§ 18-11. Preface

Open this section

(a) The health, welfare and economic well-being of nearly nine million residents in the five counties of New York City ("the City"), and of an increasing number of upstate New York communities is inextricably tied to the quality of the source waters in the watersheds of the New York City Water Supply located in Westchester, Putnam, Dutchess, Delaware, Ulster, Greene, Sullivan and Schoharie Counties, and Fairfield County in Connecticut. The high quality of these waters faces a continuing threat from the cumulative and episodic impacts of pollution sources generated by certain land uses and activities in the watersheds. It is the duty of the Commissioner of the New York City Department of Environmental Protection (the "Department") to protect the high quality of waters from which the City's water supply is drawn and preserve it from degradation for the purpose of protecting the health and general welfare of its consumers.

(b) These rules and regulations repeal in their entirety and supersede the Rules and Regulations for the Department of Water Supply, Gas and Electricity of the City of New York enacted the 11th day of June, 1953.

(c) These rules and regulations are hereby enacted pursuant to the authority vested in the Commissioner of the Department of Environmental Protection, as set forth in 15 RCNY § 18-13.

§ 18-12. Purpose and Findings

Open this section

(a) The quality of the drinking water supplied to the City and upstate communities which draw from the New York City water supply depends primarily on the quality of the source waters which feed the reservoirs. The source waters and reservoirs are vulnerable to degradation and contamination from various sources and activities, including, but not limited to:

(1) Wastewater discharges to surface water and groundwater;

(2) Urban, suburban, rural, mining, silvicultural and agricultural land use practices that result in nonpoint source runoff of pollution and/or in adverse changes in the natural rate at which water flows into and through a delineated drainage basin; and

(3) Improper use, handling, storage, transport and/or disposal of substances, including but not limited to, hazardous substances, radioactive materials, pesticides, fertilizers, winter highway maintenance materials, solid wastes, and animal wastes.

(b) The Department finds that such sources and activities, either alone or in conjunction with any other related activities, may constitute a source of contamination to or degradation of the water supply, may cause a contravention of the State water quality standards set forth in 6 NYCRR Parts 701-705, and Subchapter D of these rules and regulations, and may result in the impairment of the use of the water supply for drinking, culinary or food processing purposes.

(c) In response to the Safe Drinking Water Act Amendments of 1986, the United States Environmental Protection Agency has begun implementing a significant expansion of regulatory requirements for public water systems. In order to protect the public health, and to satisfy the legislative mandates of the Safe Drinking Water Act Amendments and the rules and regulations in 40 C.F.R. Parts 141 and 142, the New York State Department of Health has amended the State Sanitary Code, 10 NYCRR Part 5, Subpart 5-1, Public Water Systems, which contains New York State's Surface Water Treatment Rule. Although both Federal and State law propose filtration as a method for water quality treatment for pathogen control, the effectiveness of the filtration process and complexity of plant operation is dependent upon the quality of the water entering the filtration plant. In addition, many contaminants are not removed by conventional filtration. Therefore, it is clear that enhancement of the City's existing watershed rules and regulations would be necessary even if the City were to build filtration plants to filter its entire water supply.

(d) It is the goal and intent of these rules and regulations to protect the public health by averting future contamination to and degradation of the water supply and by remediating existing sources of pollution or degradation of the New York City water supply. These rules and regulations implement the Department's intention to minimize the discharge of pollutants into the source waters from both point and nonpoint sources, minimize the adverse impacts of erosion, limit the discharge of phosphorus to source waters which may accelerate the eutrophication process, and provide notification to the City of ongoing or proposed activities, which either alone or in conjunction with other existing and proposed regulated activities, may cause contamination to or degradation of the water supply.

(e) It is the purpose of these rules and regulations to insure compliance with the Federal and State standards by providing a comprehensive watershed protection program. Furthermore, these rules and regulations articulate an antidegradation policy for the New York City water supply system. These rules and regulations are promulgated to govern those activities in the watershed that threaten the quality of the water supply of the numerous upstate communities and the City of New York. While bound by its responsibility to protect the public health, the City has also taken the needs of the communities and businesses in the New York City watershed into consideration in drafting and promulgating these rules and regulations.

(f) The City reserves the right to re-examine these rules and regulations periodically to insure that they continue to further the goal and intent referred to in paragraph (d) of this subdivision and the purposes referred to in paragraph (e) of this subdivision.

(Amended City Record 10/30/2019, eff. 11/29/2019)

§ 18-13. Authority

Open this section

These rules and regulations are promulgated pursuant to Article 11 of the New York State Public Health Law and § 24-302 of the New York City Administrative Code, and have been duly promulgated by the Commissioner of the Department of Environmental Protection of the City of New York and approved by the Commissioner of the New York State Department of Health. These rules and regulations shall become effective upon completion of any conditions set forth in the approval issued by the New York State Department of Health pursuant to § 1100(1) of the Public Health Law; publication of these rules and regulations pursuant to § 1100(2) of the Public Health Law; and upon completion of the requirements of the New York City Administrative Procedure Act.

§ 18-14. Applicability

Open this section

(a) These rules and regulations apply to all persons undertaking, or proposing to undertake, the activities in the categories listed below, where such activities are specifically regulated in these rules and regulations and occur in the New York City watershed:

(1) Discharge or storage of pathogenic materials.

(2) Discharge or storage of hazardous substances and hazardous wastes.

(3) Discharge or storage of radioactive materials.

(4) Discharge or storage of petroleum products.

(5) Discharge or transport of human excreta and use of holding tanks.

(6) Design, construction and operation of wastewater treatment plants.

(7) Design, construction and operation of sewer systems and service connections.

(8) Design, construction and operation of intermediate sized and individual sewage treatment systems.

(9) Discharge of stormwater and sediment, and preparation and implementation of stormwater pollution prevention plans.

(10) Construction of impervious surfaces.

(11) Discharge from miscellaneous point sources.

(12) Discharge of solid waste, including the siting of junkyards and solid waste management facilities.

(13) Discharge from agricultural activities.

(14) Discharge or storage of pesticides.

(15) Application and storage of fertilizers.

(16) Snow disposal and application and storage of winter highway maintenance materials.

(b) These rules and regulations apply to substantial alterations or modifications of the activities described in subdivision (a) of this section.

(c) These rules and regulations apply to a substantial alteration or modification of any noncomplying regulated activity, as set forth in these rules and regulations.

(d) These rules and regulations apply to noncomplying regulated activities that are required to come into compliance with these rules and regulations as set forth in these rules and regulations.

(e) The boundaries of the New York City watershed have been delineated on United States Geological Survey maps, which are available for inspection at the offices of the local representatives of the Department listed in 15 RCNY § 18-15. A map of the watershed is provided in Appendix 18-A of this Part for reference purposes only.

§ 18-15. Local Representatives

Open this section

(a) Information about these rules and regulations and application and other forms required by these rules and regulations may be obtained from the following offices of the Department or on the Department's website at www.nyc.gov/dep. Applications for Department approval of a regulatory activity must be submitted to one of these offices or online in accordance with instructions that may be provided on the Department's website. Petitions appealing from a determination issued by the Department or requesting a hearing on a cease and desist order issued by the Department must be submitted to the offices listed in subdivision (b) or online in accordance with instructions that may be provided on the Department's website.

(1) New York City Department of Environmental Protection Regulatory and Engineering Programs 465 Columbus Avenue Valhalla, New York 10595 Telephone: (914) 742-2028

(2) New York City Department of Environmental Protection Regulatory and Engineering Programs 71 Smith Avenue Kingston, New York 12401 Telephone: (845) 340-7215

(b) Petitions for a hearing on a determination by the Department to revoke, suspend, or modify a determination or variance in accordance with 15 RCNY § 18-26, petitions for appeal of a determination issued by the Department in accordance with 15 RCNY § 18-28, and petitions for a hearing on a cease and desist order issued by the Department in accordance with 15 RCNY § 18-29 must be submitted to the address listed in paragraph (1), with a copy to the address listed in paragraph (2).

(1) New York City Office of Administrative Trials and Hearings 100 Church Street, 12th floor New York, New York 10007 Telephone: (844) 628-4692

(2) New York City Department of Environmental Protection General Counsel 59-17 Junction Boulevard 19th Floor Flushing, New York 11373-5107 Telephone: (718) 595-6555

(c) For communications with the Department regarding any known or suspected violations of these rules and regulations or notification of potential contamination of the water supply occurring anywhere in the watershed:

(1) New York City Water Supply Watershed Police Telephone: 1-888-H20-SHED (1-888-426-7433)

(d) Addresses and phone numbers contained in this section are informational and persons subject to these rules and regulations must utilize addresses and phone numbers specified herein, or successor addresses and phone numbers where appropriate.

(Amended City Record 10/30/2019, eff. 11/29/2019)

§ 18-16. Definitions

Open this section

(a) The following terms shall have the stated meanings when used in this Chapter, except where otherwise specifically provided:

(1) Absorption area means the area to which wastewater is distributed for infiltration to the soil.

(2) Absorption field means the area to which sewage is distributed for infiltration to the soil by means of a network of pipes. A gravelless absorption system is a type of absorption field.

(3) Access road means an impervious private or public road, other than a driveway, which connects a parcel to an existing public or private road and which is necessary in order to enable the parcel to be developed.

(4) Affiliate means any agency or person controlled by, controlling, or under common control with an applicant.

