15 RCNY Chapter 1 Asbestos Control Program, part 2 of 2

§ 1-83 to Illustrations: 24 sections.

§ 1-83. Waste Decontamination Enclosure System

Open this section

The following procedures shall be followed for removal of asbestos-containing waste material and equipment during the conduct of abatement activities on asbestos projects: (a) The waste decontamination enclosure system shall be located outside the work area and attached to all locations through which ACM waste will be removed from the work area. A waste decontamination enclosure system shall consist of two totally enclosed chambers and shall also comply with the following requirements:

(1) the washroom shall be constructed with a curtained doorway to the work area and an airlock doorway to the holding area (see Illustration II); and be equipped with a catch basin and a drain installed to collect and deliver wastewater to either the shower drain or to a separate holding vessel where it is filtered;

(2) the holding area shall be constructed with a curtained doorway to the washroom and a lockable door to the outside (see Illustration II); if remote from the washroom, it shall comply with all applicable NYC Department of Sanitation regulations pursuant to Local Laws 70 of 1985 and 21 of 1987.

(b) Where there is only one means of egress from the work area:

(1) the holding area of the waste decontamination enclosure system may branch off from the equipment/decontamination room (see Illustration III). Thus constructed, the equipment room alternates as a waste washroom. In this case the waste washroom shall be equipped with a catch basin and a drain, installed to collect and deliver waste water to either the shower drain or a separate holding vessel from where it is filtered, or

(2) where total asbestos-containing material disturbed in the asbestos project is less than 1,000 linear feet or 1,000 square feet, the shower room may be used as a waste washroom and shall be equipped as set forth in 15 RCNY § 1-83(b)(1), and

(i) the clean room, in the configuration shown in Illustration I, may not be used for waste storage but may be used for waste transfer to carts, which are stored outside the clean room in a designated holding area.

(c) The waste decontamination enclosure system shall be constructed to meet the requirements of 15 RCNY §§ 1-82(a), (c), (d), (e), (g)(3) and (h).

§ 1-84. Small Asbestos Project Worker and Waste Decontamination Enclosure System

Open this section

The following alternative to 15 RCNY §§ 1-82 and 1-83 shall be applicable for small projects only:

(a) The worker decontamination enclosure system shall consist of, as a minimum, an equipment room, a shower room, and a clean room separated from each other and from the work area by curtained doorways. Equipment storage, personal gross decontamination and removal of disposable clothing shall occur in the equipment room prior to entering the shower. All other requirements set forth in 15 RCNY § 1-82 and 15 RCNY § 1-92 shall apply.

(b) For small asbestos projects with only one exit from the work area, the shower room may be used as a waste washroom. The clean room shall not be used for waste storage. All other requirements set forth in 15 RCNY §§ 1-83 and 1-93 shall apply.

§ 1-91. Engineering Controls

Open this section

The following procedures shall be followed during the conduct of abatement activities on asbestos projects:

(a) All asbestos projects shall utilize negative pressure ventilation equipment.

(1) On all asbestos projects, a manometer shall be used to document the pressure differential. The manometer shall be installed and made operational once the negative pressure has been established in the work area. Magnahelic manometers shall be calibrated at least every six months, and a copy of the current calibration certification shall be available at the work site.

(b) The negative pressure ventilation equipment shall operate continuously, 24 hours a day, from the establishment of isolation barriers through successful clearance air monitoring. If such equipment shuts off, adjacent areas shall be monitored for asbestos fibers.

(c) A static negative air pressure of 0.02 inches (minimum) water column shall be maintained at all times in the work place during abatement to ensure that contaminated air in the work area does not filter back to uncontaminated areas.

(d) If more than one ventilation unit is installed, units shall be turned on one at a time while checking the integrity of all barriers for secure attachment and the need for additional reinforcement.

(e) A dedicated power supply for the negative pressure ventilating units shall be utilized. The negative air equipment shall be on a ground fault circuit interrupter (GFCI) protected circuit separate from the remainder of the work area temporary power circuits.

(f) If the containment area of an asbestos project covers the entire floor of the affected building, or an area greater than 15,000 square feet on any given floor, the installation of a negative air cut off switch or switches shall be required at a single location outside the work place, such as inside a stairwell one floor below the lowest floor containing a work place, or at a secured location in the ground floor lobby when conditions warrant (such as when the work place is in a basement or below). The required switch or switches must be installed by a licensed electrician, pursuant to a permit issued by the Department of Buildings. If negative pressure ventilation equipment is used on multiple floors the cut off switch must be able to turn off the equipment on all floors.

(g) On loss of negative pressure or electric power to the negative pressure ventilating units, abatement shall stop immediately and shall not resume until power is restored and negative pressure ventilation equipment is operating again. When power failure or loss of negative pressure equipment lasts or is expected to last longer than one-half hour:

(1) the make-up air inlets shall be sealed airtight, and

(2) the decontamination systems shall be sealed airtight after the evacuation of workers and/or authorized visitors from the work area, and

(3) all adjacent areas shall be monitored for asbestos fiber concentration upon discovery of, and subsequently throughout, the power failure.

(h) Negative pressure ventilation equipment shall be installed and operated to provide at least one air change in the work area every 15 minutes. Where there are no floor or wall barriers because floor or wall material is being abated, there shall be at least one air change in the work area every ten minutes.

(i) Openings made in the isolation barrier to accommodate these units shall be made airtight. The units shall remain within the work area unless located securely outside the building.

(j) Negative air pressure equipment shall be in compliance with ANSI Z9.2 (2012), Local Exhaust Ventilation.

(k) Negative air pressure systems shall be operated in accordance with "Specifications and Operating Procedures for the Use of Negative Pressure Systems for Asbestos Abatement, Guidance for Controlling Asbestos-Containing Materials in Buildings", EPA Report Number 560/5-85-024 (1985).

(l) Negative pressure ventilation equipment shall be exhausted to the outside of the building away from occupied areas.

(1) All openings (including but not limited to operable windows, doors, vents, air intakes or exhausts of any mechanical devices) less than 15 feet from the exterior exhaust duct termination location shall be plasticized or made airtight, or a second negative pressure ventilation unit with the primary unit's capacity shall be connected in series prior to exhausting to the outside.

(2) Negative pressure ventilation equipment shall exhaust away from areas accessible to the public.

(3) All ducting must be sealed and braced or supported to maintain airtight joints. Ducts must be reinforced and must be installed so as to prevent breakage. Damage to ducts must be repaired immediately and air monitoring must be conducted in the affected space.

(m) Where ducting to the outside is not possible, a second negative pressure ventilation unit compatible with the primary unit's capacity shall be connected in series. The area receiving the exhaust shall have sufficient, non-recycling exhaust capacity to the outside of the structure, and must be a normally non-occupied area.

(n) Careful installation shall be done to ensure that the ducting does not release fibers into uncontaminated building areas.

(o) Routine smoke testing and daily inspection must be performed by the Asbestos Handler Supervisor to ensure that the ducting does not release fibers into uncontaminated building areas.

