1 RCNY Chapter 4000 Electrical Code
§ 4000-01. Electrical Work Review
(a) Electrical work review. Electrical work review is required in the following circumstances:
(1) Electrical installations. Electrical Plan review (EPR) is required in accordance with Section 110.2(B) of the New York city electrical code (“Electrical Code”).
(i) A new installation of equipment totaling 1000 KVA or higher;
(ii) Any change in an installation with a rating of 1000 KVA or higher, up to and including the second level overcurrent protection, unless it was fully described and approved as “future” on the original approved plan.
(iii) Any addition to an existing installation which would bring the total to 1000 KVA or higher.
(iv) A new installation or revised installation above 600 volts, irrespective of KVA rating.
(v) The addition of any equipment in a room, which would affect clearances around the equipment of a 1000 KVA installation.
(2) Electrical equipment. Electrical equipment review is required for electrical equipment not specifically addressed in the Electrical Code Technical Standards and any other electrical equipment not bearing the label of approval of an electrical testing laboratory acceptable to the Commissioner.
(b) Filing requirements.
(1) EPR. Filings for installations referenced in paragraph (1) of subdivision (a) of this rule must comply with the following:
(i) Submission of all required documents, including all drawings, must be made in a manner prescribed by the Department, including electronically, by a New York State Licensed and Registered Professional Engineer or a New York State Licensed and Registered Architect.
(ii) A filing fee of $650.00 must be paid for each submission.
(iii) All submissions must include a one-line diagram, a plan view, and, if required, an equipment room layout and be in accordance with the following requirements:
- One line diagram
- Plan view / service equipment room layout
- Submissions must be in accordance with, and include, the following requirements:
(A) All drawings must be clear, legible, and use standard notations.
(B) Installations that are not all new must clearly mark what is new and what is existing. In addition, all new work must be encircled by a ‘bubble' or ‘cloud' on the drawings.
(C) For residential installations, the calculations justifying a de-rating of the neutral must be submitted.
(D) The plan view must be drawn to scale, showing the point of service entrance into the building. If the building sets back from the property line, the underground service feeder must be shown, including wire and raceway sizes.
(E) The arrangement of service equipment and its proximity to the point of service entrance must be shown, including the manner in which service will be extended to the service equipment. If the switchboard is free standing, the clearance around the switchboard must be shown.
(F) The location of the main switchboard and/or distribution panels in relation to the service equipment must be shown.
(G) The location of the electric service room with respect to the surrounding areas must be shown.
(H) The means of egress from the switchboard room and where it leads to must be shown. The legal exit(s) to which egress door(s) lead must also be shown.
(I) When there is more than one service location within a building, drawings must contain a notation indicating that signs are posted at the entrance door of each switchboard room showing the location of all the other switchboard rooms. The location and wording of the signs must be specified.
(J) If the existing service equipment and/or point of service entrance is to be discontinued, the drawings must so state.
(K) If existing service equipment is to remain in conjunction with new service equipment and is to be supplied by the same service entrance, the drawing must indicate the make and size of the existing service equipment, and the type and size of the fuses and/or circuit breakers in the existing equipment.
(L) The drawing must show grouping of service equipment at the point of service entrance.
(M) The drawing must show a method of cooling, with or without fresh air circulation, to prevent temperature rise in the room, when the service equipment totals 2000 KVA or larger (this may be in the form of a note on the drawing).
(N) The drawing must show the available short circuit current at the point of service entrance and at the point of change in the interrupting rating of the overcurrent protection. Where used, series ratings must be indicated.
(O) A statement confirming that all fuses and/or circuit breakers have been coordinated for selective short circuit overcurrent protection must be on the drawing.
(P) A one-line diagram must be submitted indicating the service equipment and the distribution equipment up to and including the second level overcurrent protection, showing all overcurrent devices and electrical equipment with their ampere rating, make and type, interrupting current ratings and wire sizes. Frame and trip sizes for circuit breakers must be indicated.
(Q) Drawings must indicate that transformers are properly grounded. Service and distribution equipment proposed for future installation must be marked on the drawings as "future."
(R) All voltages must be clearly shown on the drawings, which must include voltages pertaining to all of the equipment overcurrent protection up to and including the second level protection.