(5) Agency means any local, state or federal department, agency, board, public benefit corporation, public authority, commission, district, or governing body, including any city, county, and other political entity of the State.

(6) Agricultural activity means (i) an activity that occurs on "land used in agricultural production" as that term is defined in § 301(4) of the Agriculture and Markets Law, or (ii) an activity which is covered by a whole farm plan approved by the Watershed Agricultural Council, or by a New York State Agricultural Environmental Management Plan, or by another federal, state, or other conservation plan determined by the Department to provide water quality protection equivalent to whole farm plans approved by the Watershed Agricultural Council.

(7) Alteration or modification means any change in physical configuration, intensity of use, location, plans, design, site, capacity, treatment standard or method, or other change in a regulated activity or in a noncomplying regulated activity. This term shall not include remediation, routine repairs or maintenance of structures and equipment.

(8) Approval means any final decision by an agency to issue a permit, certificate, license, lease, renewal or other entitlement or to otherwise authorize a proposed project or activity.

(9) Area zoned for commercial or industrial uses means a commercial or industrial zoning district, hamlet zoning district, or highway business zoning district. Areas zoned for commercial or industrial uses shall not include agricultural zoning districts.

(10) Base flow means visible sustained or fair weather runoff of water, including groundwater.

(11) Best management practices (BMPs) means methods, measures or practices determined to be the most practical and effective in preventing or reducing the contamination to or degradation of the water supply. Best management practices include, but are not limited to, structural and nonstructural controls and operations and maintenance procedures, that can be applied before, during or after regulated activities to achieve the purposes stated herein.

(12) Best treatment technology (BTT) means methods, measures or practices determined to be the most practical and effective in reducing amounts of phosphorus in both surface and subsurface point source discharges which occur within the New York City watershed. BTT will vary with the size of the wastewater treatment plant, but is generally understood to consist of secondary treatment and chemical removal (usually accomplished by the addition of aluminum salts, iron salts, polymers, or pH adjustments with lime), with media filtration as a final step if necessary to achieve higher removal rates.

(13) C.F.R. means the Code of Federal Regulations.

(14) City means the City of New York.

(15) Clear cutting means cutting all of the trees, not just selected trees, within a specified boundary designated by the owner of the property.

(16) Coliform restricted basin means the drainage basin of a reservoir or controlled lake in which the coliform standards as set forth in 15 RCNY § 18-48(c) or (d) are exceeded as determined by the Department pursuant to its annual review conducted under 15 RCNY § 18-48(e).

(17) Combined sewer system means a structure used for conveying both sewage and stormwater.

(18) Commissioner means the Commissioner of the New York City Department of Environmental Protection or its successors or a deputy commissioner authorized to act for such Department pursuant to law.

(19) Construction or construction activity means any building, demolition, renovation, replacement, restoration, rehabilitation or alteration of any structure or road, or land clearing, land grading, excavation, filling or stockpiling activities that result in soil disturbance.

(20) Construction and demolition debris means uncontaminated solid waste resulting from the construction, remodeling, repair and demolition of structures and roads; and uncontaminated solid waste consisting of vegetation resulting from land clearing and grubbing, utility line maintenance and seasonal and storm related cleanup.

(21) Contamination means the introduction of any pollutant to the water supply.

(22) Controlled lake means a lake from which the City may withdraw water pursuant to rights acquired by the City or as a right of ownership. The controlled lakes are: Kirk Lake, Lake Gleneida and Lake Gilead.

(23) Croton System means Middle Branch, Bog Brook, East Branch, Croton Falls, Diverting, Titicus, Amawalk, Muscoot, New Croton, and Cross River Reservoirs, Kirk Lake, Lake Gleneida and Lake Gilead, and their respective drainage basins.

(24) Degradation means a process of reduction or deterioration of the water quality of the water supply, including the process of eutrophication.

(25) Department means the New York City Department of Environmental Protection or its successors.

(26) Design capacity means the approved flow limit of the physical apparatus of a wastewater treatment plant as specified in its SPDES permit.

(27) Design point means a point where stormwater runoff enters a watercourse or wetland or leaves the site of an activity for which a stormwater pollution prevention plan must be prepared pursuant to this Chapter.

(28) Design professional means a professional engineer or a registered architect who is licensed to practice in the State of New York, or a land surveyor with an exemption under § 7208(n) of the Education Law.

(29) Designated Main Street Area means a defined area of limited size located within the East of Hudson Watershed which is an existing center of commercial, industrial, residential, or mixed use. Designated Main Street Areas were proposed by local governments in the East of Hudson Watershed in 1997 and approved by the Department pursuant to these rules and regulations.

(30) Designated Village Center means an area in the Croton System described by the metes and bounds of a village center, whether or not located in an incorporated village, designated by a local government(s) in a Comprehensive Croton Water Quality Protection Plan prepared and agreed to in accordance with 15 RCNY § 18-82 by submitting to the Department a description of the metes and bounds of such proposed Designated Village Center, a map of the described area, and a statement of the features which qualify the area as a Designated Village Center. A Designated Village Center must be an existing center of commercial, residential or mixed uses.

(31) Discharge means the intentional or unintentional disposal, deposit, injection, emission, application, dumping, spilling, leaking, washing off, release, running off, draining or placing of any solid, semi-solid, liquid, or any other non-gaseous waste or other substance into or onto any land or water or into any sewer system so that such waste or other substance may directly or indirectly enter into any watercourse, wetland, reservoir, reservoir stem, controlled lake or groundwater.

(32) Discontinuation means an interruption in the use of a regulated activity including a noncomplying regulated activity. The period of discontinuation shall commence on the date when regular or seasonal use ceases. Incidental or illegal use of an unoccupied structure shall not be sufficient to interrupt a period of discontinuation.

(33) Disturbed area means the portion of a site for which the imperviousness of the ground has changed from pre-construction conditions as a result of any land clearing, land grading or construction activity. Disturbed areas may include lawns and landscaped areas.

(34) Drainage Area means all land and water area from which runoff may run to a common design point.

(35) Drainage basin means the land area which contributes surface water to a reservoir or controlled lake.

(36) Driveway means a route accessible by a motor vehicle between an individual residence and a public or private road to provide ingress and egress from the individual residence.

(37) East of Hudson Watershed means West Branch, Boyd's Corner, Bog Brook, East Branch, Croton Falls, Diverting, Titicus, Amawalk, Muscoot, New Croton, Cross River, Middle Branch and Kensico Reservoirs, Kirk Lake, Lake Gleneida and Lake Gilead, and their respective drainage basins.

(38) Effective Date means May 1, 1997.

(39) Effluent means water or wastewater that flows out from a wastewater treatment plant or other treatment process.

(40) Enhanced subsurface sewage treatment system means a subsurface sewage treatment system that provides enhanced treatment of wastewater to reduce the amount of biochemical oxygen demand (BOD) and total suspended solids (TSS) of wastewater effluent prior to distribution to an absorption field. Enhanced subsurface sewage treatment systems include, but are not limited to, aerobic treatment units, peat filters, and textile filters.

(41) Epilimnion means the uppermost, warmest, well-mixed layer of a lake during thermal stratification.

(42) Erosion means the wearing away or the movement of soil by such physical agents as wind or water, that is exacerbated by such practices as the disturbance of ground cover by stripping or removing vegetation, construction activity, or tilling.

(43) Exfiltration means wastewater that leaks out of a sewer system into the surrounding environment, through faulty joints, defective pipes, cracks in pipes, connections, or at manholes.

(44) Existing, where used to describe storage of hazardous substances, storage of petroleum products, or the siting of junkyards and solid waste management facilities, means physically constructed, functioning and operational prior to May 1, 1997.

(45) Expansion means an increase in the permitted flow limit for a wastewater treatment plant as specified in the SPDES permit and/or an increase in the design capacity of a wastewater treatment plant.

(46) Facility means a structure, room or other physical feature designed to perform a particular function and that makes possible some activity.

(47) Fertilizer means any commercially produced mixture, generally containing phosphorus, nitrogen and/or potassium, except compost, that is applied to the ground to increase the supply of nutrients to plants.

(48) Galley System means any subsurface system for treating sewage that employs structural chambers in a horizontal or vertical arrangement for the storage of effluent until it can be absorbed into the soil, that is utilized following a septic tank as an alternative to a standard absorption field, and that did not have all discretionary approvals necessary for construction and operation before June 30, 2002.

(49) Gasoline station means an establishment at which gasoline is sold or offered for sale to the public for use in motor vehicles.

(50) Gravelless absorption system means an absorption field using a wastewater distribution system designed to be installed without gravel or stone aggregate. Gravelless absorption systems may involve the use of geotextile, sand, or other media.

(51) Groundwater means any water beneath the land surface in the zone of saturation. The zone of saturation is where water fills all available pore spaces.

(52) Hamlet means a population center designated as a hamlet by a Town Board in the West of Hudson watershed and described as a hamlet in a Water Supply Permit duly issued by the New York State Department of Environmental Conservation or in any written agreement among the affected parties to the 1997 New York City Watershed Memorandum of Agreement, including the New York State Department of Environmental Conservation.

(53) Hazardous substance means any substance defined or listed in 6 NYCRR Part 597 except that hazardous substance does not mean any petroleum product, including those listed in 6 NYCRR § 597.2, Table 1, and also does not mean any hazardous waste.

