operating such recycling processing facility.
(d) Registration forms may be obtained from the Department's website or by written request to:
New York City Department of Sanitation 125 Worth Street, Room 723 New York, New York 10013 Attn: Recycling Processing Facility Registration
(e) A registration must include, at a minimum:
(1) The business name, business address and telephone number of the recycling processing facility. A post office box is not an acceptable address;
(2) The names of the principals and/or officers, on-site managers, and a contact person to whom all official Department correspondence may be sent regarding the recycling processing facility;
(3) Copies of all registrations, permits, licenses or other authorizations to operate required under federal, state, or local laws, rules or regulations; and
(4) The days and hours of operation of such recycling processing facility.
(f) (1) A registration issued to a recycling processing facility shall not be transferrable or assignable to any other party. In the event there is a change in ownership or a sale of the recycling processing facility, the new owner of the facility must register the recycling processing facility within 30 days of such purchase.
(2) A recycling processing facility that terminates its business must notify the Department immediately of the date of cessation of its operations.
(3) A recycling processing facility must advise the Department within 30 days of any changes to the information submitted pursuant to subdivision (e) of this section.
(g) This section will not apply to a redemption center, dealer or distributor as defined in section 27-1003 of the environmental conservation law, or to any person that, using a motor vehicle, collects recyclable containers in bulk and is required to be registered pursuant to Chapter 4-D of Title 16 of the Administrative Code of the City of New York.
(h) Registration of a recycling processing facility is an official act of a ministerial nature, involving no exercise of discretion for purposes of the state environmental quality review act, codified as article 8 of the environmental conservation law and part 617 of title 6 of the New York codes, rules, and regulations and the rules of procedure for city environmental quality review codified as 62 RCNY Chapter 5.
(Added City Record 9/23/2016, eff. 10/23/2016)
§ 4-53. Posting of Registration
Any recycling processing facility must conspicuously post the registration issued by the Commissioner at the place of business.
(Added City Record 9/23/2016, eff. 10/23/2016)
§ 4-54. Receipt and Handling of Recyclable Material
(a) External storage of paper and other recyclables whose marketability may be adversely affected by exposure to the sun or weather conditions is prohibited unless stored in covered containers or in a manner otherwise acceptable to the Department.
(b) No recycling processing facility shall store recyclable materials in such a manner that they become a nuisance or a sanitary or environmental problem.
(Added City Record 9/23/2016, eff. 10/23/2016)
§ 4-55. Receipt of a Department-Marked Item
No recycling processing facility shall receive for storage, collection or processing any Department-marked item from any person other than an authorized employee or agent of the Department. A written agreement between the owner of a residential building or an authorized agent of such owner, and anyone delivering a Department-marked item to a recycling processing facility shall not be a defense in any proceeding before the environmental control board to the improper receipt of such item.
(Added City Record 9/23/2016, eff. 10/23/2016)
§ 4-56. Receipt of Refrigerant-Containing Item
Any recycling processing facility that receives for storage, collection or processing any refrigerant-containing item shall ensure that the refrigerant has been removed from the item previously or that any removal of refrigerant from such item by the recycling processing facility complies with all applicable city, state and federal laws and regulations.
(Added City Record 9/23/2016, eff. 10/23/2016)
§ 4-57. Quarterly reporting requirements
(a) Every registered recycling processing facility must submit to the Department a copy of any report required to be filed with the New York state department of environmental conservation pursuant to part 360 of title 6 of the New York codes, rules, and regulations, if applicable. Any such report must be submitted to the Department at the same time it is submitted to the New York state department of environmental conservation.
(b) Every registered recycling processing facility, other than a scrap metal processor, must submit to the Department quarterly reports that contain the following information, calculated by weight in tons on a monthly basis:
(1) the total amount of recyclable material received;
(2) the origin of the recyclable material received; and
(3) the destination of the recyclable material removed, including a listing, by type, of recyclable material.
(c) Every scrap metal processor must report to the Department quarterly the total amount of recyclable material, by type, calculated by weight in tons, that it has transported out from the facility and the destination of the recyclable material by state and county. Such report shall not separate ferrous and non-ferrous metal, but shall report the total amount of metal transported from the facility as one category.
(d) Quarterly reports must be submitted on forms prescribed by or acceptable to the Department. Such report must include a description of any changes in operation that occurred in the previous quarter, if applicable.
(e) The report for the quarter ending on March 31 shall be due on May 1; the report for the quarter ending on June 30 shall be due on August 1; the report for the quarter ending September 30 shall be due on November 1; and the report for the quarter ending December 31 shall be due on February 1.
(f) The first such report shall be due on May 1, 2017 for the quarterly reporting period from January 1, 2017 through March 31, 2017.
(Added City Record 9/23/2016, eff. 10/23/2016)
§ 4-58. Compliance with Federal, State and Local Laws
Every person who owns, operates, maintains or otherwise controls a recycling processing facility regulated by this subchapter shall comply fully with all applicable federal, state and local laws, rules and regulations of any governmental authorities having jurisdiction over any of the registrant's activities. Failure to comply with these laws, rules or regulations shall be grounds for suspension and/or revocation of the registration, in addition to any other penalty provided by law.
(Added City Record 9/23/2016, eff. 10/23/2016)
§ 4-59. Enforcement and Compliance
(a) The Department reserves the right to conduct lawful inspections during business hours to ensure compliance with this subchapter.
(b) Where a notice of violation is issued for a violation of any of the provisions of this subchapter, such notice shall be returnable to the ECB or court of appropriate jurisdiction, which shall have the power to impose the civil penalties provided.
(c) The Department shall issue a warning letter to a recycling processing facility that fails to comply with 16 RCNY § 4-52, 16 RCNY § 4-53 or 16 RCNY § 4-57. Such warning letter shall give the recycling processing facility 30 days to submit proof of having cured the violating condition. Any recycling processing facility that does not submit proof of having cured such violating condition within the 30 day time period shall be issued a notice of violation by the Department and shall be liable for a civil penalty of $2,500.00 for the first offense, $5,000.00 for the second offense and $10,000.00 for each subsequent offense committed within any three year period.
(d) Any recycling processing facility that violates 16 RCNY § 4-54 shall be liable for a civil penalty of $2,500.00 for the first offense, $5,000.00 for the second offense and $10,000.00 for each subsequent offense committed within any three year period.
(e) Any recycling processing facility that violates 16 RCNY § 4-55 or 16 RCNY § 4-56 shall be liable for (1) a criminal fine of $1,500.00 or imprisonment not to exceed 48 hours, or both, or (2) a civil penalty of $1,500.00 for the first offense and $3,000.00 for each subsequent offense within an 18-month period. For the purpose of imposing a criminal fine or civil penalty pursuant to this paragraph, each receipt from a separate motor vehicle of Department-marked material shall constitute a separate violation for which a criminal fine or civil penalty may be imposed.
(Added City Record 9/23/2016, eff. 10/23/2016)