Title 28, Chapter 6, Appendix A Annual Schedule of Reasonable Costs

(a) Construction costs. The construction cost component of the Total Project Cost, excluding land acquisition costs, site preparation costs, and off-site costs, shall be determined by the use of the latest available Calculator Valuation Guide, published by Calculator Inc., or a comparable publication designated by the Office. Applicants whose construction costs include unique and special costs and are therefore at variance with the Calculator Valuation Guide will be required to produce detailed documentation establishing these costs. Except in cases where such unique costs are approved, the Construction Costs Allowance will be limited to the maximum established by the Calculator Valuation Guide, minus the Builder's Fee.

(b) Off-site and other costs. In recognition of the fact that off-site costs, including but not limited to legal, engineering, and architectural fees, insurance, interest and taxes during construction, and title and mortgage fees, may vary greatly with the size of a project, these costs as well as such other amounts as are ordinarily incurred in connection with the construction, conversion or rehabilitation of a multiple dwelling, will be reviewed and analyzed independently with respect to each building.

(c) Operating and maintenance schedule.

(1) Real estate taxes. Projected real estate taxes shall equal the actual assessed value of the property in the tax year prior to the start of construction multiplied by the projected tax rate for the tax year in which completion is expected. The projected tax rate shall be determined by increasing the current tax rate at the time the application is received by 5 percent for each year between such current year and the projected year of completion.

(2) Replacement reserve. The replacement reserve shall equal six-tenths of 1 percent of construction costs approved pursuant to item (a) of the Annual Schedule of Reasonable Costs.

(3) Other operating and maintenance expense maximum allowances. The schedule of maximum allowances listed below shall apply except when the schedule amounts for each commodity shall be increased or decreased on a compounded annual basis for each year between publication of these rules and the year of projected project completion based upon the Price Indices of Operating Costs (PIOC) percentages published annually by the Rent Guidelines Board for each commodity. For the purposes of projecting future allowances in years for which the PIOC is not available, the Office will apply the percentage for the most recent year for which the Index is available for each subsequent year prior to the estimated completion date. The office will allow the lesser of the owner's claimed costs and the maximum allowance listed below for each commodity.

Schedule Maximum Allowances for Other Operating and Maintenance Expenses

Commodity 1 Maximum Per Room Annual Allowance Maximum Per Room Monthly Allowance Labor2 $273.00 $22.75 Fuel $105.00 $8.75 Utilities XXXX XXXX Water and Sewer $96.00 $8.00 Gas3 $36.00 $3.00 Electricity4 $36.00 $3.00 Other $6.00 $0.50 Contractor Services $141.00 $11.75 Insurance $60.00 $5.00 Parts and Supplies $30.00 $2.50

1. Categories are defined as specified by the Price Index of Operating Costs published by the Rent Guidelines Board.

2. To qualify for a Labor allowance, applicants must submit a list of all personnel to be employed in the maintenance and operation of each building along with corresponding projected wage and salary data. Projects with five units or less are not eligible for the Labor allowance.

3. Available only when the owner pays apartment gas bills.

4. Does not include electricity within apartments.

(d) Vacancy reserve and management and administration fee. The vacancy reserve allowance and the management and administration fee shall together be equal to 9 percent of the sum of the expenses determined pursuant to 28 RCNY §§ 6-04(a)(1)(i), (iii), and (iv) less the amount determined pursuant to 28 RCNY § 6-04(a)(1)(v).

(e) Room calculation. For purposes of this Appendix A's schedule of maximum allowances, the number of rooms shall be calculated in accordance with the definition of "room count" contained in subdivision (c) of 28 RCNY § 6-01.