(Amended City Record 12/7/2018, eff. 1/6/2019; amended City Record 1/15/2025, eff. 2/14/2025)

§ 1-92. Work Place Entry and Exit Procedures

Open this section

The following procedures shall be followed during the conduct of abatement activities on asbestos projects:

(a) Entrance procedures.

(1) All workers and authorized visitors shall enter the work area through the worker decontamination enclosure system.

(2) All individuals who enter the work area shall sign the abatement contractor's log located in the clean room, upon each entry and exit. The abatement contractor's log shall be permanently bound and at a minimum shall identify fully the building owner, agents, contractor(s), the project, each work area and worker respiratory protection employed, and other pertinent information including daily activities, cleanings and waste transfers, names and certificate numbers of asbestos handler supervisors and asbestos handlers; results of inspections of decontamination systems, barriers, and negative pressure ventilation equipment; summary of corrective actions and repairs; work stoppages with reason for stoppage; manometer readings at least twice per work shift; daily checks of emergency and fire exits and any unusual events. The abatement contractor's log shall be available for examination during abatement activities by the Department, the owner and the workers. A copy of the abatement contractor's log shall be submitted directly to the Department within 72 hours of request.

(3) All individuals before entering the work area shall be familiar with all posted regulations, personal protection requirements and emergency procedures. The abatement contractor's log headings shall indicate, and the signatures shall be used to acknowledge, that the regulations and procedures have been reviewed and understood by all persons prior to entering the work area. The postings and abatement contractor's log headings shall be in English and in the language of the majority of the asbestos handlers.

(4) All individuals shall proceed first to the clean room, remove all street clothing, store these items in clean sealable plastic bags or a locker and don personal protective equipment. Clean personal protective equipment shall be provided by the abatement contractor and utilized by each individual for each separate entry into the work area.

(b) Exit procedures.

(1) Before leaving the work area, each individual shall remove the gross contamination from the outside of the respirators and protective clothing by wet cleaning, and/or HEPA vacuuming.

(2) In the equipment room, all personal protective equipment except respirators shall be removed. Disposable clothing shall be deposited into labeled containers for disposal. Reusable contaminated clothing, footwear, and/or head gear shall be stored in the equipment room when not in use.

(3) Still wearing a respirator, each person shall proceed to the shower room, clean the outside of the respirator and the exposed face area under running water prior to removal of the respirator, and then fully and vigorously shower and shampoo to remove residual asbestos contamination. Respirators shall be washed thoroughly with soap and water or a suitable sanitizing agent. Various types of respirators may require slight modification of these procedures.

(4) After showering and drying, personnel shall proceed to the clean room and don clean disposable clothing if returning to the work area or street clothing if remaining outside the work area.

(c) When abatement activities are located in a confined space the contractor must comply with all the requirements set forth in OSHA 29 C.F.R. 1910.146.and 1926.21(a) and (b).

(Amended City Record 12/7/2018, eff. 1/6/2019; amended City Record 4/28/2022, eff. 5/28/2022)

§ 1-93. Equipment and Waste Container Decontamination and Removal Procedures

Open this section

The following procedures shall be followed whenever equipment or containers are removed from the work area during an asbestos project:

(a) When the worker decontamination enclosure system shown in Illustration I alternates as a waste decontamination enclosure system, the clean room shall be considered a holding area during the period of active waste transfer only for the purpose of the loading of carts. Storage of waste and carts in the clean room is prohibited.

(b) Where the waste decontamination enclosure system is part of the worker decontamination enclosure system (see Illustration III), waste removal shall not occur during worker shift changes or when workers are showering or changing. Care shall be taken to prevent short circuiting and cycling of air outward through the shower and clean room.

(c) Where only one means of egress exists and the shower room is used as a waste washroom, workers are to be stationed in each room/area of the decontamination enclosure to transfer/process (see subdivisions (d), (h) and (I) of this section) the containers and equipment to or from adjacent sections. These workers are not to cross into the adjacent areas/rooms until the waste/equipment transfer is finished for that period and the workers have gone through decontaminations required by 15 RCNY § 1-92. The clean room/holding area workers shall have entered from uncontaminated areas with appropriate personal protective equipment; or prior to the start of waste transfer, these workers shall have exited the work area, fully decontaminated, and subsequently donned clean personal protective equipment.

(d) External surfaces of contaminated containers and equipment shall be cleaned by wet cleaning and/or HEPA vacuuming in the work area before transferring such items into the decontamination enclosure system. Contaminated workers shall not enter the washroom during this procedure.

(e) The cleaned containers of ACM and equipment shall be recontainerized (double-bagged) by either placing them in uncontaminated leak-tight plastic bags or sheeting as the item's physical characteristics demand while in the washroom of the waste decontamination enclosure system. Air volume shall be minimized and the bags of sheeting shall be sealed. Items that may puncture or tear the plastic bags or sheeting shall be placed in a hardwall container and sealed.

(f) The clean recontainerized items shall be moved into the airlock for subsequent transfer to the holding area. The washroom workers shall not enter this airlock or the work area until waste removal is finished for that period.

(g) Recontainerized items and cleaned equipment shall be removed from the airlock to the holding area by workers who have entered from uncontaminated areas with appropriate personal protective equipment.

(h) The recontainerized items of ACM and cleaned, bagged equipment shall be placed in open top, watertight plastic carts. These carts shall be held in the holding area pending removal. The carts shall be HEPA vacuumed or wet-cleaned following the removal of the containers of ACM from them.

(i) The exit from the waste decontamination enclosure system shall be secured to prevent unauthorized entry.

(j) The carts shall be stored in a holding area of the work site.

§ 1-94. Maintenance of Decontamination Enclosure Systems and Barriers

Open this section

The following procedures shall be followed during the conduct of abatement activities on asbestos projects:

(a) All plastic barriers inside the work place and partitions constructed to isolate the work area from occupied areas shall be inspected by the asbestos handler supervisor at least twice per shift.

(b) Smoke tubes shall be used to test the integrity of the work area barriers and the decontamination enclosure systems daily at a minimum both before abatement activity begins and at the end of each shift. A visual inspection of the barriers, including the use of differential manometers, shall be considered acceptable as a back-up test.

(c) Damage and defects in the decontamination enclosure system shall be repaired immediately. The decontamination enclosure system shall be maintained in a clean and sanitary condition at all times.

(d) At any time during the abatement activity, if visible emissions are observed, or elevated asbestos fiber counts outside the work area are measured, or if damage occurs to barriers, abatement shall stop. The source of the contamination shall be located, the integrity of the barriers shall be restored, and visible residue shall be cleaned up using appropriate HEPA vacuuming and wet cleaning procedures immediately.

(e) Inspections (including all inspections and testing required by subdivision (b) of this section), observations, and unusual incidents (e.g. barrier damage, contamination beyond the work area, etc.) must be documented in the abatement contractor’s log by the asbestos handler supervisor and in the project air sampling log.

(f) The daily inspection to ensure that exits have been checked against exterior blockage or impediments to exiting as per 15 RCNY § 1-81(t) shall be documented in the abatement contractor's log.

(g) If exits are found blocked, abatement activities shall stop until the blockage is cleared.

