§ 28-301.1 to Title 28, Chapter 3, Article 309: 100 sections.

§ 28-301.1. Owner's responsibilities

Open this section

All buildings and all parts thereof and all other structures shall be maintained in a safe condition. All service equipment, means of egress, materials, devices, and safeguards that are required in a building by the provisions of this code, the 1968 building code or other applicable laws or rules, or that were required by law when the building was erected, altered, or repaired, shall be maintained in good working condition. Whenever persons engaged in building operations have reason to believe in the course of such operations that any building or other structure is dangerous or unsafe, such person shall forthwith report such belief in writing to the department. The owner shall be responsible at all times to maintain the building and its facilities and all other structures regulated by this code in a safe and code-compliant manner and shall comply with the inspection and maintenance requirements of this chapter.

§ 28-301.1.1. Parapets

Open this section

A building's parapet shall be maintained in a safe condition. A building owner must have an annual parapet observation performed as described in the rules of the department. This observation must be performed on all buildings, regardless of height.

Exception: The requirements of this section shall not apply to detached one- or two-family homes.

(L.L. 2021/126, 11/7/2021, eff. 11/7/2022)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2021/126.

§ 28-301.2. Filing of reports in writing or electronically

Open this section

Reports required to be filed under this chapter shall be filed in writing or electronically as the commissioner may require.

§ 28-302.1. General

Open this section

A building's exterior walls and appurtenances thereof shall be maintained in a safe condition. All buildings greater than six stories shall comply with the maintenance requirement of this article.

Exception: The requirements imposed by this article shall not apply to any part of an exterior wall that is less than 12 inches (305 mm) from the exterior wall of an adjacent building.

§ 28-302.2. Inspection requirements

Open this section

A critical examination of a building's exterior walls and appurtenances thereof shall be conducted at periodic intervals as set forth by rule of the commissioner, provided such periodic intervals are between 6 to 12 years. The initial examination for a new building shall be conducted in the eighth year following the erection or installation of any exterior wall or appurtenances as evidenced by the issuance date of a temporary or final certificate of occupancy or as otherwise prescribed by rule.

1. Such examination shall be conducted on behalf of the building owner by or under the direct supervision of a registered design professional with appropriate qualifications as prescribed by the department.

2. Such examination shall include a complete review of the most recently prepared report and an inspection.

3. Such examination shall be conducted in accordance with rules promulgated by the commissioner.

(Am. L.L. 2021/126, 11/7/2021, eff. 11/7/2022; Am. L.L. 2025/049, 4/17/2025, eff. 10/1/2026)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2007/038, L.L. 2021/126, and L.L. 2025/049.

§ 28-302.3. Immediate notice of unsafe condition

Open this section

Whenever a registered design professional learns of an unsafe condition through a critical examination of a building's exterior walls and appurtenances thereof, such person shall notify the owner and the department immediately in writing of such condition.

§ 28-302.4. Report of critical examination

Open this section

The registered design professional shall submit a written report to the commissioner within 60 days of completing the critical examination, at least once during each five-year report filing cycle, as defined by rule of the department certifying the results of such critical examination as either safe, unsafe or safe with a repair and maintenance program. The report shall clearly document the condition of the exterior walls and appurtenances thereof and shall include a record of all significant deterioration, unsafe conditions and movement observed as well as a statement concerning the watertightness of the exterior surfaces. Such report must be signed and sealed by such registered design professional.

(Am. L.L. 2021/126, 11/7/2021, eff. 11/7/2022)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2021/126.

§ 28-302.5. Repair of exterior walls, unsafe condition

Open this section

Upon the notification to the department of an unsafe condition, the owner, the owner's agent or the person in charge shall immediately commence such repairs, reinforcements or other measures as may be required to secure public safety and to make the building's exterior walls or appurtenances thereof conform to the provisions of this code.

1. All unsafe conditions shall be corrected within 90 days of filing the critical examination report.

2. The owner shall engage a registered design professional to reinspect the premises and file an amended report within two weeks after the repairs have been completed certifying that the unsafe conditions of the building have been corrected.

3. The commissioner may grant an extension of time of up to 90 days to complete the repairs required to correct an unsafe condition upon receipt and review of an initial extension application submitted by the registered design professional together with such additional documentation as may be prescribed by rule.

4. The commissioner may grant further extensions of time to complete the repairs required to remove an unsafe condition upon receipt and review of an application for a further extension submitted by the registered design professional together with such further documentation as may be prescribed by rule.

(Am. L.L. 2021/126, 11/7/2021, eff. 11/7/2022)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2021/126.

§ 28-302.6. Safe condition with a repair and maintenance program

Open this section

The registered design professional shall not file a report of a safe condition with a repair and maintenance program for the same building for two consecutive filing periods unless the second such report is accompanied by his or her professional certification attesting to the correction of all conditions identified in the prior report as requiring repair.

§ 28-303.1. General

Open this section

Periodic boiler inspections shall be performed in accordance with this article and the provisions of section 1011.3 of the New York city mechanical code.

(Am. L.L. 2021/126, 11/7/2021, eff. 1/1/2022)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2021/126.

§ 28-303.2. Annual inspections

Open this section

Except as otherwise provided in this article, each owner of a boiler, as defined in section 204 of the New York state labor law, excepting those boilers listed in subdivision five of such section of such labor law, shall have such boiler inspected at least once a year in accordance with this article. All individuals who perform periodic inspections pursuant to this article shall be qualified under section 204 of the New York state labor law and the rules promulgated by the commissioner of labor or the commissioner of buildings.

§ 28-303.2.1. Internal inspection required

Open this section

All high-pressure boilers shall have an annual internal inspection performed in accordance with section 204 of New York State Labor Law and the rules of the department. Where construction of a low-pressure boiler allows, an internal inspection shall be performed on a periodic schedule in accordance with section 204 of the New York State Labor Law and the rules of the department.

(Am. L.L. 2023/077, 6/11/2023, eff. 6/11/2023)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2023/077.

§ 28-303.2.2. External inspection required

Open this section

All high- and low-pressure boilers shall have an annual external inspection performed in accordance with section 204 of New York State Labor Law and the rules of the department. Such inspection shall include chimney connectors.

(Am. L.L. 2023/077, 6/11/2023, eff. 6/11/2023)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2023/077.

§ 28-303.2.3. Electric high-pressure boilers

Open this section

Electric boilers operating at pressures or temperatures classified as high-pressure boilers, as defined in the New York city mechanical code, shall be annually inspected as high-pressure boilers in accordance with this article.

(L.L. 2021/126, 11/7/2021, eff. 1/1/2022; Am. L.L. 2023/077, 6/11/2023, eff. 6/11/2023)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2021/126 and L.L. 2023/077.

§ 28-303.3. Qualifications of boiler inspectors

Open this section

All individuals who perform periodic inspections pursuant to this article shall have the qualifications set forth in the rules of the department and in section 28-303.3.1 or section 28-303.3.2 of this code, as applicable.

(Am. L.L. 2021/126, 11/7/2021, eff. 1/1/2022)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2021/126.