(54) Hazardous waste means any solid waste, defined or listed as a hazardous waste in 6 NYCRR Part 371.

(55) Holding tank means a tank or vault, with no outlet, used for holding sewage before it is pumped out and transported elsewhere for treatment or disposal.

(56) Hot spot runoff means runoff from an area where land use or activities generate highly contaminated runoff, with concentrations of pollutants in excess of those typically found in stormwater, such as vehicle service and maintenance facilities, fleet storage areas, industrial sites, marinas, and facilities that generate or store hazardous materials. Runoff from residential, institutional, and office development, non-industrial rooftops, roads, and pervious surfaces is not generally hot spot runoff.

(57) Hydrologic soil group means the designation of soils based on the National Engineering Handbook, Part 630, Chapter 7, Hydrologic Soil Groups, U.S. Department of Agriculture, National Resources Conservation Service, 2009 in which soils are categorized into four runoff potential groups, ranging from A soils, with high permeability and little runoff production, to D soils, which have low permeability rates and produce much more runoff.

(58) Hypolimnion means the lower, cooler layer of a lake during thermal stratification.

(59) Impervious surface means an area which is either impervious to water or which substantially prevents the infiltration of water into the soil at that location. Impervious surfaces include, but are not limited to, paving, concrete, asphalt, rooftops, and other hard surfacing materials, and do not include dirt, crushed stone, gravel surfaces, or other surfacing materials determined by the Department to be pervious for their intended purpose.

(60) Individual residence means a building consisting of one or two residential units.

(61) Individual sewage treatment system means an on-site subsurface sewage treatment system serving one or two family residential properties and receiving sewage without the admixture of industrial wastes or other wastes, as defined in the Environmental Conservation Law § 17-0701.

(62) Industrial waste means any liquid, gaseous, solid or waste substance or a combination thereof resulting from any process of industry, manufacturing, trade or business, or from the development or recovery of any natural resources, which may cause or might reasonably be expected to cause contamination to or degradation of the water supply.

(63) Infiltration means water, other than wastewater, that enters a sewer system, including sewer service connections, from the ground through such means as defective pipes, pipe joints, connections, or manholes. Infiltration does not include, and is distinguished from, inflow and from treatment of runoff by stormwater infiltration practices.

(64) Inflow means water other than wastewater that enters a sewer system, including sewer service connections, from sources such as, but not limited to, roof leaders, cellar drains, yard drains, area drains, foundation drains, drains from springs and swampy areas, manhole covers, cross connections between storm sewers and sanitary sewers, catch basins, cooling towers, storm waters, surface runoff, street wash waters, or drainage. Inflow does not include, and is distinguished from, infiltration.

(65) In situ soil means naturally occurring glacial soil; it does not include fill or stabilized fill.

(66) Intake means the points in the New York City water supply located prior to the point of disinfection where the water is no longer subject to surface runoff.

(67) Intermediate sized sewage treatment system means an on-site subsurface sewage treatment system serving an industrial, institutional, municipal, commercial, or multi-family residential facility, and receiving sewage without the admixture of industrial wastes or other wastes, as defined in the Environmental Conservation Law § 17-0701.

(68) Intermittent stream means a watercourse that during certain times of the year goes dry or whose lowest annual mean discharge during seven consecutive days with a recurrence interval of ten years (MA7CD/10) is less than 0.1 cubic foot per second and which periodically receives groundwater inflow. A drainage ditch, swale or surface feature that contains water only during and immediately after a rainstorm or a snow melt shall not be considered to be an intermittent stream.

(69) Junkyard means any place of storage or deposit, whether in connection with another business or not, where four or more unregistered, old, or second hand motor vehicles, no longer intended or in condition for legal use on the public highways, are held, whether for the purpose of resale of used parts, for the purpose of reclaiming for use some or all of the materials such as metal, glass, or fabric for the purpose of disposing of the same, or for any other purpose.

(70) Land clearing means the exposure of soil by devegetation or the exposure of soil to the forces of erosion.

(71) Land grading means the removal, addition or alteration of surface or subsurface conditions of land by excavation or filling.

(72) Limiting distance means the shortest horizontal distance from the nearest point of a structure or object to the edge, margin or steep bank forming the ordinary high water mark of a watercourse, wetland, reservoir, reservoir stem or controlled lake or to the contour line coinciding with the reservoir spillway elevation.

(73) Mapped stream means a protected stream as defined in 6 NYCRR § 608.1.

(74) Metalimnion means an intermediate zone between the epilimnion and hypolimnion where the water temperature drops rapidly with increasing depth.

(75) Microfiltration means a process in which treated effluent passes through a membrane filter having a nominal pore diameter of 0.2 microns or less.

(76) Multi-family residence means a building containing three (3) or more residential units.

(77) Municipal solid waste landfill means a landfill, as defined in 6 NYCRR § 360.2, which is owned or operated by a municipality.

(78) New, where used to describe storage of hazardous substances, storage of petroleum products, and the siting of junkyards and solid waste management facilities, means undertaken, constructed, installed, or implemented after May 1, 1997.

(79) Noncomplying regulated activity means any regulated activity or existing activity which does not conform to the standards set forth in these rules and regulations, but has obtained all discretionary approvals necessary for construction and operation, prior to the effective date of these rules and regulations and/or prior to the effective date of an amendment to these rules and regulations that made the activity noncomplying.

(80) Nonpoint source pollution means pollution sources which are diffuse and do not have a single point of origin or are not introduced into a receiving stream from a point source.

(81) NYCRR means the Official Compilation of Codes, Rules and Regulations of the State of New York.

(82) Offset means a reduction in the discharge of phosphorus into a drainage basin which is surplus, quantifiable, permanent, and enforceable, as defined herein:

(i) Surplus means that the reduction in phosphorus is not otherwise required by federal, state or local law, including these rules and regulations, or pursuant to the terms of any judgment, decree or order of any court, administrative tribunal or governmental agency, or pursuant to any watershed protection program funded by the Department, except as provided in 15 RCNY §§ 18-83(a)(3) and 18-84(a)(3).

(ii) Quantifiable means that a reasonable basis exists for calculating and verifying the amount of the reduction in phosphorus.

(iii) Permanent means that the reduction in phosphorus is ongoing and of unlimited duration, as opposed to a temporary reduction.

(iv) Enforceable means that the actions and performance standards proposed by the applicant leading to the reduction in phosphorus are incorporated into a legally valid and binding agreement which may be enforced by the City in a court of competent jurisdiction.

(83) One hundred-year, twenty-four hour storm means the storm, with a twenty-four hour duration, that statistically has a one percent chance of occurring in any given year, as set forth in the "New York State Stormwater Design Manual," New York State Department of Environmental Conservation (2015).

(84) One-year, twenty-four hour storm means the storm, with a twenty-four hour duration, that statistically has a 100 percent chance of occurring in any given year, as set forth in the "New York State Stormwater Design Manual," New York State Department of Environmental Conservation (2015).

(85) Operator means any person who leases, operates, controls or supervises a facility.

(86) Owner means any person who has legal or equitable title to a facility.

(87) Pathogenic means capable of causing disease from organisms, including but not limited to: bacteria, fungi, viruses, and protozoa (such as Giardia and Cryptosporidium).

(88) Person means any individual, public or private corporation, political entity, agency, municipality, industry, co-partnership, association, firm, trust, estate or any other legal entity whatsoever, except that person shall not mean the State of New York or any State department, agency, board, public benefit corporation, public authority or commission.

(89) Perennial stream means a watercourse that flows throughout the year from source to mouth.

(90) Pesticide means (i) any substance or mixture of substances intended for preventing, destroying, repelling, or mitigating any insects, rodents, fungi, weeds, or other forms of plant or animal life or viruses, except viruses on or in living humans, or other animals, which the Commissioner of the New York State Department of Environmental Conservation shall declare to be a pest or (ii) any substance or mixture of substances intended as a plant regulator, defoliant or desiccant.

(91) Petroleum product means oil or petroleum of any kind and in any form including, but not limited to, oil, petroleum, fuel oil, oil sludge, oil refuse, oil mixed with other wastes and crude oils, gasoline and kerosene.

(92) Phosphorus restricted basin means (i) the drainage basin of a source water reservoir in which the phosphorus load to the reservoir results in the phosphorus concentration in the reservoir exceeding 15 micrograms per liter, or (ii) the drainage basin of a reservoir other than a source water reservoir or of a controlled lake in which the phosphorus load to the reservoir or controlled lake results in the phosphorus concentration in the reservoir or controlled lake exceeding 20 micrograms per liter in both instances as determined by the Department pursuant to its annual review conducted under 15 RCNY § 18-48(e).

(93) Photic zone means the region of a lake that receives light, where photosynthesis takes place. The photic zone extends down to a depth where photosynthetic activity and respiration are balanced due to the available light, or to one percent surface illumination.

(94) Point source means any discernible, confined and discrete conveyance, including but not limited to any pipe, ditch, channel, tunnel, conduit, well, discrete fissure, container, rolling stock, or vessel or other floating craft, or landfill leachate collection system, from which pollutants are or may be discharged.

(95) Pollutant means unpermitted dredged spoil, solid waste, incinerator residue, sewage, effluent, garbage, sewage sludge, munitions, chemical waste, biological material, radioactive material, heat, wrecked or discarded equipment, rock, sand, and industrial and municipal waste discharged into water.