(S) When a generator (or other non-utility source) is part of a 1,000 KVA or greater submission and the generator itself is rated below 1,000 KVA, a one line diagram must be submitted showing how the generator is connected to the normal service. The drawings must include the grounding of the generator frame and neutral bonding if needed (four pole transfer device). If the generator is rated 1,000 KVA or larger, a room layout must be submitted along with a one line diagram.
(iv) A selective coordination report prepared by a professional engineer must be filed with the Department prior to electrical inspection. Such engineer may be different from the applicant. The report must show selective coordination was achieved, including but not limited to time-current curves (TCCs) and short circuit calculations. A summary of findings must also be included to ensure compliance with applicable codes and standards.
(v) Where installation of equipment differs from the original approved drawings, amended drawings showing the as-built condition must be filed with the Department prior to electrical inspection.
(vi) The submission of any other documentation requested by the Department.
(2) Special permission. Special permission may be granted in accordance with § 28-103.3 of the Administrative Code and § 90.4 of the Electrical Code. Request for special permission must be made electronically and comply with the following:
(i) Demonstrate practical difficulty and provide supporting documentation.
(ii) Include proposed equally safe alternative methods.
(iii) Include the appropriate filing fee as follows:
(A) For requests made under the 2011 Electrical code, a filing fee of $350.00 must be paid for each submission made where a violation was issued for failure to comply with the Electrical Code.
(B) For requests made under the 2025 Electrical Code, a filing fee must be paid as specified for a variation of the Construction Codes in 1 RCNY § 101-03.
(3) Office of Technical Certification and Research ("OTCR") review. Filings for OTCR review of electrical equipment not otherwise approved for use by the Electrical Code must comply with the following:
(i) The submission, including a cover letter, notarized application and payment, must be filed with OTCR or electronically, as the Commissioner may require.
(ii) A filing fee of $600.00 must be paid for each submission.
(iii) Payment must be made" in a form and manner as provided by the Commissioner.
(iv) The submission must contain the following:
(A) A cover letter indicating the following:
1. Type/model numbers of material/equipment being submitted for approval.
2. Items included in support of the submittal.
3. Explanatory information/comments, if applicable.
(B) A completed and notarized application for review.
(C) Two (2) brochures, or catalog data sheets, and a set of unmounted photographs or photographs.
(D) A complete test report that includes a conclusion sheet from a laboratory acceptable to the Commissioner.
(E) Equipment samples only when requested by OTCR.
Additionally, a field evaluation may be performed whenever the Electrical Code or the rules of the department require electrical equipment be listed or labeled and the electrical equipment is not so listed or labeled.
(c) Compliance with the New York City Energy Conservation Code. All electrical submissions must comply with the requirements of the Energy Conservation Code where applicable.
(d) Amendments. Any amendment made to plan reviews that were filed under the Electrical Advisory Board (EAB), including Post Approval Amendment (PAAs), must be refiled in accordance with the requirements of this rule.
(Amended and renumbered* City Record 6/11/2019, eff. 7/11/2019; amended City Record 11/21/2025, eff. 12/21/2025)
* Editor's note: Formerly 1 RCNY § 34-05.
§ 4000-02. Electrical Code Revision and Interpretation Committee
In accordance with section 83.2(4) of the Electrical Code, the Commissioner shall appoint a special committee to be known as the "electrical code revision and interpretation committee". The committee may propose to the Commissioner local amendments to the NEC and shall, upon request, provide interpretations and clarifications of the Electrical Code Technical Standards. The number of members and their organizational affiliations shall be at the discretion of the Commissioner. The members of the committee shall be appointed and shall serve at the pleasure of the Commissioner. The Committee shall have a Chair, Vice-Chair and Secretary appointed annually by the Commissioner. All proposed local amendments to the NEC adopted or considered for adoption by the city shall be submitted to the committee for review.
(Amended and renumbered* City Record 11/21/2025, eff. 12/21/2025)
* Editor's note: Formerly 1 RCNY § 34-06.