(Amended City Record 4/28/2022, eff. 5/28/2022; amended City Record 1/15/2025, eff. 2/14/2025)

§ 1-101. Applicability

Open this section

The following 15 RCNY §§ 1-102 through 1-110 inclusive shall apply to all abatement activities.

§ 1-102. ACM Disturbance, Handling and Removal Procedures

Open this section

The following procedures shall be followed during the conduct of abatement activities:

(a) Abatement of asbestos-containing materials shall be by wet methods. ACM shall not be removed or disturbed without being adequately wet. Dry removal of asbestos-containing material is prohibited, unless EPA approval has been obtained. The EPA-approved alternate removal plan shall be submitted to the Department for approval a minimum of 15 days before work is scheduled to begin or begins. The plan shall explain and justify why ACM must be removed dry and how asbestos fibers will be controlled to prevent their release.

(b) When amended water is used, the ACM must be sprayed with sufficient frequency and quantity for enhanced penetration. Sufficient time must be allowed for penetration to occur prior to removal action or other disturbance taking place. Accumulation of standing or free water is prohibited. Soft loosely bound ACM must be saturated. Material that resists wetting, such as tremolite or amosite, must be thoroughly wetted on all surfaces while work is being conducted.

(c) When used, removal encapsulants that minimize fiber generation and enhance penetration, shall be applied per manufacturer's specifications and in accordance with federal guidelines.

(d) ACM on detachment from the substrate is to be bagged directly or dropped onto a flexible catch basin and promptly bagged. Detached ACM is not permitted to lie on the floor for any period of time. Excess air in the bag must be minimized and the bag must be sealed. Material that resists wetting must not be dropped. ACM must not be dropped from a height greater than 10 feet. Above 10 feet in height dust-free enclosed inclined chutes may only be used inside a work area that is under negative pressure. Vertical chutes are prohibited. The angle of the chute must not exceed 60 degrees from horizontal.

(e) Large components removed intact that cannot be containerized shall be maintained wet, wrapped (minimizing excess air) in at least one layer of fire retardant 6-mil polyethylene sheeting, and secured by sealing with tape.

(f) After completion of all stripping work, surfaces from which asbestos-containing materials have been removed shall be cleaned (e.g. wet-brushed and/or wet-cleaned) to remove all visible residue.

(Amended City Record 12/7/2018, eff. 1/6/2019; amended City Record 4/28/2022, eff. 5/28/2022)

§ 1-103. Encapsulation Procedures

Open this section

All sections of these rules must be followed in conjunction with this section except 15 RCNY § 1-102(e), § 1-104, § 1-105, § 1-107 through § 1-111, § 1-112(c), (d), (e), (g), and (h).

Encapsulation procedures must be conducted with the full containment of the work area (see 15 RCNY § 1-81) or the tent procedure (see 15 RCNY § 1-106) as follows:

(a) All material used for repair or encapsulation of asbestos-containing material shall have a flame spread rating, fireproofing, and smoke characteristics similar to the material being encapsulated. The encapsulate shall not alter the insulating characteristics of the material subject to encapsulation, and shall comply with current fire proofing standards and the encapsulate shall not add excess weight to the material increasing the potential that the material may lose cohesion or adhesion.

(b) Loose or hanging asbestos-containing materials shall be removed in accordance with the requirements of 15 RCNY § 1-102 and § 1-111.

(c) Only pigmented (non-transparent) encapsulants shown to be ratable as acceptable or marginally acceptable on the basis of Battelle Columbus Laboratory test procedures and rating requirements developed under the 1978 USEPA contract shall be used for encapsulation.

(d) The encapsulant solvent or vehicle must not contain a volatile substance.

(e) Latex Paint with solids content greater than 15 percent may be used as an encapsulant only as follows:

(1) as a lockdown sealant for coating all non-metallic surfaces, or

(2) for sealing of cementitious ACM.

(f) Encapsulants shall be field tested prior to use by applying each to a small area to determine suitability of the material to be encapsulated.

(1) Testing is to occur only after the isolation barriers are in place.

(2) Testing shall be by the USEPA method specified in the appendix of "Guidelines for the Use of Encapsulants on Asbestos-Containing Materials" (June, 1981) or ASTM Standard Test Method E 736-80. The encapsulated materials shall achieve a cohesive/adhesive strength of 100 lb/ft perpendicular to the surface.

(g) Application of bridging encapsulants over ACM shall provide the manufacturer's specified number of inches or minimum dry film thickness.

(h) A different color for each coat of encapsulant (per manufacturer's specifications) shall be used.

(i) Penetrating encapsulants shall be applied to penetrate existing asbestos-containing materials to the substrate. During treatment with a penetrating encapsulant, selected random core samples of the asbestos-containing materials shall be removed to check the depth of penetration. The resulting space shall be treated as outlined (in subdivision (a)) above and re-encapsulated.

(j) Encapsulants shall be applied using airless spray equipment.

(1) Spraying shall occur at the lowest pressure range possible to minimize fiber release from encapsulant impact at the surface. It shall be applied with a consistent horizontal or vertical motion.

(2) Each subsequent coat of encapsulant shall be applied at a right angle to the preceding coat application or per manufacturer's specifications.

(k) Encapsulated asbestos-containing materials shall be identified (e.g. using labels, signs or color coding) in order to warn building maintenance personnel in the event encapsulated materials must be disturbed.

(l) The following maintenance procedures are required, except when the encapsulated material is on utility lines located in the street:

(1) A periodic inspection and maintenance program, consisting of an inspection at least annually to check for damage to all encapsulated surfaces. Recoating and repairs are to be performed according to procedures in this section.

(2) Maintenance of records by the building owner, on the locations and condition of the encapsulated material and on alteration, renovation, modification, or other procedures that resulted in disturbance of the encapsulated material.

(3) When conditions change and encapsulation is no longer an appropriate method, additional abatement methods should be conducted.

(Amended City Record 12/7/2018, eff. 1/6/2019; amended City Record 4/28/2022, eff. 5/28/2022)

§ 1-104. Enclosure Procedures

Open this section

All sections of these rules must be followed in conjunction with this section except 15 RCNY § 1-102(e), § 1-103, § 1-105, § 1-107 through § 1-111, § 1-112(c), (d), (e), (g), and (h).

Enclosure procedures must be conducted with the full containment of the work area (see 15 RCNY § 1-81) or the tent procedure (see 15 RCNY § 1-106) as follows:

(a) Loose and hanging asbestos-containing materials that may be disturbed during the installation of hangers or other support/framing materials for the enclosure shall be removed by wet methods in accordance with 15 RCNY § 1-102 and § 1-111.

(b) After installation of hangers, brackets or other enclosure supports and before installation of enclosure materials, damaged areas of fireproofing/thermal insulation shall be repaired using a replacement material.

(c) Utilities' service components shall be lowered or removed as necessary and reinstalled in a manner which permits proper utilization and does not disturb the integrity of the enclosures.

(d) Enclosed asbestos-containing materials shall be identified (e.g., using a sign, label, or color coding) in order to warn building maintenance personnel in the event that the enclosure must be disturbed.