§ 28-303.3.1. High-pressure boilers

Open this section

Inspections required by section 28-303.2 of this code for a high-pressure boiler must be performed, in accordance with the rules of the department, on behalf of the owner, by boiler inspectors in the employ of a duly authorized insurance company who are qualified in accordance with section 204 of the New York State Labor Law.

(L.L. 2021/126, 11/7/2021, eff. 1/1/2022; Am. L.L. 2023/077, 6/11/2023, eff. 6/11/2023)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2021/126 and L.L. 2023/077.

§ 28-303.3.2. Low-pressure boilers

Open this section

Inspections required by section 28-303.2 of a low-pressure boiler must be performed, in accordance with the rules of the department, on behalf of the owner, by boiler inspectors who are qualified in accordance with section 204 of the New York State Labor law.

(Am. L.L. 2021/126, 11/7/2021, eff. 1/1/2022)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2021/126.

§ 28-303.4. Staggered inspection cycles

Open this section

The commissioner may by rule establish staggered inspection cycles for buildings required to comply with this article.

§ 28-303.5. Repair of defects

Open this section

The owner of each boiler that is subject to periodic inspection shall correct any defects identified in the annual boiler inspection.

§ 28-303.6. Reporting an unsafe or hazardous condition

Open this section

If an inspection reveals that any boiler is unsafe or hazardous to life and safety, the device is to be immediately taken out of service by the approved boiler inspection agency performing the inspection and the building owner shall be notified. Such agency shall notify the department of the unsafe or hazardous condition of the boiler within 24 hours after the condition is discovered. Notification to the department may be made by telephone, electronically or in writing.

(Am. L.L. 2021/126, 11/7/2021, eff. 1/1/2022)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2021/126.

§ 28-303.7. Owner's annual boiler inspection report

Open this section

The owner of each boiler that is subject to inspection pursuant to section 28-303.2 shall file a signed annual report with the commissioner in accordance with the rules of the department within 14 days after the required annual inspection of the boiler has been performed. Extensions of time to file such report may be granted in accordance with the rules of the department. The report shall include, but shall not be limited to:

1. The location of the boiler.

2. The name and address of the inspector, the qualification of the inspector to perform the inspection, the date of inspection and if the inspector is a qualified boiler inspector in the employ of a duly authorized insurance company, the policy number covering the boiler.

3. A list of all defects found in the inspection for each device inspected.

(Am. L.L. 2021/126, 11/7/2021, eff. 1/1/2022)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2021/126.

§ 28-303.7.1. Affirmation of correction

Open this section

All defects identified in the annual boiler inspection report shall be corrected within 90 days after the date of initial inspection. The department may grant an extension of 45 days upon submission of an application by the owner demonstrating a practical difficulty in complying within the 90 day timeframe. In no case shall a single extension request be granted for more than 45 days, and no more than two such extensions be granted for a specific defect. An affirmation of correction shall be filed within 14 days of the date of correction.

(Am. L.L. 2021/126, 11/7/2021, eff. 1/1/2022)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2021/126.

§ 28-303.8. Scope of inspection

Open this section

During required inspection and testing, in addition to any other requirements prescribed by this code or the rules of the department, all parts of the equipment shall be inspected to determine that they are in safe operating condition and that parts subject to wear have not worn to such an extent as to affect the safe and reliable operation of the boiler.

§ 28-303.9. Removal or discontinuance notice

Open this section

The owner of a boiler that is removed or discontinued from use shall file a written notice of such removal or discontinuance with the commissioner within 30 days of the date of removal or discontinuance.

§ 28-303.10. Additional inspections

Open this section

In addition to the inspections required by this article, the commissioner may make such additional inspections as required to enforce the provisions of this code.

§ 28-303.11. Fees

Open this section

The owner of each boiler subject to periodic inspection pursuant to this article shall pay to the department an annual fee for each boiler in the amount prescribed by this code to cover the city's administrative and supervisory costs. The fee shall be payable at the time of the filing of the owner's annual boiler inspection report. No fee shall be charged for additional inspections made by the department pursuant to section 28-303.10.

§ 28-304.1. General

Open this section

Elevators and conveying systems shall be maintained in a safe condition and in accordance with ASME A17.1, as modified by Appendix K of the New York city building code. Every new and existing elevator or conveying system shall be inspected and tested in accordance with this article.

(Am. L.L. 2021/126, 11/7/2021, eff. 1/1/2022)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2021/126.

§ 28-304.2. Elevators, escalators, moving walkways, material lifts, man lifts and dumbwaiters

Open this section

Elevators, escalators, moving walkways, material lifts, man lifts and dumbwaiters shall be inspected and tested in accordance with section 28-304.6, chapter 30 of the New York city building code, and the schedule set forth in Table N1 of ASME A17.1 as modified by chapter K1 of appendix K of the New York city building code.

(Am. L.L. 2021/126, 11/7/2021, eff. 1/1/2022)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2008/008 and L.L. 2021/126.

§ 28-304.3. Platform lifts, stairway chair lifts and vertical reciprocating conveyors (VRCs)

Open this section

Platform lifts, stairway chair lifts and VRCs shall be inspected and tested at intervals not exceeding one year. Inspections and tests shall be performed in accordance with Table N1.

(Am. L.L. 2021/126, 11/7/2021, eff. 1/1/2022)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2021/126.

§ 28-304.4. Amusement devices

Open this section

Amusement devices shall be inspected and tested in accordance with department rules.

§ 28-304.5. Frequency of inspection and testing

Open this section

Elevators and other conveying systems may be subject to more frequent inspection and testing as the commissioner finds necessary to protect public safety.

§ 28-304.6. Inspection and testing process

Open this section

All devices shall be inspected and tested in accordance with Table N1 of ASME A17.1 as modified by chapter K1 of appendix K of the New York city building code and, where applicable, department rules and with sections 28-304.6.1 through 28-304.6.6 of this code.

(Am. L.L. 2021/126, 11/7/2021, eff. 1/1/2022)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2021/126.

§ 28-304.6.1. Inspection and testing entities

Open this section

The required category tests and periodic inspections in Table N1 of ASME A17.1 as modified by chapter K1 of appendix K of the New York City building code shall be performed on behalf of the owner by an approved elevator agency in accordance with this code and department rules. Where indicated in Table N1, tests shall be witnessed by an approved elevator agency not affiliated with the agency performing the test, and not affiliated with the agency performing the elevator work. Where indicated in Table N1, inspections shall be performed by an approved elevator agency not affiliated with the agency performing the maintenance. Not affiliated, as used in this section, shall mean the approved elevator agency owners, directors and inspectors shall be independent of all relative approved elevator agencies, maintenance firms or other entities providing any associated services to the device owner. Such other tests and inspections shall comply with the timeframes established as follows:

1. Category 1 tests shall be performed between January 1st and December 31st of each year at a minimal time interval of six months from the date of the previous Category 1 testing. Category 1 tests are required on new installations the calendar year following final acceptance test.

2. Category 3 tests for water hydraulics shall be performed every three years on or before the anniversary month of the last Category 3 testing.