(96) Portable toilet means a non-waterborne sewage system with offsite residual disposal, as identified in 10 NYCRR Appendix 75-A.

(97) Principal means an agency or person that owns 10 percent or more of the voting stock or has the ability to control a corporation, partnership or other entity.

(98) Qualifying municipal sewer use law means a local law or ordinance that includes provisions substantially similar to Articles 1 - 3, 5 - 7, 11 - 14 and the Appendix of the New York State Department of Environmental Conservation Model Sewer Use Law, dated 1994, or which the New York State Department of Environmental Conservation has otherwise accepted pursuant to the SPDES permit for the wastewater treatment plant served by a municipal sewer system.

(99) Radioactive material means any material in any form that emits radiation spontaneously.

(100) Redevelopment means the reconstruction or modification of any previously developed land such as residential, commercial, industrial, or road/highway, which involves soil disturbance. Redevelopment is distinguished from new development in that new development refers to soil disturbance on land which has not been developed. The term "redevelopment" specifically applies to areas previously developed with impervious surfaces.

(101) Regulated activity means any activity to which these rules and regulations apply, as described in subdivisions (a) - (d) of 15 RCNY § 18-14.

(102) Remediation means the repair or replacement, other than routine repair or maintenance as described in 15 RCNY § 18-38(b)(5)(iii) of Subchapter C, of a subsurface sewage treatment system. Remediation does not include alteration or modification as defined in these rules and regulations.

(103) Reserve absorption field means an area identified in the design for a subsurface sewage treatment system as suitable for infiltration of sewage to the soil by means of a network of pipes.

(104) Reservoir means any natural or artificial impoundment of water owned or controlled by the City which is tributary to the City Water supply system.

(105) Reservoir stem means any watercourse segment which is tributary to a reservoir and lies within 500 feet or less of the reservoir.

(106) Residential lot(s) means any parcel of land of five acres or less, any point on the boundary line of which is less than one-half mile from any point on the boundary line of another such lot in the same tract, unless any such lot may not legally be used for residential purposes. Without limiting the generality of the foregoing, the term "residential" shall include temporary, seasonal and permanent residential use.

(107) Sediment means organic or mineral solids or colloids that are transported by the process of hydrologic, hydraulic, or atmospheric transport, including but not limited to erosion.

(108) Sewage means the water-carried human or animal wastes from residences, buildings, industrial establishments or other places, together with such groundwater infiltration and surface water as may be present. The admixture of sewage with industrial waste or any other waste as herein defined, shall also be considered "sewage" within the meaning of these rules and regulations.

(109) Sewer connection means the connection between a building, residence, or other structure and a sewer system except that any connection designed and intended to convey 2,500 gallons per day or more of sewage, industrial waste or other wastes shall be considered a sewer extension. Sewer connections designed to facilitate additional sewer connections, which are proposed on or after November 29, 2019, shall be considered sewer extensions.

(110) Sewer extension means newly constructed sewer pipe lines or conduits, and pumping stations and other constructions appurtenant thereto, designed to serve one or more sewer connections and to convey sewage, industrial waste or other wastes to a sewer system.

(111) Sewer system means pipe lines or conduits, pumping stations, and force mains, and all other constructions, devices, and appliances appurtenant thereto, including sewer extensions, used for conducting sewage, industrial waste or other wastes to a treatment facility.

(112) Silvicultural activity means the removal of selected trees within a specified boundary designated by the owner of the property so that adequate numbers of trees are left to provide seed and partial shade for the development of new tree seedlings, and when such activity is in accordance with Federal, State and local laws.

(113) Small quantity generator has the meaning set forth in 6 NYCRR § 370.2(b)(154).

(114) Solid waste means all putrescible and non-putrescible materials or substances that are discarded, abandoned, or rejected as being spent, useless, worthless or in excess to the owners at the time of such discard or rejection, including but not limited to garbage, refuse, industrial and commercial waste, sludges from air or water treatment facilities, rubbish, tires, ashes, contained gaseous material, incinerator residue, construction and demolition debris, discarded automobiles and offal, except where exempt from compliance with 6 NYCRR Part 360 as described in 6 NYCRR § 360.2(a)(3).

(115) Solid waste management facility means any facility employed beyond the initial solid waste collection process and managing solid waste, as defined in 6 NYCRR § 360.2.

(116) Source water reservoir means Ashokan, Cross River, Croton Falls, Kensico, New Croton, Rondout, and West Branch Reservoirs.

(117) SPDES flow parameter violation means two or more violations of a permitted State Pollutant Discharge Elimination System (SPDES) flow parameter limit during a consecutive six month period. A facility that operates less than 6 months per year will be deemed to have a SPDES flow parameter violation if the permitted SPDES flow parameter limit is violated one or more times during any consecutive four month period.

(118) State Pollutant Discharge Elimination System (SPDES) permit means a permit issued pursuant to Titles 7 and 8 of Article 17 of the Environmental Conservation Law.

(119) Stormwater means that portion of precipitation that is in excess of the evaporative or infiltrative capacity of soils, or the retentive capacity of surface features, that flows off the land by surface runoff or by subsurface interflow to watercourses, wetlands, reservoirs, reservoir stems and controlled lakes, i.e., that portion of the water supplied to surface drainage that is not groundwater or base flow.

(120) Stormwater bioretention practice means a stormwater management practice that uses landscaping and soils to treat stormwater runoff by collecting it in shallow depressions, before filtering through a fabricated planting soil media.

(121) Stormwater conveyance measure means a swale, drainage ditch, pipe, spillway, or other structure located outside a stormwater management practice that is used solely to transport water between stormwater management practices or to a watercourse or wetland. A stormwater conveyance measure constructed to convey stormwater, on a temporary basis, during active construction, which will not be used as a stormwater conveyance measure after construction is complete, is not considered a watercourse under this Chapter. A stormwater conveyance measure that contains water only during and immediately after a rainstorm or a snowmelt is not considered a watercourse.

(122) Stormwater infiltration practice means a stormwater management practice designed to collect and temporarily store runoff and to distribute that runoff to the underlying soil for treatment.

(123) Stormwater management practice means a stormwater pond, stormwater wetland (also known as a constructed wetland), infiltration system, filter practice, or open channel used primarily for managing and/or treating stormwater, including a Department approved alternative stormwater management practice.

(124) Stormwater Project Review Committee ("Committee") means a Committee formed in each Town or Village in the watershed to assist the Department in implementing 15 RCNY § 18-39(b) and (c), and consisting of the following four Committee members: a representative of the Department, who shall act as chairperson; a representative of the New York State Department of Environmental Conservation from the region in which the activity requiring a stormwater pollution prevention plan is proposed to be located; a representative of the Town or Village in which the activity requiring a stormwater pollution prevention plan is proposed to be located or if no one is designated by the Town, or if the activity is proposed for a village, the Village, a representative of the appropriate County Planning Department, provided, however, that a Town, or if the activity is proposed for a village, the Village, may at any time designate a representative to replace the one designated by the County Planning Department; and a representative of the County Department of Health from the County in which the activity requiring a stormwater pollution prevention plan is proposed to be located, or in a County without a County Department of Health, a representative of the County Soil and Water Conservation Service.

(125) Stormwater retrofit means any construction of a structural stormwater management practice in a previously developed area, the modification of a structural stormwater management practice, or the implementation of a nonstructural practice to improve stormwater management and/or stormwater treatment over current conditions.

(126) Stratification means the physical condition caused primarily by temperature-created differences in water density, which results in the formation of a warm, surface layer (epilimnion), a zone of transition (metalimnion), and a cooler, deep layer of water (hypolimnion).

(127) Subdivision means any tract of land which is divided into five or more parcels of five acres or less, along an existing or proposed street, highway, easement or right-of-way, for sale or for rent as residential lots. A tract of land shall constitute a subdivision upon the sale, rental or offer for sale or lease of the fifth residential lot therefrom within any consecutive three year period.

(128) Subsurface discharge means discharge to an absorption area, i.e., a process designed to allow filtered, treated sewage effluent to be discharged into the ground as a means of ultimate disposal.

(129) Subsurface sewage treatment system means any underground system used for collecting, treating, and disposing of sewage into the ground including, but not limited to, individual and intermediate sized sewage treatment systems, as defined in these rules and regulations.

(130) Superintendent, where used in connection with a municipality with a qualifying municipal sewer use law, means "superintendent" as defined in that law.

(131) Ten-year, twenty-four hour storm means the storm, with a twenty-four hour duration, that statistically has a ten percent chance of occurring in any given year, as set forth in the "New York State Stormwater Design Manual," New York State Department of Environmental Conservation (2015).

(132) Terminal reservoir means Kensico, West Branch, New Croton, Ashokan and Rondout Reservoirs.

(133) Two-year, twenty-four hour storm means the storm, with a twenty-four hour duration, that statistically has a fifty percent chance of occurring in any given year, as set forth in the "New York State Stormwater Design Manual," New York State Department of Environmental Conservation (2015).

(134) Ulster County Fill System means a subsurface sewage treatment system used in Ulster County which has been approved by the New York State Department of Health for use in Ulster County and which is built upon two (2) feet of in situ soil that has a percolation rate between 3 to 60 minutes/inch, and which uses at least four (4) feet of fill material, including at least three (3) feet between the bottom of the trench and the in situ soil, that has a percolation rate between 3 and 10 minutes/inch. Ulster County Fill Systems may be used on individual lots or in subdivisions in Ulster County and may also be used in a county other than Ulster if the New York State Department of Health has approved the system for use in such other county.