(e) The following maintenance procedures are required:

(1) A periodic inspection and maintenance program, consisting of an inspection at least annually to check for damage to all enclosed surfaces. Re-enclosure and repairs are to be performed according to the requirements of this section.

(2) Maintenance of records by the building owner, on the locations and condition of the enclosed material and on alteration, renovation, modification, or other procedures resulting in disturbance of the enclosed material.

(3) When conditions change and enclosure is no longer an appropriate method of asbestos abatement, additional abatement methods should be conducted.

(Amended City Record 12/7/2018, eff. 1/6/2019; amended City Record 4/28/2022, eff. 5/28/2022)

§ 1-105. Glovebag Procedures

Open this section

Glovebag procedures may only be used in conjunction with the full containment of the work area (see 15 RCNY § 1-81) or the tent procedure (see 15 RCNY § 1-106).

The following procedures shall be followed during the conduct of abatement activities:

(a) Glovebag procedures must be done using commercially available glovebags of 6-mil clear plastic, appropriately sized for the project. Glovebags may not be shifted and must not be moved from the initial surface to another surface, or reinstalled on the initial surface once removed. Glovebag procedures may only be used on horizontal piping.

(b) The glovebag procedure shall be performed in accordance with the following:

(1) All necessary tools and materials shall be brought into the work area before the glovebag procedure begins.

(2) Air monitoring shall be conducted in accordance with 15 RCNY §§ 1-31 through 1-45.

(3) Glovebag procedures shall be conducted by workers specifically trained in glovebag procedures and equipped with appropriate personal protective equipment.

(4) The insulation diameter worked shall not exceed one half the bag working length above the attached gloves.

(5) The ACM within the secured glovebag shall be wetted with amended water prior to stripping.

(6) The bag shall be attached over duct tape which has been placed securely around the insulation, forming a smooth seal. The bag shall be securely attached to the insulation in a manner to prevent air transfer.

(7) After placement, each glovebag must pass a smoke test. The glovebag shall be placed under negative pressure utilizing a HEPA vacuum, and a smoke tube shall then be aspirated to direct smoke at all seams and seals from outside the glovebag. Any leaks detected by the smoke test shall be duct taped airtight.

(8) If the insulation adjacent to the section which will be worked on is damaged, or if the insulation terminates or is jointed or contains an elbow adjacent to the work section, the adjacent insulation shall be wrapped in fire retardant 6-mil polyethylene sheeting and sealed airtight with duct tape.

(9) After the insulation has been removed, the surface shall be sprayed with amended water and brush-scrubbed to remove all visible ACM. The surface, the interior of the bag, the insulation and the tools shall then be sprayed with amended water. The enclosed volume shall be misted and time allowed for the mist to settle out before breaking the seal to remove the glovebag.

(10) Any insulation ends created by this procedure shall be:

(i) sealed with encapsulant prior to bag removal, or

(ii) thoroughly wetted before bag removal and sealed with wettable cloth end caps and spray glue or any combination of these materials immediately following bag removal.

(11) The tool pouch shall be separated from the bag prior to disposal by twisting it and the wall to which it is attached several times, and taping the twist to hold it in place, thus sealing the bag and the pouch which are severed at the midpoint of the twist. Alternatively, the tools can be pulled through with one or both glove inserts, thus turning the gloves inside out. The glove(s) is/are then twist sealed forming a new pouch, taped and severed mid-seal forming two separate bags.

(12) A HEPA vacuum shall be used for evacuation of the glovebag in preparation for removal of the bag from the surface for clean-up in the event of a spill, and for post project clean-up.

(13) With the glovebag collapsed and the ACM in the bottom of the bag, the bag shall be twisted several times and taped to seal that section during bag removal.

(14) A 6-mil plastic bag shall be slipped around the glovebag while it is still attached to the surface. The bag shall be detached from the surface by removing the tape or cutting the top with blunt scissors.

(15) The asbestos-containing waste, the clean-up materials, and protective clothing shall be wetted sufficiently, double-bagged minimizing air content, sealed separately, and disposed of in conformance with 15 RCNY §§ 1-93 and 1-102.

(16) A visual clearance inspection must be conducted by the asbestos handler supervisor and project monitor after the work area dries, to ensure the absence of ACM residue or debris in the work area. The clearance inspection must be documented in the abatement contractor's log and the project air sampling log.

(c) [Reserved.]

(d) Glovebag procedures may only be utilized as part of a large or small asbestos project within full containment as set forth in 15 RCNY § 1-81, or inside a tent constructed in accordance with 15 RCNY § 1-106.

(Amended City Record 12/7/2018, eff. 1/6/2019; amended City Record 4/28/2022, eff. 5/28/2022)

§ 1-106. Tent Procedures

Open this section

All sections of these rules must be followed in conjunction with this section except 15 RCNY § 1-112(a) - (h). Tent Procedures must be conducted as follows:

(a) Tent procedures must be limited to the removal of less than 260 linear feet and 160 square feet of ACM on any individual floor and must not result in disturbance of ACM during tent erection. Tent procedures may be used as part of a large asbestos project only as provided for in 15 RCNY § 1-81(f) or in conjunction with the glovebag procedure set forth in 15 RCNY § 1-105. Multiple tent enclosures may be used as part of a large asbestos project on an individual floor only in conjunction with the use of the glovebag procedure set forth in 15 RCNY § 1-105. Multiple tent enclosures without the use of the glovebag procedure on a large asbestos project require a variance for the use of modified tent procedures and a remote worker decontamination enclosure. Air monitoring shall be conducted in accordance with 15 RCNY §§ 1-31 through § 1-45.

(b) Tent procedures must be conducted in a constructed or commercially available fire retardant plastic tent, plasticizing and sealing all surfaces and fixed objects not being abated within the tent periphery forming an enclosure. The tent must be of fire retardant 6-mil plastic at a minimum, with seams heat-sealed, or double-folded, stapled and taped airtight and then taped flush with the adjacent tent wall. This is a single use barrier that must not be reused once dismantled or collapsed.

(c) There shall be an airlock at the entrance to the tent, unless there is an attached worker or waste decontamination system.

(d) Asbestos handlers involved in the tent procedure must wear personal protective equipment as specified in 15 RCNY § 1-51(c), plus a second disposable suit. All street clothes must be removed and stored in a clean room within the work site. The personal protective equipment with two disposable suits must be used for installation of the tent and throughout the procedure if a decontamination unit with a shower is not physically connected to the tent. If a decontamination unit (with shower and clean room at a minimum) is physically connected to the tent, only one disposable suit shall be required; in this case, prior to exiting the tent, the worker must HEPA vacuum and wet clean the disposable suit.

(e) The tent shall be attached to the surface to produce an airtight seal except for an appropriate section to allow for make-up air into the tent.

(f) Negative pressure ventilation equipment shall be used to continuously exhaust the enclosed area as specified under 15 RCNY § 1-91, Engineering Controls.

(g) Removal of ACM shall be by wet methods in accordance with 15 RCNY § 1-102.