3. Category 5 tests shall be performed every five years on or before the month of the final acceptance test for new elevators or the anniversary month of the last Category 5 testing.

4. Periodic inspections shall be performed between January 1 and December 31 of each year at a minimum of three months from the date of any Category 1 testing or previous periodic inspection. Initial periodic inspections on new installations shall be performed in the calendar year following the final acceptance test. For private residence elevators, the periodic inspection and category testing may be performed on the same date.

(Am. 2019 N.Y. Laws Ch. 750, 1/1/2020, eff. 1/1/2022; Am. 2020 N.Y. Laws Ch. 55, 4/3/2020, eff. 1/1/2022; Am. L.L. 2021/126, 11/7/2021, eff. 1/1/2022)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2021/126.

§ 28-304.6.1.1. Department notification

Open this section

The department shall be notified by the agency performing the test at least five days prior to the Category 1 testing of escalators, Category 3 testing of water hydraulic elevators and Category 5 testing of elevators, pursuant to the rules of the department.

(Am. L.L. 2021/126, 11/7/2021, eff. 1/1/2022)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2021/126.

§ 28-304.6.2. Scope

Open this section

During periodic inspection and category testing, in addition to any other requirements prescribed by this code, all parts of the equipment shall be inspected to determine that they are in safe operating condition and that parts subject to wear have not worn to such an extent as to affect the safe and reliable operation of the installation

(Am. L.L. 2021/126, 11/7/2021, eff. 1/1/2022)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2021/126.

§ 28-304.6.3. Reporting an unsafe or hazardous condition

Open this section

If a periodic inspection or category test reveals that any elevator or other conveying system is unsafe or hazardous to life and safety, the device is to be taken out of service immediately by the agency performing the inspection or test and the building owner notified immediately. The performing agency shall notify the department by telephone, electronically or in writing within 24 hours.

(Am. L.L. 2021/126, 11/7/2021, eff. 1/1/2022)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2021/126.

§ 28-304.6.4. Periodic inspection and category testing reports and notations on the inspection certificate

Open this section

Periodic inspection and category testing reports and notations on the inspection certificate shall comply with the requirements of sections 28-304.6.4.1, 28-304.6.4.2, and 28-304.6.4.3.

(Am. L.L. 2021/126, 11/7/2021, eff. 1/1/2022; Am. L.L. 2023/077, 6/11/2023, eff. 6/11/2023)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2021/126 and L.L. 2023/077.

§ 28-304.6.4.1. Periodic inspections

Open this section

For the periodic inspections listed in Table N1 of ASME A17.1, as modified by chapter K1 of appendix K of the New York city building code, the performing inspector shall, on the day of each inspection: (i) complete the periodic inspection report, documenting all violating conditions, if any, and affix his or her signature; (ii) provide a copy of such report to the owner or owner's representative; and (iii) affix the date and his or her signature over a stamp identifying his or her approved elevator agency and his or her approval number on the inspection certificate issued by the department attesting to completion of items (i) and (ii). No witnessing agency is required to witness the periodic inspections.

(Am. L.L. 2021/126, 11/7/2021, eff. 1/1/2022)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2021/126.

§ 28-304.6.4.2. Category testing when a witnessing agency is required

Open this section

When a witnessing agency is required to witness category tests listed in Table N1 of ASME A17.1, as modified by chapter K1 of appendix K of the New York city building code, the performing inspector shall, on the day of each test complete the category test report, documenting all violating conditions, if any, and affix his or her signature; and provide a copy of such report to the owner or owner's representative with the witnessing agency inspector signature. The witnessing agency inspector shall, on the day of each test: (i) review and confirm the category test report and also affix his or her signature to it; (ii) confirm that a copy of such report was provided to the owner or owner's representative; and (iii) affix the date and his or her signature over a stamp identifying his or her approved elevator agency and his or her approval number on the inspection certificate issued by the department attesting to the completion of items (i) and (ii).

(Am. L.L. 2021/126, 11/7/2021, eff. 1/1/2022)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2021/126.

§ 28-304.6.4.3. Category testing when no witnessing agency is required

Open this section

When no witnessing agency is required to witness the category tests listed in Table N1 of ASME A17.1, as modified by chapter K1 of appendix K of the New York city building code, the performing inspector shall, on the day of each test: (i) complete the category test report, documenting all violating conditions, if any, and affix his or her signature; (ii) provide a copy of such report to the owner or owner's representative; and (iii) affix the date and his or her signature over a stamp identifying his or her approved elevator agency and his or her approval number on the inspection certificate issued by the department attesting to completion of items (i) and (ii).

(L.L. 2021/126, 11/7/2021, eff. 1/1/2022)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2021/126.

§ 28-304.6.5. Periodic inspection or category test reports submission

Open this section

Periodic inspection or category test reports shall be submitted to the department on such forms and in such manner as required by the commissioner. Such reports shall comply with the following and department rules.

(Am. L.L. 2021/126, 11/7/2021, eff. 1/1/2022)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2021/126.

§ 28-304.6.5.1. Periodic inspection reports

Open this section

Reports of periodic inspections shall comply with the following:

1. The reports shall contain the signatures of (i) the performing agency director, and (ii) the building owner.

2. The reports, with all applicable signatures, shall be filed with the department within 14 days after the date of the inspection.

(L.L. 2021/126, 11/7/2021, eff. 1/1/2022)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2021/126.

§ 28-304.6.5.2. Category test reports

Open this section

Reports of category tests shall comply with the following:

1. The reports shall contain signatures of (i) the performing agency inspector and director, (ii) the witnessing agency director, if required under Table N1 of ASME A17.1 as modified by chapter K1 of appendix K of the New York city building code, and (iii) the building owner.

2. The completed reports, with all applicable signatures, shall be filed with the department within 21 days after the date of the test.

Exception: Reports are not required to be submitted to the department for private residence wheelchair lifts and private residence dumbwaiters devices. However, the owner shall maintain an inspection and test log to be available to the department upon request.

(L.L. 2021/126, 11/7/2021, eff. 1/1/2022)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2021/126.

§ 28-304.6.6. Periodic inspection and category testing repair

Open this section

All defects as found in periodic inspection and category testing reports shall be corrected in accordance with the requirements of sections 28-304.6.6.1 and 28-304.6.6.2 of this code, except that all hazardous conditions and defects related to firefighters' Phase I emergency recall operations or Phase II emergency in-car operation as required by section 3003.2 of the New York city building code shall be corrected immediately.

(Am. L.L. 2021/126, 11/7/2021, eff. 1/1/2022)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2021/126.

§ 28-304.6.6.1. Category test repair

Open this section

All defects as found in such category test report shall be corrected within 90 days after the date of inspection. The department may grant an extension of 45 days upon submission of an application by the owner demonstrating a practical difficulty in complying within the 90 day timeframe. In no case shall more than two such extensions be granted for a specific defect. An affirmation of correction shall be filed within 14 days after the date of correction.

(L.L. 2021/126, 11/7/2021, eff. 1/1/2022)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2021/126.