§ 4000-03. Electrical Code Advisory Committee
In accordance with section 83.2(4) of the Electrical Code, the Commissioner shall appoint a special committee to be known as the "electrical code advisory committee". The committee shall advise the Commissioner regarding the approval of local amendments to the NEC proposed by the Electrical Code Revision and Interpretation Committee and the implementation of such amendments, and shall act as a conduit between the Department and the electrical industry regarding such proposed amendments and their implementation. The members of the committee shall be appointed annually and shall serve at the pleasure of the Commissioner. The number of members and their organizational affiliations shall be at the discretion of the Commissioner. The Committee shall have a Chair, Vice-Chair and Secretary appointed annually by the Commissioner. The Commissioner shall submit all local amendments to the edition of the National Fire Protection Association NFPA 70 NEC currently adopted or being considered for adoption by the city to the committee for review.
(Amended and renumbered* City Record 11/21/2025, eff. 12/21/2025)
* Editor's note: Formerly 1 RCNY § 34-07.
§ 4000-04. Designation of Private Agencies to Perform Electrical Inspections in the City of New York
(a) Grounds for certification and renewal of certification. The Commissioner may grant and each January thereafter renew certification of private electrical inspection agencies, provided:
(1) the agency applying for certification certifies in writing that each of the inspectors it shall employ to conduct the inspections permitted by § 83.2(1)(b) of the Electrical Code shall possess five years of experience as an electrician or inspector of electrical installation; or three years of experience as an electrician or inspector of electrical installation plus two years of education at an accredited college technical school in a program emphasizing courses in electrical installations or education toward a baccalaureate degree in Electrical Engineering or Engineering Technology with an emphasis on electrical installation or repair. Two of the requisite years of working experience as an electrician or inspector of electrical installation must be experience in the installation of lighting, heating and power. Experience and education must be acceptable to the Department of Buildings and is subject to the Commissioner's review and approval; and
(2) the agency possesses
(i) a general liability insurance policy in excess of $5 million, and
(ii) worker's compensation insurance for its employees and submits copies of the Insurance Certificates to the Commissioner; and
(3) the agency furnishes the names of its inspectors and documentation supporting the experience required by 1 RCNY § 4000-04(a)(1) hereof, and thereafter promptly advises the commissioner of any changes in personnel affecting the inspection permitted; and
(4) the agency prohibits its inspectors and other employees from accepting any gratuities or other benefit for work performed pursuant to these regulations and § 83.2(1)(b) of the Electrical Code; and
(5) the agency does not conduct an inspection pursuant to § 83.2(1)(b) of the Electrical Code of any work performed by any of its own officers, employees, or any other person associated with the agency; and
(6) the agency has a legal place of business within the city of New York (P.O. Box not acceptable).
(b) Right to deny or revoke certification.
(1) The Commissioner or his or her designee may deny or revoke certification where investigation reveals any of the following:
(i) the agency has failed to comply with any of the provisions enumerated in 1 RCNY § 4000-04(a);
(ii) the agency has knowingly made false or misleading statements, or knowingly falsified or allowed to be falsified any certificate, form, signed statement, application, or report filed with the department, or failed to file a report required by law or the department or willfully impeded or obstructed such filing, or induced another person to do so; (iii) the agency engages in any other conduct evidencing a willful or grossly negligent failure to comply with provisions of state or local law, or rules or regulations promulgated pursuant to statutory authority; or
(iv) the agency engages in any other conduct evidencing a departure from the standard or good character applicable to the trade of licensed electrician.
(2) Where the Commissioner or his or her designee, in his or her discretion, deems the certification of the agency shall be revoked, the agency shall be entitled to a hearing before the Office of Administrative Trials and Hearings as provided by rules promulgated by the department.
(3) Where the Commissioner or his or her designee, in his or her discretion, deems that continued certification of the agency would be likely to create a condition of imminent peril to public safety, the revocation determination shall be effective immediately. In such an instance, the agency shall be entitled to a hearing pursuant to 1 RCNY § 4000-04(b)(2) at the next available scheduled hearing session before the Office of Administrative Trials and Hearings.
(c) Contractual obligation.
(1) A contractual agreement between the agency and the City of New York is required in order for the agency to perform electrical inspections for the City of New York.
(2) Certification by the Commissioner is a prerequisite for participation in the contracting process.
(Amended and renumbered* City Record 11/21/2025, eff. 12/21/2025)
* Editor's note: Formerly 1 RCNY § 35-01.
§ 4000-06. Fire Alarm Wiring and Power Sources. [Repealed]
(Repealed City Record 12/3/2015, eff. 1/2/2016)