(h) ACM removed shall be placed in a leak-tight container without dropping it.

(i) Upon completion of abatement, and prior to tent collapse, the enclosed surfaces shall:

(1) be wet cleaned using rags, mops or sponges; and

(2) be permitted sufficient time to dry, prior to HEPA vacuuming all substrates; and

(3) be encapsulated to lockdown residual asbestos.

(j) Upon barrier disturbance, loss of engineering controls, or termination of tent usage, the tent and the enclosed surfaces shall be treated according to subdivision (i) above.

(k) The bagged waste shall be wet cleaned or HEPA vacuumed and then transferred outside the tent, double bagged, and appropriately handled prior to disposal.

(l) The outer disposable suit (if 2 suits are worn) shall be HEPA vacuumed in the tent prior to exiting. The outer disposable suit shall be removed in the airlock and a clean suit shall be worn over the inner suit. The workers shall immediately proceed to a shower at the work site. The inner disposable suit and respirator shall be removed in the shower after appropriate wetting. The disposable clothing shall be disposed of as asbestos-containing waste material. The workers shall then fully and vigorously shower with supplied liquid bath soap, shampoo, and clean dry towels.

(m) The negative pressure ventilation equipment shall be used to filter a minimum of 4 volume changes through the tent after completion of abatement but prior to collapse of the tent/barrier. All required air monitoring must be successfully completed before the tent/barrier is collapsed.

(n) The tent shall be collapsed inward, enclosing the contaminated clothing. This contaminated material shall be disposed of in another plastic bag. The HEPA vacuum shall be decontaminated and sealed.

(o) Glovebag procedures for removal of material within the tent for any sized project shall follow the rules set forth in 15 RCNY § 1-105.

(p) A visual clearance inspection must be conducted by the asbestos handler supervisor and project monitor after the work area dries, to ensure the absence of ACM residue or debris in the work area. The clearance inspection must be documented in the abatement contractor's log and the project air sampling log.

(Amended City Record 12/7/2018, eff. 1/6/2019; amended City Record 4/28/2022, eff. 5/28/2022; amended City Record 1/15/2025, eff. 2/14/2025)

§ 1-107. Foam Procedure for Roof Removal

Open this section

All sections of these rules must be followed in conjunction with this section with the exception of 15 RCNY § 1-81(m), § 1-81(p), § 1-91, § 1-102(b), § 1-112(c), (d), (e), (g) and (h).

(a) These procedures apply only to the removal of asbestos-containing roofing material (ACRM) from exterior roof surfaces. The work area on the roof must be cordoned off with clearly visible barriers such as caution tape, and only persons authorized by the building owner or the building owner's representative may have access.

(1) The contractor must establish and maintain a warning line system on the roof throughout the project.

(2) The contractor must comply with the requirements set forth in OSHA 29 C.F.R. 1926. Subpart M, Fall Protection standard, specifically 29 C.F.R. 1926. 500; 501; and 502.

(3) Only persons authorized by the building owner or the building owner's representative may have access to the roof during abatement activities.

(4) Walking Surfaces. Walking and working surfaces shall be protected from tripping or stepping into or through holes or openings, including skylights, by covers secured to the surface in accordance with OSHA Section 29 C.F.R. 1926.501.

(b) The foam or viscous liquid shall be non-toxic, shall not require special respiratory protection for handling, and shall not affect the handling and disposal of the waste.

(c) The foam or viscous liquid shall coat and maintain a stable blanket (minimum 1" thickness) for the duration of the removal process and shall leave an identifiable colored residue when it dissipates.

(d) The foam or viscous liquid shall wet the ACRM. The ACRM shall be kept wet through the bagging process.

(e) Persons entering the work area must wear personal protective equipment as required by 15 RCNY § 1-51 as well as correctly-fitting, good traction rubber boots.

(f) Abatement shall not be carried out during adverse weather conditions (e.g. precipitation, high winds, ambient temperature below 32 degrees Fahrenheit, etc.).

(g) The worker decontamination unit may be attached to each work area at an entry/exit from each work area in accordance with 15 RCNY § 1-82, or may be remote, in which case the work area shall be equipped with an airlock at the entrance. For removal of less than 1,000 square feet of ACRM, in addition to the shower head(s), the shower room shall be equipped with a flexible hose for waste decontamination. For 1,000 square feet or more of ACRM removal, a separate waste decontamination facility as per 15 RCNY § 1-83 shall be located at an entry/exit from each work area. Remote holding areas for the asbestos containing waste shall comply with Title 16, Chapter 8, Rules of the City of New York (16 RCNY §§ 8.01 et seq.).

(h) Movable objects shall be removed from the work area, or kept in place and wrapped in one sheet of fire retardant 6 mil plastic sheeting.

(i) Provisions must be made to ensure a safe and adequate air supply to any affected building. All vents, skylights, air intakes, windows and doors opening onto the roof, and all other openings must be sealed with 2 layers of fire retardant 6mil plastic or fitted with HEPA filters when appropriate. Vents, air intakes, etc. can be vertically extended temporarily to a height of ten feet instead of sealing them with 2 layers of plastic or HEPA-filters. Drains may be equipped with 5 micron filtering system in lieu of being sealed.

(j) Fixed objects including perimeter walls, bulkheads, cooling towers, ducts and other rooftop accessories must be covered in one sheet of fire retardant 6 mil plastic up to a height of at least six feet.

(k) Prior to actual removal, the built-up roofing shall be blanketed and wetted with a minimum 1" coating of the acceptable foam or viscous liquid which shall be maintained for the duration of the removal until the material is bagged. The foam or viscous liquid shall be confined to the work area.

(l) Power tools used to drill, cut into, or otherwise disturb the ACRM shall be equipped with HEPA-filtered local exhaust ventilation and operated to prevent potential fiber release.

(m) Clean-up procedures shall include the removal and direct bagging of ACRM, so that loose ACRM does not accumulate on the roof. Exterior or interior chutes are prohibited to transport ACRM from the roof to lower floors. Clean-up procedures shall also include the removal of all visible accumulations of asbestos containing waste and the removal of all excess foam or similar viscous liquids. Following the removal of all debris, the work area shall be thoroughly wet cleaned.

(n) The work area shall be allowed to dry completely before the visual inspection is conducted. The project monitor and asbestos handler supervisor shall confirm the absence in the work area of ACM, asbestos-containing waste or debris, and foam or other viscous liquid. This visual inspection must be documented in the abatement contractor's log and project air sampling log.

(o) Upon successful visual inspection, all installed plastic sheeting shall be removed.

(p) Air monitoring shall be conducted in accordance with the relevant provisions of Subchapter D of these rules.

(Amended City Record 12/7/2018, eff. 1/6/2019; amended City Record 4/28/2022, eff. 5/28/2022)

§ 1-108. Foam/Viscous Liquid Use in Flooring Removal

Open this section

All sections of these rules must be followed in conjunction with this section with the exception of 15 RCNY § 1-81(m), § 1-81(p), § 1-91(c), § 1-102(b), § 1-112(d), and § 1-112(g).