§ 28-304.6.6.2. Periodic inspection repair

Open this section

Editor's note: this section has been amended by L.L. 2026/042, 1/17/2026, eff. 1/1/2027.

All defects as found in such periodic inspection report shall be corrected within 90 days after the date of test. An affirmation of correction shall be filed within 14 days of the date of correction.

(L.L. 2021/126, 11/7/2021, eff. 1/1/2022)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2021/126.

§ 28-304.7. Required contract

Open this section

The owner of all new and existing passenger elevators, freight elevators, and escalators shall have a contract with an approved elevator agency to perform elevator and escalator maintenance, repair and replacement work as defined by ASME A17.1 as modified by chapter K1 of appendix K of the New York city building code. The name, address and telephone number of such agency shall be maintained at each premises, on the mainline disconnect switch and in a location readily accessible to employees of the department and to maintenance and custodial staff at the premises.

(Am. L.L. 2021/126, 11/7/2021, eff. 1/1/2022)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2021/126.

§ 28-304.8. Fees

Open this section

Editor's note: this section has been amended by L.L. 2026/042, 1/17/2026, eff. 1/1/2027.

Every owner of elevators and other devices shall pay to the department a report filing fee for each elevator or device in the amount prescribed by the department's rules.

(Am. L.L. 2021/126, 11/7/2021, eff. 1/1/2022)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2021/126.

§ 28-304.9. Additional inspections

Open this section

The commissioner may make such additional inspections as required to enforce the provisions of this code. No fee shall be charged for such additional inspections.

§ 28-304.10. Occupant notification for elevator work

Open this section

In occupancy groups R-1 and R-2, when an elevator is to be out of service, a notice identifying the type of work to be performed and the expected start and end dates for such outage shall be provided in English, Spanish, and such other languages as the department may provide by rule, in accordance with sections 28-304.10.1 and 28-304.10.2.

(Am. L.L. 2015/047, 6/2/2015, eff. 9/30/2015)

§ 28-304.10.1. Occupant notification for alteration work

Open this section

When an elevator is to be out of service for alteration work, notice shall be given to the residential occupants no fewer than 10 business days before the start of the work, except in case of emergency repairs. This notification requirement does not apply to minor alterations and ordinary repairs.

(L.L. 2015/047, 6/2/2015, eff. 9/30/2015)

§ 28-304.10.2. Occupant notification for other elevator service outages

Open this section

When all elevators servicing a building or any section of a building are expected to be out of service for two or more hours, notice shall be posted at least twenty-four hours before the start of the work. When all elevators servicing a building or any section of a building are expected to be out of service for less than two hours, or are out of service as the result of emergency work, notice is not required to be posted, except that where such outage lasts for two or more hours, notice shall be posted as soon as practicable after the commencement of such service outage.

(L.L. 2015/047, 6/2/2015, eff. 9/30/2015)

§ 28-305.1. Retaining walls, partition fences and other site structures

Open this section

In addition to the requirements set forth in chapter 33 of the New York city building code, the responsibility for maintaining and repairing retaining walls, partition fences and other site structures shall be in accordance with sections 28-305.1.1, 28-305.1.2 and 28-305.4.

(Am. L.L. 2021/126, 11/7/2021, eff. 11/7/2022)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2021/126.

§ 28-305.1.1. Structures located on the lot line of adjacent properties and partially on both properties

Open this section

The owners of adjacent properties shall be responsible jointly for the proper maintenance and repair of retaining walls, partition fences and other site structures, or portions thereof, that are located along the common lot line and on both their properties; and each such owner shall be responsible for one-half of the costs of maintaining and repairing such fences, retaining walls and other site structures, or such portions thereof. Where an owner elects to remove temporarily a retaining wall or partition fence that is required to support a grade differential between the two properties, or for any other reason is required by this code, such owner shall protect the adjacent property, shall not impair its safe use, and shall replace the retaining wall or partition fence at his or her own cost. Refer to chapter 33 of the New York city building code for additional requirements during construction and demolition operations.

(Am. L.L. 2021/126, 11/7/2021, eff. 11/7/2022)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2021/126.

§ 28-305.1.2. Structures located entirely on one property

Open this section

Where such retaining walls, partition fences or other site structures, or portions thereof, are located entirely on one property, the owner of such property shall be wholly responsible for the proper maintenance and repair of the retaining wall, partition fence or other site structure. If, however, the proper maintenance and/or repair of such retaining wall, partition fence or other site structures requires access to the adjoining property, the owner of such adjoining property shall allow such access. Refer to chapter 33 of the New York city building code for additional requirements during construction and demolition operations.

(Am. L.L. 2021/126, 11/7/2021, eff. 11/7/2022)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2021/126.

§ 28-305.2. Retaining walls required

Open this section

Hereafter, when an owner elects to set his or her grade either higher or lower than the grade of an adjoining property at the property line, such owner shall erect, maintain and repair a retaining wall of sufficient height, structure and foundation to support such grade differential, and with proper drainage, in accordance with this code, such that the adjacent property is not impacted, and shall do so at the sole expense of such owner and entirely on the property of such owner without access to the adjoining property.

§ 28-305.3. Special agreement

Open this section

Nothing in this article shall be construed to prevent the owners of adjacent properties from making or enforcing by private action special agreements with respect to maintenance or repair of retaining walls, partition fences and other site structures or access to adjoining property for such purpose.

§ 28-305.4. Maintenance, inspection and repair of retaining walls

Open this section

Maintenance, inspection and repair of retaining walls shall comply with sections 28-305.4.1 through 28-305.4.8.

§ 28-305.4.1. Definition

Open this section

As used in this article, the following term shall have the following meaning:

RETAINING WALL. A wall that resists lateral pressures and limits lateral displacement caused by soil, rock, water or other materials, except that basement and vault walls that are part of a building, underground structures, including but not limited to utility vault structures, tunnels, transit stations and swimming pools, shall not be considered retaining walls.

§ 28-305.4.2. Owner's responsibility

Open this section

Owners of retaining walls with a height of ten feet or more and fronting a public right-of-way shall comply with the requirements of this section. For the purposes of this section, the height of a retaining wall shall be the distance from the top of the ground in front of the wall to the top of the wall stem, or wall step for stepped walls, including any parapets or fencing capable of retaining material.

§ 28-305.4.3. Condition assessment requirements

Open this section

A condition assessment of a retaining wall shall be conducted at periodic intervals as set forth by rule of the commissioner, but such assessment shall be conducted at least once every five years. The commissioner may establish staggered assessment cycles for retaining walls required to comply with this section.

(Am. L.L. 2021/126, 11/7/2021, eff. 11/7/2022)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2021/126.

§ 28-305.4.3.1. Registered design professional

Open this section

The condition assessment shall be conducted on behalf of the owner by or under the direct supervision of a registered design professional with appropriate qualifications as prescribed by the department.

§ 28-305.4.3.2. Department rules

Open this section

The condition assessment shall be conducted in accordance with rules promulgated by the commissioner.