(135) Village means a territory which has been incorporated as a village pursuant to Article 2 of the New York State Village Law.

(136) Village extension means an area immediately adjoining a main road extending outside an existing village which has been designated as a village extension by a Town Board in the West of Hudson watershed and described in a Water Supply Permit duly issued by the New York State Department of Environmental Conservation or in any written agreement among the affected parties to the 1997 New York City Watershed Memorandum of Agreement, including the New York State Department of Environmental Conservation.

(137) Wastewater treatment plant means any facility which treats sewage or discharges treated effluent not intended to receive further treatment in the watershed, and which requires a permit under Titles 7 or 8 of Article 17 of the Environmental Conservation Law. A wastewater treatment plant is installed for the purpose of treating, neutralizing, stabilizing or disposing of sewage by removal of contaminants accomplished by unit operations or processes or by a combination of such operations and processes as may be applicable to a given design for a wastewater treatment plant. Wastewater treatment plants shall not include intermediate sized sewage treatment systems as defined in these rules and regulations.

(138) Water Quality Volume (WQ v ) means the storage needed to capture and treat 90% of the average annual stormwater runoff volume. WQv is calculated as follows:

WQv = (P)(R v )(A) 12

where:

WQv = water quality volume (in acre-feet)

P = 90% Rain Event Number as set forth in the "New York State Stormwater Design Manual," New York State Department of Environmental Conservation (2015).

Rv = 0.05 + 0.009(I), where I is percent impervious cover

A = site area in acres

(139) Water supply means the New York City public water supply system, and includes all watercourses, wetlands, reservoirs, reservoir stems and controlled lakes tributary thereto.

(140) Watercourse means a visible path through which surface water travels on a regular basis, including an intermittent stream, which is tributary to the water supply. A drainage ditch, swale or surface feature that contains water only during and immediately after a rainstorm or a snowmelt shall not be considered to be a watercourse.

(141) Watershed means the land area contributing surface water to the New York City water supply.

(142) Watershed Agricultural Council means the Watershed Agricultural Council for the New York City Watershed, Inc., a not-for-profit organization with its principal place of business at 33195 State Highway 10, Walton, New York 13856.

(143) West of Hudson watershed means the Ashokan, Cannonsville, Pepacton, Neversink, Rondout, and Schoharie Reservoirs and their drainage basins.

(144) Wetland means an area in the watershed that was mapped by the New York State Department of Environmental Conservation as a regulated wetland on or before December 31, 2024.

(145) Winter highway maintenance materials means the solid compounds or the solutions that are commonly used for traction on, or for the abatement of, winter road ice, including, but not limited to, chloride compounds, and mixtures of sand and chloride compounds.

(Amended City Record 10/30/2019, eff. 11/29/2019; Amended City Record 1/29/2025, eff. 2/28/2025)

§ 18-17. References

Open this section

The following laws, guidance documents, regulations or technical material have been incorporated by reference in this 15 RCNY Chapter 18. These references are available online at the web pages listed below and for physical inspection and copying at the Department of Environmental Protection, Bureau of Water Supply, Division of Water Quality, 465 Columbus Avenue, Valhalla, New York, 10595, and at the New York State Department of Health, Office of Regulatory Affairs, Tower Building, Room 2415, Empire State Plaza, Albany, NY 12237, or can be directly obtained from the sources listed for the given reference.

(1) Federal Categorical Pretreatment Standards, 40 C.F.R. Part 403, 1992, Superintendent of Documents, United States Government Printing Office, Washington, D.C. 20402, available at https://www.ecfr.gov/current/title-40/chapter-I/subchapter-N/part-403.

(2) USDA Soil Conservation Service Soil Type Boundaries, USDA SCS, Room 771, Federal Building, 100 South Clinton Street, P.O. Box 7248, Syracuse, New York 13261-7248, available at https://websoilsurvey.nrcs.usda.gov/app/.

(3) National Engineering Handbook, Part 630, Chapter 7, Hydrologic Soil Groups, U.S. Department of Agriculture, National Resources Conservation Service, 2009, U.S. Department of Agriculture 1400 Independence Ave., Washington, D.C. 20250, available at https://efotg.sc.egov.usda.gov/references/public/FL/FL7-3a-b.pdf.

(4) New York State Department of Environmental Conservation Technical and Operational Guidance Series (TOGS) 1.1.1, Ambient Water Quality Standards and Guidance Values and Groundwater Effluent Limitations (October 22, 1993, Reissue Date June 1998, as modified and supplemented by the January 1999 Errata Sheet and the April 2000 and June 2004 Addenda), New York State Department of Environmental Conservation, 625 Broadway, Albany, New York 12233, available at https://extapps.dec.ny.gov/docs/water_pdf/togs111.pdf.

(5) New York State Department of Environmental Conservation Technical and Operational Guidance Series (TOGS) 1.3.1, Total Maximum Daily Loads and Water Quality Based Effluent Limits (July 8, 1996, Revised February 1998), including Amendments A through E (July 8, 1996), New York State Department of Environmental Conservation, 625 Broadway, Albany, New York 12233.

(6) New York State Department of Environmental Conservation Technical and Operational Guidance Series (TOGS) 1.3.1B, Total Maximum Daily Loads and Water Quality-Based Effluent Limits, Amendments-Low and Intermittent Stream Standards (July 8, 1996), New York State Department of Environmental Conservation, 625 Broadway, Albany, New York 12233, available at https://extapps.dec.ny.gov/docs/water_pdf/togsb96.pdf.

(7) New York State Department of Environmental Conservation SPDES General Permit for Stormwater Discharges from Construction Activity, Permit No. GP-0-15-002, Effective January 29, 2015, New York State Department of Environmental Conservation, 625 Broadway, Albany, New York 12233, available at https://www.nyc.gov/site/dep/environment/regulations.page.

(8) New York State Design Standards for Intermediate Sized Wastewater Treatment Systems, 2014, New York State Department of Environmental Conservation, 625 Broadway, Albany, New York 12233, available at https://extapps.dec.ny.gov/docs/water_pdf/2014designstd.pdf.

(9) New York State Stormwater Design Manual, 2015, New York State Department of Environmental Conservation, 625 Broadway, Albany, New York 12233, available at https://extapps.dec.ny.gov/fs/docs/pdf/stormwaterdesignmanual2015.pdf.

(10) Model Sewer Use Law, 1994, New York State Department of Environmental Conservation, 625 Broadway, Albany, New York 12233, available at available at https://extapps.dec.ny.gov/docs/water_pdf/modelseweruselaw.pdf.

(11) Recommended Standards for Wastewater Facilities, Great Lakes-Upper Mississippi River Board of State and Provincial Public Health and Environmental Managers, 2014, Health Education Services, Health Education Services Division, P.O. Box 7126, Albany, New York 12224, available at https://extapps.dec.ny.gov/fs/projects/spdes/TenStateStrdsWastewater.pdf.

(12) Maps delineating New York State Department of Environmental Conservation regulated wetlands in the watershed on or before December 31, 2024, available at https://www.nyc.gov/site/dep/environment/regulations.page.

(Amended City Record 10/30/2019, eff. 11/29/2019; Amended City Record 1/29/2025, eff. 2/28/2025)

§ 18-21. Standards for Regulated Activities

Open this section

(a) The following general standards apply to all regulated activities unless specifically noted otherwise, whether or not the regulated activity also requires the review and approval of the Department. In addition, certain regulated activities must meet additional standards or procedures where specifically set forth in this subchapter or in other subchapters:

(1) All regulated activities shall be planned, designed, scheduled and conducted in such manner as to not constitute a source of contamination to or degradation of the water supply.

(2) The Department shall base its review and approval of any regulated activity on compliance with these rules and regulations, including the water quality standards set forth in Subchapter D, and shall additionally take into consideration the system specific water quality characteristics set forth in Appendix 18-B.

(3) The burden of demonstrating compliance with the requirements of these rules and regulations shall be on the person proposing to engage in a regulated activity. In the event that any person finds that compliance with any standard set forth in these rules and regulations is not possible, then she or he may apply for a variance in accordance with the provisions of Subchapter F of these rules and regulations. Variances may be granted provided that the Department makes the findings required by Subchapter F of these rules and regulations.

(4) Failure to comply with the conditions of any approval issued by the Department under these rules and regulations shall be a violation of these rules and regulations.

(5) The Department may order that a regulated activity cease, and/or a facility where such regulated activity is taking place be closed or removed, if such regulated activity is causing contamination to or degradation of the water supply, such that the activity is a threat to the life, health, or safety of water supply users that requires immediate corrective action. Any person who receives such an order may request a hearing on such order in the manner provided in 15 RCNY § 18-29.

§ 18-22. Procedures for Notification and/or Reporting

Open this section

Where any notification, application or reporting to the Department required by these rules and regulations is to be made in writing, it shall be sent by certified mail to both the local Department representative in the portion of the watershed in which the regulated activity takes place and to the Engineering Section. Addresses are listed in 15 RCNY § 18-15.

§ 18-23. Application Procedures and Requirements

Open this section

(a) These procedures shall apply to the following:

(1) Applications for review and approval of regulated activities, including renewals of approvals of regulated activities. An application for renewal of an approval of a regulated activity shall be submitted to the Department no less than 180 days prior to the expiration of the approval. This deadline shall apply unless stated otherwise in a special condition of the approval.