(a) These procedures only apply to the removal of surface flooring material including vinyl asbestos floor tiles (VAT), ACM floor coverings (e.g., linoleum) and associated mastics and adhesives, where the only ACM being abated in the work area is flooring material.

(b) The foam or viscous liquid shall be non-toxic, shall not require special respiratory protection for handling, and shall not affect the handling and disposal of the waste.

(c) The foam or viscous liquid shall coat and maintain a stable blanket (minimum 1" thickness) for the duration of the removal process and shall leave an identifiable colored residue when it dissipates. The acceptable foam or viscous liquid shall be maintained for the duration of the removal until the material is bagged.

(d) The foam or viscous liquid shall coat and wet the ACM. The ACM shall be kept wet through the bagging process.

(e) Persons entering the work area must wear personal protective equipment as required by 15 RCNY § 1-51 as well as correctly-fitting, good-traction rubber boots.

(f) Baseboards and wall surfaces up to a minimum height of four feet above the floor must be covered with a layer of fire retardant 6-mil plastic sheeting. If hand power tools are used during the abatement, wall surfaces must be covered with a layer of 6-mil polyethylene sheeting to a minimum height of six feet. Abrasive removal methods, including the use of grinders and beadblasters, are prohibited.

(g) Negative air pressure ventilation shall be provided to allow make-up air into the work area, and the air outlet from the work area shall be at or near the floor level.

(h) Clean-up procedures shall involve removal and bagging of the ACM, of visible accumulations of asbestos containing waste, and of all traces of foam or similar viscous liquid. Following the removal of all debris, the work area shall be thoroughly wet cleaned and HEPA-vacuumed.

(i) The work area shall be allowed to dry completely before the visual inspection is conducted. The project monitor and asbestos handler supervisor shall confirm the absence in the work area of ACM, asbestos-containing waste or debris, and foam or other viscous liquid. This visual inspection must be documented in the abatement contractor's log and project air sampling log.

(j) Upon successful visual inspection, plastic sheeting shall be removed from baseboards and wall surfaces. Isolation barriers shall remain in place.

(k) Air monitoring shall be conducted in accordance with the relevant provisions of Subchapter D of these rules.

(Amended City Record 12/7/2018, eff. 1/6/2019; amended City Record 4/28/2022, eff. 5/28/2022; amended City Record 1/15/2025, eff. 2/14/2025)

§ 1-109. Abatement from Vertical Exterior Surfaces

Open this section

All applicable sections of these rules shall be followed in conjunction with this section except 15 RCNY § 1-81(m), § 1-81(p), § 1-91, and § 1-112(c), (d), (e), (g), and (h).

This section shall apply to projects involving the abatement of asbestos-containing materials from the vertical exterior surfaces (and associated horizontal surfaces, e.g. coping stones on top of a parapet wall) of a building or structure, including but not limited to the following materials:

Caulking or glazing compounds Asphaltic mastic or tar (e.g., flashing on parapet walls) Cement siding or shingles (including Transite) Paints Sealants for coping stone caps or clay roofing tiles

(a) The work area shall be prepared as follows:

(1) The entire surface to be abated and ground-level perimeter shall be considered the work area unless partitions and warning tape are used to define the work area, except that if the horizontal surface below the surface to be abated is not the ground (e.g., surface to be abated is inside parapet wall on roof), the horizontal surface underneath the abatement shall be considered the work area, not the ground.

(2) A restricted area shall be established using warning tape extending at least 25 feet from the affected areas of the building or to the nearest vertical obstruction or the curb.

(3) The restricted area may be entered only by certified workers or authorized visitors.

(4) Before plasticizing, the restricted area shall be inspected for ACM debris and, if necessary, pre-cleaned using HEPA vacuums and wet methods.

(5) All openings to the building or structure's interior which are within 25 feet of the affected ACM shall be closed and made airtight.

(6) Scaffolding erected to access the ACM shall be constructed, maintained, and used in accordance with applicable federal, state, and city laws. The contractor must comply with the requirements set forth in OSHA 29 C.F.R. 1926. Subpart M, Fall Protection and Subpart L (Scaffolds) and the NYC Building Code.

(7) Elevated platforms being used to access the affected ACM shall be plasticized with two layers of fire-retardant 6-mil plastic, which shall extend up from the platform to at least the height of the mid-rail on three sides, and shall be attached directly to the building just below the surfaces under abatement.

(8) The ground-level restricted area shall be cleared of all moveable objects and plasticized with two sheets of fire-retardant 6-mil plastic, which shall be extended one foot up the side of the building. The plasticized area shall be twenty-five feet wide or to the curb. This plastic shall be cleaned, replaced, and disposed of as asbestos waste at the end of each shift.

(9) Sidewalk bridges in the restricted area shall be covered with two layers of fire-retardant 6-mil plastic, placed over and secured to the bridge, spread across the full width of the bridge and up the interior walls of the bridge so the walls are fully plasticized.

(b) A worker/waste decontamination system shall be constructed within the restricted area.

(c) Persons entering the work area must wear personal protective equipment as required by 15 RCNY § 1-51.

(d) Removal Procedure.

(1) Removal of ACM must be by wet methods in accordance with 15 RCNY § 1-102.

(2) ACM removed must be placed in a leak-tight container without dropping the ACM into the container.

(e) Cleanup Procedure.

(1) The stripped substrate must be HEPA vacuumed and wet-wiped.

(2) A visual clearance inspection must be conducted by the asbestos handler supervisor and project monitor after the work area dries, to ensure the absence of ACM residue or debris in the work area.

(3) After the inspection is completed, the warning tapes and barriers may be removed.

(4) The clearance inspection must be documented in the abatement contractor's log and the project air sampling log.

(f) Air monitoring must be conducted in accordance with the relevant provisions of Subchapter D of these rules.

(g) Abatement must not be performed under this section during bad weather (e.g. precipitation, high winds, temperatures in the immediate outdoor surroundings below 32 degrees Fahrenheit, etc.).

(h) Power tools used to drill, cut into, or otherwise disturb ACM must be equipped with HEPA-filtered local exhaust ventilation and operated to prevent potential fiber release.

(Amended City Record 12/7/2018, eff. 1/6/2019; amended City Record 4/28/2022, eff. 5/28/2022)

§ 1-110. Controlled Demolition with Asbestos in Place

Open this section

(a) A building or structure may be demolished with asbestos in place only if the building is in imminent danger of collapse as set forth in § 28-215.1 of Title 28 of the Administrative Code and/or 56 NYCRR 11.5(c).

(b) A condemnation order or declaration issued by the Department of Buildings (DOB) or a signed and sealed condemnation letter from the Owner's registered design professional which has been acknowledged by the Department of Buildings (DOB) must be submitted to the DEP through the ARTS E-File system. A site-specific scope of work identifying the steps to control asbestos emissions during the controlled demolition must be submitted and approved by DEP prior to the commencement of work. The contractor must comply with all procedures set forth in the approved scope of work document. Any variation from the approved scope of work must be approved in advance by DEP.

(c) The demolition shall be performed in accordance with § 28-215.1 of Title 28 of the Administrative Code and/or 56 NYCRR 11.5(c).