§ 28-305.4.4. Report of condition assessment

Open this section

A report of condition assessment shall be submitted to the department in accordance with sections 28-305.4.4.1 and 28-305.4.4.2.

§ 28-305.4.4.1. Submission deadlines

Open this section

Except as otherwise provided in section 28-305.4.6, the registered design professional shall submit a written report to the commissioner within 60 days of completing the assessment, but not more than five years following submission of the preceding report of assessment, certifying the results of the assessment.

(Am. L.L. 2021/126, 11/7/2021, eff. 11/7/2022)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2021/126.

§ 28-305.4.4.2. Contents

Open this section

The report shall certify the results of the assessment as either safe, safe with minor repair or safe with repair and/or engineering monitoring, as prescribed by rules of the department. The report shall clearly document the condition of the retaining wall and shall include a record of all significant deterioration, potentially unsafe conditions of the wall or affecting the wall, and movement observed. The report must be certified by the registered design professional.

§ 28-305.4.5. Fees

Open this section

Every owner of a retaining wall shall pay to the department a report filing fee for each report of condition assessment in the amount prescribed by this code.

§ 28-305.4.6. Immediate notice of unsafe condition

Open this section

Whenever the registered design professional under whose supervision the inspection is performed learns of an unsafe condition through a condition assessment of a retaining wall, such person shall notify the owner and the department of such condition immediately by calling 311 and by written notification to the department.

§ 28-305.4.7. Repair of unsafe condition

Open this section

Upon the notification to the department of an unsafe condition, the owner or the owner's agent shall immediately commence such repairs, reinforcements or other measures as may be required to secure public safety.

§ 28-305.4.7.1. Permit

Open this section

The owner or the owner's agent shall obtain a permit within the time set forth in the rules of the department in order to correct the unsafe condition, after securing public safety as provided above.

§ 28-305.4.7.2. Monitoring

Open this section

The owner or the owner's agent shall monitor the protection of public safety until the unsafe condition is remedied.

§ 28-305.4.7.3. Reinspection

Open this section

The owner or the owner's agent shall reinspect the retaining wall and file an amended report within two weeks after the repairs have been completed certifying that the unsafe conditions of the retaining wall have been corrected.

§ 28-305.4.7.4. Extension

Open this section

The commissioner may grant an extension of time of up to 90 days from the date of the application for an extension to complete the repairs required to correct an unsafe condition upon receipt and review of an initial extension application submitted by the registered design professional together with such additional documentation as may be prescribed by rule.

§ 28-305.4.7.5. Further extension

Open this section

The commissioner may grant further extensions of time to complete the repairs required to remove an unsafe condition upon receipt and review of an application for a further extension submitted by the registered design professional together with such further documentation as may be prescribed by rule.

§ 28-305.4.8. Safe with repair and/or engineering monitoring

Open this section

A retaining wall or any part thereof that may pose a potential danger to persons or property, but does not require immediate action shall be rated safe with repair and/or engineering monitoring. This condition requires further investigation and timely remedial action to prevent its deterioration into an unsafe condition. A registered design professional shall be responsible for appropriately monitoring the wall until the repair is completed.

§ 28-305.4.8.1. Safe with repair and/or engineering monitoring for two cycles

Open this section

The registered design professional shall not file a report of safe with repair and/or engineering monitoring for the same retaining wall for two consecutive filing periods unless the second such report is accompanied by his or her professional certification attesting to the correction of all conditions identified in the prior report as requiring repair.

(Am. L.L. 2021/126, 11/7/2021, eff. 11/7/2022)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2021/126.

§ 28-305.5. Removal of retaining structures

Open this section

Any retaining structure, standing partly on the land of each owner, may be removed by either owner when the original reason for the erection of such retaining structure ceases to exist. Notification shall be provided to the adjoining property owner.

(L.L. 2021/126, 11/7/2021, eff. 11/7/2022)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2021/126.

§ 28-306.1. Responsibility for party walls

Open this section

Repair and maintenance of the construction, design and fire-resistance rating of party walls shall be the joint responsibility of the owners of the adjoining properties, and any change by either owner must maintain the weather protection, structural, vertical fire division and other requirements of this code for party walls.

§ 28-306.2. Safeguards during construction or demolition

Open this section

Refer to section 3309 of the New York city building code for additional requirements for the maintenance of party walls during construction or demolition operations.

(Am. L.L. 2021/126, 11/7/2021, eff. 11/7/2022)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2021/126.

§ 28-307.1. Obstruction of workplace exits prohibited

Open this section

Except for the exemptions specified in subdivision j of section 27-371 of the New York city administrative code or chapter 10 of the New York city building code, as applicable, it shall be unlawful for an employer or the agent of an employer to lock the doors of a workplace or otherwise obstruct or prohibit exit from a workplace when such act may endanger the health or safety of any employee, independent contractor or other individual in such workplace in the event of a fire or other hazardous condition or event. The commissioner shall classify a violation of this section as an immediately hazardous violation. Notwithstanding any other provision of this code, upon criminal conviction or civil adjudication of liability for a violation of this section an additional fine or civil penalty of not less than $5,000 nor more than $20,000 shall be imposed for each employee, independent contractor or other individual endangered by a violation of this section.

(Am. L.L. 2021/126, 11/7/2021, eff. 11/7/2022)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2021/126.

§ 28-307.1.1. Notice

Open this section

A sign shall be posted conspicuously at the workplace of a person convicted of or found liable for a violation of section 28-307.1. Such sign shall, in English, Spanish, Korean, Chinese or any other language directed by the fire commissioner, provide notice to employees of the acts prohibited by section 28-307.1 and of the remedies for employer retaliation as set forth in section 28-307.3. The sign shall be in a form and posted in a manner directed by the fire commissioner and may contain any other information deemed necessary by the fire commissioner or as recommended by the police commissioner or the commissioner. The fire commissioner may, in the interest of public safety, adopt a rule requiring the posting of such signs at other workplaces.

§ 28-307.2. Unannounced inspections of workplaces by fire department

Open this section

In addition to any other inspections required by law or rule, the fire department shall conduct a minimum of 50 unannounced workplace inspections annually to ensure the identification and abatement of any hazardous conditions in violation of section 28-307.1. Such inspections shall include, but not be limited to, sites where there are known or suspected conditions affecting employee safety and health.

(Am. L.L. 2021/126, 11/7/2021, eff. 11/7/2022)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2021/126.

§ 28-307.3. Retaliation

Open this section

It shall be unlawful for an employer or the agent of such employer to take a retaliatory action, as defined by section 740 of the New York state labor law, against an employee because of the lawful acts of such employee in furtherance of a civil or criminal enforcement proceeding arising out of the failure of such employer or agent to comply with section 28-307.1 of this code. An employee who is the victim of such retaliatory action may commence an action in any court of competent jurisdiction for the relief provided for in this section and shall be entitled to all relief necessary to make such employee whole. Lawful acts of an employee shall include, but not be limited to, assisting in the investigation and initiation of an enforcement proceeding alleging a violation of section 28-307.1 of this code, providing testimony in any such proceeding or providing other assistance in connection therewith. The relief to which such employee shall be entitled shall include, but not be limited to, (i) an injunction to restrain any adverse or retaliatory action, (ii) reinstatement to the position such officer or employee would have had but for such action, or to an equivalent position, (iii) reinstatement of full benefits and seniority rights including payment of any missed back pay, plus interest and (iv) compensation for any special damages sustained as a result of such action, including litigation costs and reasonable attorneys' fees.