(2) Applications for review and approval of a substantial alteration or modification of any regulated activity;

(3) Applications for review and approval of any substantial alteration or modification of a noncomplying regulated activity; and

(4) Applications for variances pursuant to Subchapter F of these rules and regulations.

(b) The applicant shall meet the following requirements:

(1) No person shall undertake any activity listed in 15 RCNY § 18-14 which requires the review and approval of the Department without first obtaining written approval from the Department, except where a temporary emergency approval has been obtained from the Department pursuant to 15 RCNY § 18-24.

(2) Any person proposing to undertake any activity listed in 15 RCNY § 18-14 which requires the review and approval of the Department, shall submit to the Department, at the address of the Department representative for the area where the regulated activity is to be undertaken set forth in 15 RCNY § 18-15, an application for review and approval which includes a plan of the activity which meets the requirements of this subchapter and any additional requirements for the specific activity set forth in these rules and regulations. Failure by the applicant to submit information to the Department or to follow the Department procedures set forth in these rules and regulations is sufficient grounds to deny the approval.

(3) Any person seeking approval of an activity may be subject to such terms and conditions as the Department may require, including time limitations and limitations on transfer of the approval given by the Department.

(4) (i) An applicant shall affirmatively state in the application whether any enforcement action has been commenced during the five (5) years preceding the application against the applicant, or any principal or affiliate of the applicant, for alleged violations of law related to the specific regulated activity for which the approval is sought, or related to the facility or site at which the activity is located. The applicant shall supply the following information with respect to each enforcement action: the agency or entity commencing the action, the date of commencement, the facility location and address where the alleged violation occurred, and disposition of the action.

(ii) Failure to fully and accurately disclose any material information required to be disclosed pursuant to subparagraph 4(i) shall be a basis for the Department to deny a permit application.

(iii) Failure to cure any adjudicated violation of this Chapter or any law, rule or regulation enforced by the Department shall be a basis to deny a permit application.

(iv) If the Department or the City has commenced an enforcement action against the applicant for violations of law related to the facility or site at which the activity for which the approval is sought is located, the Department may suspend processing of the application until such alleged violations are cured.

(5) Any property owner may request that the Department perform a site visit and evaluation to determine and flag the presence of a watercourse, reservoir, reservoir stem or controlled lake on the owner's property. If the property owner supplies the Department with a surveyor's map of the property which includes a representation of the flagged watercourses, reservoirs, reservoir stems or controlled lakes identified by the Department, the Department shall confirm or annotate the findings upon the surveyor's map as soon as is practicable. A confirmed survey map shall be binding upon the Department for five years following the date of the confirmation.

(6) If an applicant for Department review and approval of a regulated activity requests that the Department conduct a site visit and evaluation to determine and flag the presence of a watercourse, reservoir, reservoir stem or controlled lake on the applicant's property the Department shall do so as soon as is practicable. If the applicant supplies the Department with a surveyor's map of the property which includes a representation of the flagged watercourses, reservoirs, reservoir stems or controlled lakes identified by the Department, the Department shall confirm or annotate the findings upon the surveyor's map within 20 business days of receipt thereof. A confirmed survey map shall be binding upon the Department for five years following the date of the confirmation. The absence of a Department confirmed surveyor's map will not cause an application to be considered incomplete.

(c) An application shall contain the following information:

(1) An application for the review and approval of any activity listed in 15 RCNY § 18-14 shall provide a description of the activity, the location and topography of the area of the activity, identification of any existing structures at the location, and any engineering, construction or other plans which detail the methods to be used in undertaking the activity such that it shall meet the requirements of this subchapter and any additional requirements for the specific activity set forth in these rules and regulations.

(2) An application for review and approval of any activity listed in 15 RCNY § 18-14 shall include a copy of any Environmental Assessment Form (EAF), and either a Draft Environmental Impact Statement (DEIS) or a determination of nonsignificance by the lead agency, where such documents are prepared pursuant to Article 8 of the Environmental Conservation Law and the rules and regulations promulgated thereunder.

(3) When a regulated activity requires a related approval from any other agency or more than one approval from the Department, the application for review and approval shall include a list of such approvals which the applicant knows to be required, and a statement of the status of any required approval at the time of filing of the application with the Department.

(4) An application for review and approval of any regulated activity shall include the name, address, telephone number, email address, and fax number of the applicant or the applicant's authorized representative, and of the design professional(s), if any, involved in preparing the application.

(d) Review and Approval Procedures.

(1) The applicant proposing to engage in any activity listed in 15 RCNY § 18-14 which requires the review and approval of the Department shall certify in writing that she or he believes that the application is complete and in compliance with the requirements of this subchapter and any additional requirements for the specific activity set forth in these rules and regulations.

(2) An application is complete when it is determined by the Department to contain sufficient information for the purpose of commencing review of the application. The Department retains the right to seek additional information in order to enable the Department to make a determination pursuant to these rules and regulations. Within ten (10) days of receiving an application for review and approval of a conventional individual sewage treatment system to be installed on an individual lot which is not within a subdivision, or within twenty (20) days of receiving any other type of application for review or approval, the Department shall either:

(i) Notify the applicant in writing that the application is complete and that the Department shall commence its review; or

(ii) Notify the applicant in writing that the application is incomplete and specifically request all additional information from the applicant as the Department deems necessary. If additional information is requested or comments are issued by the Department that need to be addressed by the applicant, the twenty (20) day period described in paragraph (d)(4) of this subdivision or the forty-five (45) day period described in paragraph (d)(5) of this subdivision shall not commence to run. The Department shall notify the applicant in writing within ten (10) days of receiving the additional information that has been requested either that the application is complete and that the Department has commenced its review or that further information is required.

(iii) Except in cases where the applicant has submitted false or misleading information or where a change in relevant law has occurred or changes have been proposed for the project, the Department may require further information based only upon the additional information submitted by the applicant or new issues raised by such information. In addition, the Department may also require further information based on a change in ownership of the property, the identity of the applicant, or the identity of the applicant's owners, principals, shareholders, directors, or officers.

(3) If the Department fails to notify an applicant in writing of its determination as to the completeness or incompleteness of the application within the time periods set forth in paragraph (d)(2) of this subdivision, the applicant may notify the Department of its failure by means of certified mail, return receipt requested, to the local Department representative identified in 15 RCNY § 18-15 who is responsible for processing the application and a copy to the Engineering Section. If the Department fails to notify the applicant of its determination as to the completeness or incompleteness of the application within ten (10) business days of receiving the notice, the application shall be deemed complete as of the eleventh day.

(4) The Department shall notify the applicant in writing of its determination within twenty (20) days of determining that an application for review and approval of a conventional individual sewage treatment system to be installed on an individual lot which is not within a subdivision is complete pursuant to the procedures set forth in paragraph (d)(2) of this subdivision unless the Department and the applicant mutually agree in writing upon an extension of the twenty (20) day review period. If, during the twenty (20) day review period, the Department requests revisions to the application, the review period shall be suspended from the date such request is made until the date on which the Department receives such revisions, provided that the Department shall have no fewer than ten (10) days from the date of receipt to issue a determination.

(5) For all applications for review and approval, other than for a conventional individual sewage treatment system to be installed on an individual lot which is not within a subdivision, the Department shall notify an applicant in writing of its determination within forty-five (45) days of notifying the applicant that the application is complete pursuant to the procedures set forth in paragraph (d)(2) of this subdivision unless the Department and the applicant mutually agree in writing upon an extension of the forty-five (45) day review period. If, during the forty-five (45) day review period, the Department requests revisions to the application, the review period shall be suspended from the date such request is made until the date on which the Department receives such revisions, provided that the Department shall have no fewer than ten (10) days from the date of receipt to issue a determination.

(6) If the Department fails to notify an applicant in writing of its determination within the twenty (20) day time period as set forth in paragraph (d)(4) of this subdivision or the forty-five (45) day time period as set forth in paragraph (d)(5) of this subdivision, the applicant may notify the Department of its failure by means of certified mail, return receipt requested to the local Department representative identified in 15 RCNY § 18-15 who is responsible for processing the application and a copy to Regulatory and Engineering Programs. The notice shall contain the applicant's name, location of the proposed project, the office in which the application was filed, and a statement that a decision is sought in accordance with this subdivision. Any notice failing to provide this information will not invoke this provision.

(i) If the Department fails to notify the applicant of its decision within ten (10) business days of the receipt of such notice, the application shall be deemed approved subject to the standard terms and conditions applicable to such an approval.

(7) Notwithstanding the time period for notifying an applicant of the Department's determination specified in paragraphs (d)(4), (d)(5) and (d)(6) of this section, if a lead agency has determined that a project may have a significant effect on the environment for purposes of the State Environmental Quality Review Act (SEQRA), such time periods shall be suspended pending receipt from the lead agency of either a Final Environmental Impact Statement (FEIS) or a determination of nonsignificance. Upon receipt of either document, the time periods shall resume, provided, however, that the Department shall have at least twenty (20) days to notify an applicant of its determination.

(8) Notwithstanding the time periods for decisions specified in this subdivision, the Department may condition an approval on the applicant providing satisfactory proof of any bonds required by the Department within thirty days of the applicant receiving the conditional approval from the Department.