(Amended City Record 4/28/2022, eff. 5/28/2022; amended City Record 1/15/2025, eff. 2/14/2025)

§ 1-111. Preliminary Clean-up Procedures

Open this section

The following clean-up requirements shall be followed during the conduct of abatement activities on asbestos projects:

(a) (1) All waste generated shall be bagged, wrapped or containerized immediately upon removal. The personal and waste decontamination enclosure systems and floor and scaffold surfaces shall be HEPA vacuumed and wet cleaned at the end of each work shift at a minimum.

(2) Visible accumulations of asbestos-containing waste material shall be containerized utilizing non-metallic dust pans and non-metallic squeegees or HEPA vacuums.

(3) Metal shovels shall not be used to pick up or move accumulated asbestos-containing waste material or any other debris in the vicinity of isolation or surface barriers.

(b) The waste decontamination enclosure system shall be wet cleaned twice using wet cleaning methods upon completion of waste removal. When the worker decontamination enclosure shower room alternates as a waste container wash room, the shower room shall be washed immediately with cloths or mops saturated with a detergent solution prior to wet cleaning.

(c) The worker decontamination enclosure system shall be wet cleaned / HEPA vacuumed, as appropriate, after each shift change and meal break.

(d) If there is free standing water or if flooding occurs in the work area, work must stop until the water is collected and safely and properly removed.

(Amended City Record 12/7/2018, eff. 1/6/2019)

§ 1-112. Additional Clean-up Procedures (Final)

Open this section

Additional clean-up procedures shall be performed in the order set forth below prior to commencement of clearance air monitoring.

(a) After removal of visible accumulations of asbestos-containing waste material, all surfaces must be HEPA vacuumed. To pick up excess water and saturated debris, a wet-dry shop HEPA vacuum, dedicated to asbestos abatement, may be used.

(b) All surfaces in the work area shall be wet cleaned (first cleaning).

(c) A thin coat of lockdown encapsulant shall be applied to all surfaces in the work area which were not the subject of removal or abatement, including the cleaned layer of the surface barriers and excluding sprinklers, standpipes, and other active elements of the fire suppression system.

(d) After the first cleaning, the work area shall be vacated for 12 hours to allow fibers to settle.

(e) The cleaned and encapsulated layer of the surface barriers shall be removed from the walls and floors.

(f) All objects and surfaces in the work area shall be HEPA vacuumed and wet cleaned a second time.

(g) After the second cleaning, the work area shall be vacated for 4 hours before wet cleaning and/or HEPA vacuuming all surfaces in the work area for a third cleaning.

(h) After the plastic barriers on the walls and floors have been removed, a third cleaning shall be performed of all surfaces in the work area by wet cleaning and/or HEPA vacuuming. A minimum of a one hour waiting period shall be conducted to allow the work area to dry prior to the visual inspection by the air monitor and asbestos supervisor.

(i) Before starting clearance air monitoring, a thorough visual inspection must be conducted to verify the absence of asbestos-containing waste material (e.g. dust). This inspection must be documented in the project air sampling log.

(j) All containerized waste shall be removed from the work area through the decontamination enclosures and the holding area.

(k) All tools and equipment shall be removed from the work area and decontaminated in the waste decontamination enclosure system. Cloths, mops, and other cleaning aids shall be disposed of as asbestos-containing waste material.

(l) After successful clearance air monitoring (see 15 RCNY §§ 1-31 et seq.), the isolation barriers shall be removed and the remaining worker and waste decontamination enclosure(s) must be dismantled and removed from the work site. All plastic sheeting must be cleaned using a HEPA vacuum and disposed of as asbestos contaminated waste.

(m) Within 21 days of the completion of all steps set forth above, including successful clearance air monitoring, a project monitor’s report (Form ACP15) must be submitted to DEP. Failure to submit the ACP15 Form will result in suspension of the air monitor’s account and the contractor’s account in the ARTS E-File System until the form is submitted. This report must be based on an inspection performed after the completion of all steps listed in this section, and may not be based on the visual inspection performed prior to the commencement of clearance air monitoring. This inspection must be documented in the project air sampling log. The project monitor who prepares the report must be independent of the abatement contractor. If a project is being performed on multiple floors of a building, a separate project monitor’s report may be submitted as each floor is completed. Compliance with this subdivision is the responsibility of the building owner.

(Amended City Record 12/7/2018, eff. 1/6/2019 amended City Record 4/28/2022, eff. 5/28/2022; amended City Record 1/15/2025, eff. 2/14/2025)

§ 1-120. Applicability of Regulations to Pre-Demolition Abatement Activities

Open this section

The following regulations shall apply to pre-demolition abatement activities:

15 RCNY §§ 1-01 through 1-61 General Regulations 15 RCNY § 1-81* Work Place Preparation Requirements 15 RCNY § 1-82 Worker Decontamination Enclosure System 15 RCNY § 1-83 Waste Decontamination Enclosure System 15 RCNY § 1-91 through 1-94 Work Place Procedures 15 RCNY § 1-102 ACM Disturbance, Handling and Removal Procedures 15 RCNY § 1-105 Glovebag Procedure 15 RCNY § 1-106 Tent Procedure 15 RCNY § 1-107 Foam Procedure for Roof Removal 15 RCNY § 1-108 Foam/Viscous Liquid Use in Flooring Removal 15 RCNY § 1-109 Abatement from Vertical Exterior Surfaces 15 RCNY § 1-120 through 1-128 Pre-Demolition Abatement Activity Procedures

* Subsections (b), (j), (l), (u), (v) and (z) only.

(Amended City Record 12/7/2018, eff. 1/6/2019)

§ 1-125. Work Area Preparation

Open this section

The following work area preparation shall be followed during the conduct of pre-demolition abatement activities:

(a) Prior to the start of abatement activities on asbestos projects the building owner or designated representative must post a general notification at all main entrances to the structure. Postings of this notification must be in English and Spanish, at eye level in a conspicuous well-lit place that can be viewed by the public without obstruction. Information provided in the notification must include contractor, project location, that the project is regulated by NYC DEP, and the Call Center "311" for government information and services. The notice must have the following heading: NOTICE OF ASBESTOS ABATEMENT, in a minimum of one inch sans serif, gothic or block style lettering, with the balance of the lettering of the notice to be of the same type lettering in a minimum of one quarter inch size. The notification must be posted throughout all abatement activities.

(b) The building shall be vacated prior to the start of abatement activities.

(c) Electric power to all work areas shall be shut down and locked out. Safe temporary power and lighting shall be provided in accordance with all applicable NYC Code(s) and Regulations. Existing light sources (e.g., house lights) shall not be utilized. All power to a work area shall be brought in from outside the area through ground-fault interrupter at the source.

(d) The worker decontamination enclosure system shall be installed or constructed prior to plasticizing the work area and before disturbing ACM. The waste decontamination enclosure system shall be installed or constructed prior to commencement of abatement. The area in which these systems are located shall require HVAC system isolation and plasticizing of electrical outlets and equipment that are within 6 inches of floor level.