(Am. L.L. 2021/126, 11/7/2021, eff. 11/7/2022)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2021/126.

Title 28, Chapter 3, Article 308. Energy Audits and Retro-Commissioning of Base Building Systems

Open this section

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2009/087.

§ 28-308.1. Definitions

Open this section

As used in this article, the following terms shall have the following meanings:

BASE BUILDING SYSTEMS. The systems or subsystems of a building that use energy and/or impact energy consumption including:

1. The building envelope.

2. The heating ventilating and air conditioning (HVAC) systems.

3. Conveying systems.

4. Domestic hot water systems.

5. Electrical and lighting systems.

Exception: The term "base building systems" shall not include:

1. Systems or subsystems owned by tenants (other than a net lessee for a term of 49 years or more, inclusive of renewal options), condominium unit owners or cooperative unit shareholders, or a system or subsystems for which a tenant bears full maintenance responsibility and that is within the tenant's leased space and/or exclusively serves such leased space.

2. Industrial processes that occur within a covered building.

BUILDING MANAGEMENT SYSTEM. A computer-based system that monitors and controls a building's mechanical and electrical equipment, such as HVAC, lighting, power, fire, and security systems, including, at a minimum, control of the heating equipment using interior temperature sensors.

CITY BUILDING. A covered building that is owned by the city and for which the city regularly pays all or part of the annual energy bills.

Exception: The term "city building" shall not include:

1. Any building that participates in the tenant interim lease apartment purchase program.

2. Any building that participates in a program administered by the department of housing preservation and development.

3. Any building managed by the New York city health and hospitals corporation.

4. Any senior college in the City University of New York system.

5. Any cultural institution that is in the Cultural Institutions Group as determined by the department of cultural affairs.

COOPERATIVE CORPORATION. A corporation governed by the requirements of the state cooperative corporation law or general business law that, among other things, grants persons the right to reside in a cooperative apartment, that right existing by such person's ownership of certificates of stock, proprietary lease, or other evidence of ownership of an interest in such entity.

COVERED BUILDING. As it appears in the records of the department of finance: (i) a building that exceeds 50,000 gross square feet (4645 m 2 ), (ii) two or more buildings on the same tax lot that together exceed 100,000 gross square feet (9290 m 2 ), or (iii) two or more buildings held in the condominium form of ownership that are governed by the same board of managers and that together exceed 100,000 gross square feet (9290 m 2 ).

Exception: The term "covered building" shall not include real property classified as class one pursuant to subdivision one of section 1802 of the real property tax law of the state of New York.

CURRENT FACILITY REQUIREMENTS. The owner's current operational needs and requirements for a building, including temperature and humidity set points, operating hours, filtration, and any integrated requirements such as controls, warranty review, and service contract review.

ENERGY AUDIT OR AUDIT. A systematic process of identifying and developing modifications and improvements of the base building systems, including but not limited to alterations of such systems and the installation of new equipment, insulation or other generally recognized energy efficiency technologies to optimize energy performance of the building and achieve energy savings, provided that such process shall not be less stringent than the Level II Energy Survey and Engineering Analysis of the 2004 edition of Procedures for Commercial Building Energy Audits published by the American Society of Heating, Refrigerating and Air-conditioning Engineers Inc. (ASHRAE).

ENERGY AUDITOR. An approved agency authorized by the department to perform energy audits and to certify audit reports required by this article. Until such time as there is a national standard establishing qualifications for persons performing energy audits and such standard has been adopted by the department, an energy auditor shall be a registered design professional with such other certification or qualification as the department deems to be appropriate. After the establishment of such a national standard, the department may adopt the qualifications of the national standard with such modifications as the department deems to be appropriate.

ENERGY EFFICIENCY REPORT. The report required to be filed pursuant to section 28-308.4.

ENERGY MANAGEMENT SYSTEM. A system incorporating interior temperature sensors and a central processing unit and controls, which are used to monitor and control gas, steam and oil usage, as is applicable, based on the need for heating.

FINANCIAL HARDSHIP (OF A BUILDING). A building shall be considered to be subject to financial hardship if the building:

1. Had arrears of property taxes or water or wastewater charges that resulted in the property's inclusion, within two years prior to the due date of an energy efficiency report, on the department of finance's annual New York city tax lien sale list;

2. Is exempt from real property taxes pursuant to sections 420-a, 420-b, 446 or 462 of the New York state real property tax law and applicable local law and the owner had negative revenue less expenses during the two tax years prior to the due date of an energy efficiency report as certified to the department by a certified public accountant;

3. Had outstanding balances under the department of housing preservation and development's emergency repair program that resulted in the property's inclusion, within two years prior to the due date of an energy efficiency report, on the department of finance's annual New York city tax lien sale list; or

4. Has an active or effective commitment letter from a governmental agency that provides for the financing of the rehabilitation, within a period of five years or less, of such building by such government agency for the purposes of affordable housing for low or moderate income families.

OWNER. The owner of record of a covered building, except that in the case of a net lease of an entire building for a term of 49 years or more, inclusive of renewal options, the term owner shall refer to the net lessee and in the case of a covered building held in cooperative or condominium form of ownership, the term owner shall refer to the board of managers in the case of a condominium and the board of directors in the case of a cooperative apartment corporation.

RETRO-COMMISSIONING. A systematic process for optimizing the energy efficiency of existing base building systems through the identification and correction of deficiencies in such systems, including but not limited to repairs of defects, cleaning, adjustments of valves, sensors, controls or programmed settings, and/or changes in operational practices.

RETRO-COMMISSIONING AGENT. An individual, who shall not be a certified refrigerating system operating engineer or a licensed high-pressure boiler operating engineer on the staff of the building being retro-commissioned, authorized by the department to certify retro-commissioning reports required by this article. Until such time as there is a national standard establishing qualifications for persons who perform retro-commissioning and such standard has been adopted by the department, a retro-commissioning agent shall be a registered design professional, a certified refrigerating system operating engineer, or a licensed high-pressure boiler operating engineer, with such other qualification or certification as determined by the department. After the establishment of such a national standard, the department may adopt the qualifications of the national standard with such modifications as the department deems to be appropriate.

SIMPLE BUILDING. A covered building with neither a central chilled water system nor a central cooling system that covers more than 10% of the building's gross area.

SIMPLE PAYBACK. The number of years for the projected annual energy savings to equal the amount invested in the energy conservation measure, as determined by dividing the investment by the annual energy savings.

SPACE. An area within a building enclosed by floor to ceiling walls, partitions, windows and doors.

SYSTEM OR SUBSYSTEM. Shall have the same definition as set forth in section 202 of the New York city energy conservation code.