(9) Any notice required or permitted to be given by the Department under this subchapter shall be given in such manner designed to reach the applicant, as the Department deems appropriate, and may include, but is not limited to, regular mail, certified mail return receipt requested, or telecopier.

(Amended City Record 10/30/2019, eff. 11/29/2019)

§ 18-24. Emergency Procedures

Open this section

(a) Notwithstanding any other provision of this subchapter, where an expedited review and approval of a regulated activity is necessary to respond to an imminent threat to the health and safety of humans or animals, or to respond to a substantial imminent threat to property, an applicant seeking such review and approval shall notify the Department by telephone at the office of the local representative listed in 15 RCNY § 18-15, and shall meet with the Department within 24 hours. At the meeting the applicant shall present to the representative of the Department such available information regarding the regulated activity as would otherwise be required in a written application for review and approval of the regulated activity. Additionally, the applicant shall provide an explanation of the nature of the imminent threat that necessitates the expedited review. The Department shall review the information supplied by the applicant and shall issue a temporary determination to approve or disapprove the application within 24 hours of receipt of the information required by this subdivision.

(1) An applicant shall not be required to notify the Department before undertaking the routine repair and maintenance of a subsurface sewage treatment system, including, but not limited to, the pump-out of a septic tank, the repair of a broken lateral, the leveling of a distribution box, or the removal of a blockage.

(b) An approval granted by the Department pursuant to the emergency expedited review procedure shall be a temporary approval only, and shall not be considered to be a final approval of the Department. The temporary approval may contain conditions and time limitations and shall be limited to whatever actions are necessary to abate the imminent threat. A final approval shall be issued by the Department only after review and approval of a complete written application submitted in accordance with the procedures and standards set forth in subdivision (c) of this section, and any other applicable provisions of this subchapter and these rules and regulations.

(c) An applicant who has received a temporary approval for a regulated activity pursuant to the emergency expedited review procedure shall, within twenty days of such approval, submit a written application to the Department containing all of the information required to be provided by these rules and regulations for the particular regulated activity.

§ 18-25. Optional Pre-application Conference

Open this section

(a) If a proposed regulated activity requires one or more Department reviews or approvals, or the preparation of an Environmental Impact Statement pursuant to the State Environmental Quality Review Act, the prospective applicant may request an optional pre-application conference with the appropriate Department staff as a means of clarifying application procedures to be followed in order to comply with the requirements set forth in these rules and regulations.

(b) The request for a pre-application conference should be made at the earliest possible stage of the applicant's planning process. Such request shall be made in writing to the Department representative for the area where the regulated activity is to be undertaken, as set forth in 15 RCNY § 18-15. A mutually agreed upon time and place shall be scheduled for the pre-application conference.

(c) In order to assist the prospective applicant, prior to the preapplication conference, the prospective applicant shall submit to the Department representative the following information:

(1) A description of the proposed regulated activity, a site plan or sketch showing the location and topography of the area of the activity, identification of any existing structures at the location, and any engineering, construction or other plans which describe the methods to be used to meet the requirements of these rules and regulations;

(2) A statement of the prospective applicant's timetable and financial plans for carrying out the proposed regulated activity, if known;

(3) A statement of any governmental financial aid, facilities, or other assistance which the prospective applicant expects to be provided or plans to request for the regulated activity; and

(4) Such other information as the Department deems reasonably necessary.

(d) At the pre-application conference, the proposed project will be informally discussed. Based on information provided by the applicant, review and approval requirements will be identified and the applicant will be provided with guidance concerning the application and review process. Participation in the preapplication process shall not relieve an applicant from the requirements of obtaining all approvals otherwise necessary under these rules and regulations or any other law or rules and regulations, prior to commencing the regulated activity.

§ 18-26. Modification, Suspension or Revocation of Approvals and Variances

Open this section

(a) An approval or variance issued by the Department pursuant to these rules and regulations may be modified, suspended or revoked at any time upon the Department's initiative, on any of the grounds set forth in paragraphs (1) through (5) of this subdivision.

(1) Materially false or inaccurate statements in the approval or variance application or supporting documents;

(2) Failure by the person named in the approval or variance to comply with any terms or conditions of the approval or variance;

(3) The scope of the project, as described in the application, is exceeded;

(4) Newly discovered material information or a material change in environmental conditions, relevant technology or applicable law or rules and regulations since the issuance of the existing approval or variance; or

(5) Noncompliance with previously issued approval or variance conditions, orders of the Commissioner, or with any provisions of the rules and regulations of the Department related to the activity.

(b) The Department shall send a notice of intent to modify, suspend or revoke an approval or variance to the person named in the approval or variance by certified mail, return receipt requested or by personal service. The notice shall specify the ground or grounds on which the modification, suspension, or revocation is sought, as well as the alleged facts on which the modification, suspension, or revocation is based.

(c) Within fifteen calendar days of receipt of a notice of intent, the person named in the approval or variance may submit a written statement to the Department, giving reasons why the approval or variance should not be modified, suspended or revoked. Failure by such person to timely submit a statement shall result in the Department's action becoming effective on the date specified in the notice of intent.

(d) Within fifteen calendar days of receipt of such person's statement, the Department shall either:

(1) Rescind the notice of intent based on a review of the information provided by such person;

(2) Confirm the Department's intent to modify, suspend, or revoke the approval or variance as stated in the notice of intent; or

(3) Amend the Department's notice of intent, specifying the Department's revised intent to modify, suspend, or revoke the approval or variance.

(e) If the Department confirms or amends its intent to modify, suspend, or revoke the approval or variance, the person named in the approval or variance may request a hearing on the Department's determination by submitting a petition in writing to the Office of Administrative Trials and Hearings ("OATH"), and sending a copy of the petition to the Commissioner, within thirty (30) days of receipt of confirmation of the Department's intent, in accordance with the following:

(1) Form and content of petition. The petition must state the name, address, and email address of the petitioner and must include a short and plain statement of the matters to be heard by OATH. The following documents must be included with the petition: the Department's notice of intent to modify, suspend, or revoke the approval or variance; the petitioner's statement giving reasons why the approval or variance should not be modified, suspended or revoked; the Department's confirmation or amendment of its intent; and a completed OATH intake sheet. Blank intake sheets are available from the Department.

(2) Department response. Within twenty (20) days of receipt of the petition, the Commissioner may respond to the petition. If the Commissioner responds, the Commissioner must include the record on which the determination was based. A copy of any response shall be sent to the petitioner.

(3) Proceedings before the OATH Trials Division. Upon receipt of the petition for a hearing, OATH shall promptly schedule a hearing at a time and date which shall not be less than thirty (30) days, nor exceed one hundred twenty (120) days, from the date of receipt by OATH of the petition for a hearing unless the parties and the ALJ agree to another date. The hearing may be held in the district of the Department where the activity that is the subject of the order is located, except that hearings may be held at the Department's offices in Kingston, New York for petitions relating to regulated activities in the East of Hudson watershed and at the Department's offices in Kingston, New York for petitions relating to regulated activities in the West of Hudson watershed. The hearing may also be held by video conferencing or other electronic means, or as otherwise agreed to by the parties and the ALJ. Notice of such hearing shall be provided in writing to the petitioner and to the Department.

(4) Burden of proof. The Department shall have the burden of proving, by a preponderance of the evidence, facts supporting the modification, suspension or revocation.

(5) The hearing shall be held before an OATH ALJ. The ALJ shall cause a record of the hearing to be made, and shall make a recommendation to the Commissioner within thirty (30) days of the close of the hearing record, setting forth the appearances, the relevant facts and arguments presented at the hearing, findings of fact and conclusions of law, and a recommendation as to whether approval or variance should be modified, suspended, or revoked and the reasons therefor. A transcript of the record of the hearing shall be made available at the petitioner's request and expense.

(f) Within thirty (30) days of receipt of the recommendation of the ALJ, the Commissioner shall issue a final decision approving, rejecting, or modifying the ALJ's recommendation and shall serve that decision on the parties to the proceeding. If the Commissioner does not act within that time, the ALJ's recommendation shall be deemed adopted by the Commissioner.

(g) Where the Department proposes to modify, suspend, or revoke an approval or variance, and the person named in the approval or variance requests a hearing on the proposed modification, suspension, or revocation, the original conditions of the approval or variance shall remain in effect until a decision has been issued by the Commissioner pursuant to subdivision (f) of this section. At such time the modified conditions shall take effect.

(h) Nothing in this section shall preclude or affect the Department's authority to use the remedy of summary abatement or to issue a cease and desist order under these rules and regulations, or any other law or regulation or to seek injunctive relief to enforce these rules and regulations, or any other law or regulation, in a court of competent jurisdiction.

(Amended City Record 10/30/2019, eff. 11/29/2019)

§ 18-27. Noncomplying Regulated Activities

Open this section

(a) General requirements.

(1) A noncomplying regulated activity may be continued except where specifically prohibited from continuing by these rules and regulations.

(2) A noncomplying regulated activity shall come into compliance with these rules and regulations where specifically required to do so by these rules and regulations.

(3) Should any noncomplying regulated activity cause contamination to or degradation of the water supply, such that the activity is a threat to the life, health, or safety of water supply users, the Commissioner may order that such noncomplying regulated activity conform either in whole or in part to the requirements of these rules and regulations, immediately or within a limited period of time at the Commissioner's discretion, or be discontinued immediately. Any person who receives such an order may request a hearing on such order in the manner provided in 15 RCNY § 18-29.