(e) Heating, Ventilation and Air Conditioning (HVAC) System shall be shut down and locked out. Isolation barriers shall be installed to prevent interior duct work contamination.

(f) Abatement shall not commence until work place preparation has been completed.

(g) Methods that raise dust, such as sweeping or vacuuming with equipment not equipped with HEPA filters, are prohibited.

(h) Objects which can be removed from the work area prior to abatement without disturbing ACM shall be pre-cleaned using HEPA-filtered vacuum equipment and/or wet cleaning.

(i) The isolation barriers (i.e. sealing off of all openings, including but not limited to windows, corridors, doorways, barriers, skylights, ducts, grills, diffusers, and any other penetrations of the work areas) shall be installed with 2 layers of fire retardant 6-mil plastic sheeting separately sealed with tape. All seams of HVAC or other system components that pass through the work area shall also be sealed. Chimney effects in stacks, columns, flues, shafts, double- walled enclosures, etc., that impact the work area, shall be eliminated by sealing the accesses with solid material covered with a double layer of 6-mil plastic sealed with tape.

(j) Cinderblock and porous construction materials, painted or unpainted, must be covered with one layer of fire retardant 6-mil plastic sheeting, sealed at edges and seams.

(k) Flooring within the work area shall be water-tight.

(l) Suspended ceiling tiles and T-grid components in proximity to ACM shall remain in place until the work area has been fully prepared as outlined in this section and electrical and HVAC systems have been shut down. Contaminated suspended ceiling components shall be removed prior to abatement and treated with a penetrating encapsulant.

(m) Required means of egress, including emergency and fire exits, must be maintained at all times during abatement activities except as otherwise provided, pursuant to the New York City Building and Fire Codes. Exits must be checked daily to ensure that there is no blockage or impediments to exiting.

(n) Entrances to the work area that will be used for worker entry or emergency exits shall be locked against unauthorized entry.

(o) Elevators running through the work area shall conform to the following:

(1) The elevator door in the work area shall be enclosed with conventional 2 x 4 stud framing, covered with 3/8" fire rated plywood sheeting and sealed at all edges and seams. The barrier shall be covered and lapped for 8 inches with two layers of fire retardant 6-mil plastic sheeting adhered individually with edges taped for airtightness.

(2) Elevators not remaining in service shall have the fuses removed and the power switch locked in the open position.

(3) Elevators that remain in service shall conform to the following additional procedures to minimize the piston effect that results:

(i) Elevator control shall be modified to bypass the work area.

(ii) A final larger layer of fire retardant 6-mil plastic sheeting is to be taped airtight but with slack forming a larger perimeter diaphragm. Air leakage across the barrier shall be corrected upon discovery, and the elevator shaft shall be checked for airborne asbestos contamination.

(iii) This system shall be smoke tested daily.

(4) Elevator shafts shall not be used as waste chutes for asbestos-containing waste material.

(p) Adequate toilet facilities shall be provided in the vicinity of the clean room external to the work place. Where such facilities do not exist, portable service shall be provided.

(Amended City Record 12/7/2018, eff. 1/6/2019; amended City Record 8/21/2019, eff. 9/20/2019)

§ 1-126. ACM Procedures: Order of Work

Open this section

No ACM removal shall be performed in a building concurrently with the full demolition of such building or with the removal of one or more stories of such building, except as otherwise provided in these rules pursuant to 15 RCNY §§ 1-03 and 1-26. This subsection shall not apply to emergency work being performed pursuant to Article 215 of Chapter 2 of Title 28 of the Administrative Code.

§ 1-127. Clean-up Procedures During Abatement

Open this section

The following clean-up procedures shall be followed during conduct of pre-demolition abatement:

(a) (1) All waste generated shall be bagged, wrapped, or containerized immediately upon removal. The personal and waste decontamination enclosure systems shall be HEPA vacuumed and wet cleaned at the end of each work shift at a minimum.

(2) Visible accumulations of asbestos-containing waste material may be containerized utilizing rubber dust pans and rubber squeegees or HEPA vacuums. Metal shovels may also be used EXCEPT in the vicinity of plastic sheeting which could be perforated by these tools.

(b) The waste decontamination enclosure system shall be wet cleaned twice using wet cleaning methods upon completion of waste removal. When the worker decontamination enclosure shower room alternates as a waste container wash room, the shower room shall be washed immediately with cloths or mops saturated with a detergent solution prior to wet cleaning.

(c) The worker decontamination enclosure system shall be wet cleaned / HEPA vacuumed, as appropriate, after each shift change and meal break.

(d) If there is free standing water or if flooding occurs in the area, work must stop until the water is collected and safely and properly removed.

(Amended City Record 12/7/2018, eff. 1/6/2019)

§ 1-128. Clean-up Procedures: Preparation for Clearance Air Monitoring

Open this section

The following final clean-up procedures for pre-demolition abatement shall be performed prior to commencement of clearance air monitoring:

(a) All visible accumulations of asbestos-containing waste material shall be removed and containerized. Metal shovels may be used to pick up or move accumulated waste EXCEPT in the vicinity of plastic sheet isolation and surface barriers which could be perforated by these tools. The areas around the plastic sheet isolation barriers shall be cleaned of visible accumulations utilizing rubber dust pans and rubber squeegees. To pick up excess water and gross wet debris, a wet-dry shop HEPA vacuum dedicated to asbestos abatement may be used.

(b) All containerized waste shall be removed from the work area through the decontamination enclosures and the holding area.

(c) All surfaces in the work area shall be wet cleaned using rags or mops. After allowing sufficient time for drying of the work area, HEPA vacuums shall be used to thoroughly clean all surfaces after gross clean-up.

(d) The plastic sheeting installed, pursuant to 15 RCNY § 1-125(j), must be cleaned as in subdivision (c) above, then sprayed with a lockdown encapsulant and removed when dry.

(e) All surfaces in the work area which were not the subject of removal or abatement shall be sprayed with a lockdown encapsulant, which upon drying will not dissolve upon rewetting. Sufficient time for drying shall be allowed.

(f) All tools and equipment shall be removed from the work area and decontaminated in the equipment decontamination enclosure system.

(g) After successful clearance air monitoring (see 15 RCNY §§ 1-31 et seq.), a HEPA vacuum must be used to clean up any dust or debris when removing the isolation barriers.

(h) Within 21 days of the completion of all steps set forth above, including successful clearance air monitoring, a project monitor’s report (Form ACP15) must be submitted to DEP. Failure to submit the ACP15 Form will result in suspension of the air monitor’s account and the contractor’s account in the ARTS E-File System until the form is submitted. This report must be based on an inspection performed after the completion of all steps listed in this section and may not be based on the visual inspection performed prior to the commencement of clearance air monitoring. This inspection must be documented in the project air sampling log. The project monitor who prepares the report must be independent of the abatement contractor. If a project is being performed on multiple floors of a building, a separate project monitor’s report may be submitted as each floor is completed. Compliance with this subdivision is the responsibility of the building owner.

(Amended City Record 12/7/2018, eff. 1/6/2019; amended City Record 1/15/2025, eff. 2/14/2025)