(Am. L.L. 2018/106, 5/26/2018, eff. 11/22/2018; Am. L.L. 2021/126, 11/7/2021, eff. 11/7/2022; Am. L.L. 2023/077, 6/11/2023, eff. 6/11/2023)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2009/087, L.L. 2021/126, and L.L. 2023/077.

§ 28-308.2. Energy audits required

Open this section

The owner shall ensure that an energy audit is performed on the base building systems of a covered building prior to filing an energy efficiency report as required by this article. Except as otherwise provided in section 28-308.7, an energy audit shall be performed by or under the supervision of an energy auditor and shall be performed in accordance with rules promulgated by the department. The audit process shall cover the base building systems and shall identify at a minimum:

1. All reasonable measures, including capital improvements, that would, if implemented, reduce energy use and/or the cost of operating the building;

2. For each measure, the associated annual energy savings, the cost to implement, and the simple payback, calculated by a method determined by the department;

3. The building's benchmarking output consistent with the United States Environmental Protection Administration (EPA) Portfolio Manager tool or as otherwise established by the department;

4. A break-down of energy usage by system and predicted energy savings by system after implementation of the proposed measures; and

5. A general assessment of how the major energy consuming equipment and systems used within tenant spaces impact the energy consumption of the base building systems based on a representative sample of spaces.

Exceptions:

1. No energy audit is required if the building complies with one of the following as certified by a registered design professional:

1.1. The covered building has received an EPA Energy Star label for at least two of the three years preceding the filing of the building's energy efficiency report.

1.2. There is no EPA Energy Star rating for the building type and a registered design professional submits documentation, as specified in the rules of the department, that the building's energy performance is 25 or more points better than the performance of an average building of its type over a two-year period within the three-year period prior to the filing of an energy efficiency report consistent with the methodology of the Leadership in Energy and Environmental Design (LEED) 2009 rating system for Existing Buildings published by the United States Green Building Council (USGBC) or other rating system or methodology for existing buildings, as determined by the department.

1.3. The covered building has received certification under the LEED 2009 rating system for Existing Buildings published by the USGBC or other rating system for existing buildings, as determined by the department, within four years prior to the filing of the building's energy efficiency report.

2. An energy audit shall not be required for the first energy efficiency report of a simple building that is in compliance with six out of seven of the following items as certified by a registered design professional:

2.1. Individual heating controls.

(i) Each dwelling unit in the building has one or more thermostatic controls controlling all the heating units within the dwelling unit and any heated space not within a dwelling unit has one or more thermostatic controls controlling all the heating units within the space, or

(ii) the building has a central heating system controlled by an energy management system or a building management system that incorporates temperature sensors located in at least 10 percent of the dwelling units and 10 percent of the heated spaces, except that the total number of sensors required within the building shall not be less than 10 nor more than 30.

2.2. Common area and exterior lighting. Common area (lighting outside of tenant spaces) and exterior lighting, at a minimum, are in compliance with the provisions of the New York city energy conservation code as in effect for new systems installed on or after July 1, 2010.

2.3. Low flow faucets and shower heads. All faucets and showerheads within the building, at a minimum, meet the standards of table 604.4 of the New York city plumbing code as in effect for new systems installed on or after July 1, 2010.

2.4. Pipe insulation. All exposed pipes that are used to convey heat or hot water are insulated, at a minimum, in accordance with the standards of the New York city energy conservation code as in effect for new systems installed on or after July 1, 2010.

2.5. Domestic hot water. All domestic hot water tanks that do not have built-in insulation are insulated with a minimum insulation value of R-8.

2.6. Washing machines. All common area clothes washing machines are front loading.

2.7. Cool roof. The roof complies with section 1504.8 of the New York city building code as in effect for new buildings constructed on or after July 1, 2010.

(Am. L.L. 2021/126, 11/7/2021, eff. 11/7/2022)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2009/087 and L.L. 2021/126.

§ 28-308.2.1. Contents of audit report

Open this section

The energy auditor shall prepare and certify a report of the energy audit. Except as otherwise provided in section 28-308.7, the audit report shall include such information relating to the audit as shall be specified in the rules of the department, including but not limited to (i) the date that the audit was completed, and (ii) the information specified in section 28-308.2.

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2009/087.

§ 28-308.2.1.1. Compliance with landmarks laws

Open this section

The cost estimates for covered buildings that are regulated by any city, state or federal law regulating landmarks and historic buildings shall include all additional costs necessary for the proposed work to comply with such law.

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2009/087.

§ 28-308.2.2. Timing of energy audit

Open this section

Except as otherwise provided in section 28-308.7, the energy audit shall be completed no earlier than four years prior to the date on which a covered building's energy efficiency report is filed with the department pursuant to this article.

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2009/087.

§ 28-308.3. Retro-commissioning required

Open this section

The owner shall ensure that retro-commissioning is performed on the base building systems of a covered building prior to filing an energy efficiency report as required by this article. Except as otherwise provided in section 28-308.7, retro-commissioning shall be performed by or under the supervision of a retro-commissioning agent in accordance with rules promulgated by the department. Such rules, at a minimum, shall ensure that sufficient analysis, corrections and testing have been done so that the base building systems meet the following criteria demonstrating efficient operation:

1. Operating protocols, calibration, and sequencing:

1.1. HVAC temperature and humidity set points and setbacks are appropriate and operating schedules reflect major space occupancy patterns and the current facility requirements.

1.2. HVAC sensors are properly calibrated.

1.3. HVAC controls are functioning and control sequences are appropriate for the current facility requirements.

1.4. Loads are distributed equally across equipment when appropriate (i.e. fans, boilers, pumps, etc. that run in parallel).

1.5. Ventilation rates are appropriate for the current facility requirements.

1.6. System automatic reset functions are functioning appropriately, if applicable.

1.7. Adjustments have been made to compensate for oversized or undersized equipment so that it is functioning as efficiently as possible.

1.8. Simultaneous heating and cooling does not occur unless intended.

1.9. HVAC system economizer controls are properly functioning, if applicable.

1.10. The HVAC distribution systems, both air and water side, are balanced.

1.11. Light levels are appropriate to the task.

1.12. Lighting sensors and controls are functioning properly according to occupancy, schedule, and/or available daylight, where applicable.

1.13. Domestic hot water systems have been checked to ensure proper temperature settings.

1.14. Water pumps are functioning as designed.

1.15. System water leaks have been identified and repaired.

2. Cleaning and repair:

2.1. HVAC equipment (vents, ducts, coils, valves, soot bin, etc.) is clean.

2.2. Filters are clean and protocols are in place to replace, as appropriate.

2.3. Light fixtures are clean.

2.4. Motors, fans, and pumps, including components such as belts, pulleys, and bearings, are in good operating condition.

2.5. Steam traps have been replaced as required to maintain efficient operation, if applicable.

2.6. Manual overrides on existing equipment have been remediated.

2.7. Boilers have been tuned for optimal efficiency, if applicable.

2.8. Exposed hot and chilled water and steam pipes three (3) inches or greater in diameter with associated control valves are insulated in accordance with the standards of the New York city energy conservation code as in effect for new systems installed on or after July 1, 2010.

2.9. In all easily accessible locations, sealants and weather stripping are installed where appropriate and are in good condition.

3. Training and documentation:

3.1. Permits for all HVAC, electrical and plumbing equipment are in order.

3.2. Critical operations and maintenance staff have received appropriate training, which may include labor/management training, on all major equipment and systems and general energy conservation techniques.

3.3. Operational and maintenance record keeping procedures (log books, computer maintenance records, etc.) have been implemented.

3.4. The following documentation is on site and accessible to the operators: the operations and maintenance manuals, if such manuals are still available from the manufacturer, the maintenance contracts, and the most recent retro-commissioning report.

Exception: No retro-commissioning is required if the covered building has received certification under the LEED 2009 rating system for Existing Buildings published by the USGBC or other rating system for existing buildings, as determined by the department, within two years prior to the filing of the building's energy efficiency report and earned the LEED point for Existing Building Commissioning investigation and analysis and the LEED point for Existing Building Commissioning implementation.

(Am. L.L. 2021/126, 11/7/2021, eff. 11/7/2022)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2009/087 and L.L. 2021/126.

§ 28-308.3.1. Contents of retro-commissioning report

Open this section

The retro-commissioning agent shall prepare and certify a retro-commissioning report. The retro-commissioning report shall include such information relating to the retro-commissioning as shall be set forth in the rules of the department including, at a minimum:

1. Project and team information:

1.1 Building address.

1.2 Experience and certification of person performing retro-commissioning and any staff involved in the project.

1.3 Name, affiliation, and contact information for persons performing retro-commissioning and members of the retro-commissioning team, owner of building, and facility manager of building.

2. Building information:

2.1. List of all HVAC, domestic hot water, electrical equipment, lighting, and conveyance equipment types in the base building systems.

2.2. Benchmarking output.

3. Testing protocol:

3.1. List of all equipment types tested.

3.2. For each equipment type tested, a list of the sample rates (percent of each type of equipment tested), the testing methodology, including any diagnostic equipment used, and the test results.

3.3. List of integrated system testing performed.

4. Master list of findings, including for each, the name of the retro-commissioning measure and its assigned number, a brief description of the measure, recommended corrections, the benefits attained, estimated annual savings (energy and cost), the estimated implementation cost, and the simple payback.

5. Deficiencies corrected:

5.1. List of repairs completed during investigation.

5.2. List of deficiencies corrected, including, for each deficiency, the date corrected, by whom the correction was made, the actual cost, and projected savings.

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2009/087.

§ 28-308.3.2. Timing of retro-commissioning

Open this section

Except as otherwise provided in section 28-308.7, the retro-commissioning shall be completed no earlier than four years prior to the date on which a covered building's energy efficiency report is filed with the department pursuant to this article.

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2009/087.

§ 28-308.3.3. Documentation of retro-commissioning

Open this section

A copy of the latest up-to-date equipment manuals and the most recent retro-commissioning report shall be maintained at every covered building and shall be made available upon request for inspection by the department.

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2009/087.

§ 28-308.4. Energy efficiency report required

Open this section

Except as otherwise provided in section 28-308.7, the owner of a covered building shall file an energy efficiency report for such building between January first and December thirty-first of the calendar year in which such report is due pursuant to this section and between January first and December thirty-first of every tenth calendar year thereafter.

Exceptions:

1. An owner may apply for an extension of time to file an energy efficiency report if despite such owner's good faith efforts, to be documented in such application, the owner is unable to complete the required energy audit and retro-commissioning prior to the scheduled due date for such report. The commissioner may grant no more than two such extensions of no more than one year each. Extensions granted pursuant to this provision shall not extend the scheduled due dates for subsequent energy efficiency reports.

2. An owner may receive annual extensions of time to file an energy efficiency report based on financial hardship of the building.

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2009/087.

§ 28-308.4.1. Due dates

Open this section

The first energy efficiency reports for covered buildings and for new buildings shall be due in the calendar year with a final digit that is the same as the last digit of the building's tax block number, as illustrated in the following chart:

Last digit of taxblock number 0 1 2 3 4 5 6 7 8 9 Year first EERis due 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029

Owners of covered buildings (i) that are less than 10 years old at the commencement of their first assigned calendar year or (ii) that have undergone substantial rehabilitation, as certified by a registered design professional, within the 10 year period prior to any calendar year in which an energy efficiency report is due, such that at the commencement of such calendar year all of the base building systems of such building are in compliance with the New York city energy conservation code as in effect for new buildings constructed on and after July 1, 2010, or as in effect on the date of such substantial rehabilitation, whichever is later, may defer submitting an energy efficiency report for such building until the tenth calendar year after such assigned calendar year.

Exceptions:

1. A city building constructed after December 28, 2009 shall be added to such schedule within 10 years after the issuance of the first certificate of occupancy for such building. Copies of energy efficiency reports submitted to the department with respect to city buildings that are not submitted by the department of citywide administrative services shall also be submitted to the department of citywide administrative services.

2. A cooperative corporation that owns multiple covered buildings located on different tax block numbers, that is required to file an energy efficiency report for more than one covered building in different calendar years, may consolidate all such energy efficiency reports into one report, disaggregated by covered building, due no later than the year in which the last energy efficiency report would be due, which shall be accepted by the department in satisfaction of the requirements of this section for each covered building included in such consolidated report.

(Am. L.L. 2018/106, 5/26/2018, eff. 11/22/2018; Am. L.L. 2021/126, 11/7/2021, eff. 11/7/2022)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2009/087 and L.L. 2021/126.

§ 28-308.4.2. Combined audit and retro-commissioning

Open this section

Nothing in this article shall prevent an owner from performing the audit and the retro-commissioning in a combined process, provided that all the requirements of sections 28-308.2 and 28-308.3 are met.

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2009/087.

§ 28-308.5. Content of energy efficiency report

Open this section

Except as otherwise provided in section 28-308.7, the energy efficiency report shall include, in a format prescribed by the department, (i) the energy audit report or documentation substantiating that an exception as set forth in section 28-308.2 applies to such building, and (ii) the retro-commissioning report or documentation substantiating that an exception as set forth in section 28-308.3 applies to such building.

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2009/087.

§ 28-308.6. Notification by the department of finance

Open this section

The department of finance shall notify the owner of the requirements of this article three years prior to the calendar year in which the covered building's energy efficiency report is due and in the calendar year prior to the calendar year in which such report is due.

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2009/087.

§ 28-308.7. Rules

Open this section

The department shall promulgate such rules as are necessary to carry out the provisions of this article in a timely manner, which may include separate fees for filing and review of applications and reports filed pursuant to this article.

(Am. L.L. 2021/126, 11/7/2021, eff. 11/7/2022)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2009/087 and L.L. 2021/126.

Title 28, Chapter 3, Article 309. Benchmarking Energy and Water Use and Disclosure of Energy Efficiency Scores and Grades

Open this section

(Am. L.L. 2018/033, 1/8/2018, eff. 1/8/2018).

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2018/033.