(4) Any owner or operator of a noncomplying regulated activity who was not required by these rules and regulations to notify the Department pursuant to paragraph (1) of subdivision (b) of this section, may request, in writing, a determination from the Department that such property or activity is a noncomplying regulated activity. The written request shall include a description of the property or activity and its location, and the name, telephone number, and email address of a contact person. The Department shall determine, based upon the submission, whether the property or activity is a noncomplying regulated activity, and shall notify the owner or operator of such determination in writing.

(b) Subsurface Sewage Treatment Systems. The regulations applicable to discontinuation, and the standards for alteration or modification, of noncomplying regulated activities that are subsurface sewage treatment systems are set forth in 15 RCNY § 18-38(b).

(c) Storage of hazardous substances, storage of petroleum products, and the siting of junkyards and solid waste management facilities.

(1) No noncomplying regulated activity involving storage of hazardous substances, storage of petroleum products, or the siting of junkyards and solid waste management facilities shall be substantially altered or modified without the prior review and approval of the Department. The Department shall review and approve such an alteration or modification in accordance with the standards and procedures set forth in Subchapter F (variances).

(i) Such a noncomplying regulated activity may be reduced in size or extent, or replaced with a regulated activity that complies with the provisions of these rules and regulations, without such review and approval provided that such reduction does not cause any increase in any existing discharge or any increase in the potential for contamination to or degradation of the water supply.

(2) In the case of storage of hazardous substances, storage of petroleum products, and the siting of junkyards and solid waste management facilities, a noncomplying regulated activity must come into compliance with these rules and regulations if, for any reason, there is discontinuation for a period of two consecutive years. If it cannot come into compliance, it must permanently desist. A period of discontinuation shall commence on the date when regular or seasonal use ceases. Incidental or illegal use of an unoccupied structure shall not be sufficient to interrupt a period of discontinuation, and intent to resume a noncomplying regulated activity shall not confer the right to do so. The burden of proof for showing that a noncomplying regulated activity has not been substantially discontinued shall be on the owner or operator.

(Amended City Record 10/30/2019, eff. 11/29/2019)

§ 18-28. Appeals

Open this section

(a) An applicant may appeal a final determination issued by the Department under these rules and regulations by filing a petition in writing with the Department and with the New York City Office of Administrative Trials and Hearings, Trials Division ("OATH") within thirty (30) days of the date the determination was mailed. The petition shall state the name, address, and email address of the petitioner and shall include a short and plain statement of the matters to be adjudicated, identifying the approval or variance sought by the petitioner with citation to the applicable provisions of these rules and regulations, the regulated activity for which the Department issued the determination, the proposed location of the activity, and the date of the Department's determination. The petition should also indicate whether the petitioner is requesting a hearing. A copy of the determination being appealed shall be attached to the petition. In addition, a completed OATH intake sheet shall be included with the petition. Blank intake sheets are available from the Department.

(b) The following determinations of the Department are appealable:

(1) A denial of an application for approval of a regulated activity.

(2) A denial of an application for a variance.

(3) The imposition of a substantial condition in an approval of a regulated activity.

(4) The imposition of a substantial condition in a grant of a variance.

(c) Petitions for appeal shall be referred to a City administrative law judge (ALJ) for hearing, where allowed by this section, and determination as defined in subdivision (g).

(d) The following issues are reviewable on appeal:

(1) Whether the regulated activity proposed by the petitioner will be in compliance with the requirements of these rules and regulations.

(2) Whether the imposition of a substantial condition in an approval of a regulated activity is appropriate to ensure that the regulated activity will comply with the requirements of these rules and regulations.

(3) Whether the Commissioner has abused his or her discretion in denying a request for a variance or in imposing a substantial condition in a grant of a variance.

(4) Except where the Department has acted as lead agency, the ALJ shall not review any issues relating to compliance with the State Environmental Quality Review Act (SEQRA).

(e) Except for appeals from determinations relating to variances, the petitioner shall have the burden of proving by a preponderance of the evidence that the proposed regulated activity is in compliance with the requirements of these rules and regulations. For appeals from determinations relating to variances, the petitioner shall have the burden of proving that the Commissioner has abused his or her discretion.

(f) (1) Appeals from determinations relating to individual sewage treatment systems or variances shall be decided on the record before the Department in its review of the application and any other written submissions allowed by the ALJ.

(2) A petitioner may request a hearing on appeals from all other determinations issued by the Department. If a petitioner does not request a hearing, the petition shall be decided on the record before the Department in its review of the application and any other written submissions allowed by the ALJ.

(i) The hearing may be held in the district of the Department in which the regulated activity was proposed to be located, except that hearings may be held at the Department's offices in Valhalla, New York for appeals relating to regulated activities in the East of Hudson watershed and at the Department's offices in Kingston, New York for appeals relating to regulated activities in the West of Hudson watershed. The hearing may also be held by video conferencing or other electronic means, or as otherwise agreed to by the parties and the ALJ.

(g) The ALJ shall submit a report to the Commissioner within 60 days after the record on appeal is closed with a recommendation as to whether the determination appealed from should be approved, modified or rejected. The Commissioner shall issue a final decision approving, rejecting, or modifying the ALJ's recommendation within 30 days of receipt of the ALJ's report. If the Commissioner does not act within that time, the ALJ's recommendation shall be deemed approved by the Commissioner.

(h) This section shall not apply to determinations made by local governments administering provisions of these rules and regulations pursuant to Subchapter G.

(i) An applicant shall have the option whether to file an appeal under this section and nothing in this section shall preclude an applicant from challenging the final determination issued by the Department in a court of competent jurisdiction, including instituting a proceeding under Article 78 of the Civil Practice Law and Rules, without first filing a petition for appeal pursuant to this section.

(Amended City Record 10/30/2019, eff. 11/29/2019)

§ 18-29. Hearings on Cease and Desist Orders

Open this section

(a) Any person who receives a cease and desist order may request a hearing on the order by submitting a petition in writing to the Commissioner and to the Office of Administrative Trials and Hearings, Trials Division ("OATH") within seven (7) days of receipt of the cease and desist order. The petition for a hearing shall state the name, address, and email address of the petitioner and shall include a short and plain statement of the matters to be adjudicated, identifying the activity that is the subject of the order, the location of the activity, and the date of the cease and desist order. A copy of the order shall be attached to the petition. In addition, a completed OATH intake sheet shall be included with the petition. Blank intake sheets are available from the Department.

(b) Upon receipt of the petition for a hearing, OATH shall schedule a hearing promptly in the district of the Department where the activity that is the subject of the order allegedly occurred, and at a time and date which shall not exceed fifteen (15) days from the date of receipt by OATH of the petition for a hearing unless the parties and the ALJ agree to another location and date, except that hearings may be held at the Department's offices in Valhalla, New York for petitions relating to regulated activities in the East of Hudson watershed and at the Department's offices in Kingston, New York for petitions relating to regulated activities in the West of Hudson watershed. The hearing may also be held by video conferencing or other electronic means. Notice of such hearing shall be provided in writing to the petitioner and to the Department.

(c) A petition for a hearing shall not stay compliance with the cease and desist order, and it shall continue to be the duty of the petitioner to discontinue the activity pursuant to the terms of the order. Failure to do so shall be a violation of the order and these rules and regulations.

(d) At the hearing, the Department shall have the burden of proving by a preponderance of the evidence, facts supporting the cease and desist order.

(e) The failure of the petitioner to appear at the time, date and place set forth in the notice of hearing shall constitute a waiver of the right to a hearing on the cease and desist order and the matter will be dismissed.

(f) The hearing shall be held before an OATH ALJ. The ALJ shall cause a record of the hearing to be made, and shall make a report to the Commissioner within ten (10) days of the close of the hearing record, setting forth the appearances, the relevant facts and arguments presented at the hearing, findings of fact and conclusions of law, and a recommendation as to whether the order should be continued, modified or vacated and the reasons therefor. A transcript of the record of the hearing shall be made available at the petitioner's request and expense.

(g) Within ten (10) days of receipt of the recommendation of the ALJ, the Commissioner may continue, vacate, or modify the order. If the Commissioner does not act within that time, the ALJ's recommendation shall be deemed adopted by the Commissioner.

(h) The results of the hearing on the cease and desist order do not affect the right of a person to apply for an approval or variance for a regulated activity under these regulations. In reviewing an application in connection with a regulated activity that has been the subject of a cease and desist order, however, the Department may take action on account of any violation of law, rule, regulation or order arising out of the events, situations or circumstances which led to the issuance of the order.

(Amended City Record 10/30/2019, eff. 11/29/2019)

§ 18-30. State Environmental Quality Review Act (SEQRA)

Open this section

The following activities are deemed by the Department to be "Type II" actions under SEQRA and its implementing regulations, and the Department shall not require an environmental impact statement or any other determination or procedure under SEQRA for these activities:

(a) Installation of a new individual sewage treatment system on an individual lot which is not within a subdivision, or within a subdivision which has been approved as of the effective date of these rules and regulations.

(b) Any alteration or modification of an existing individual sewage treatment system.

§ 18-31. Pathogenic Materials

Open this section

Unless otherwise permitted by these rules and regulations, a discharge, or storage which is reasonably likely to lead to a discharge, of pathogenic materials into the environment (including into groundwater), and which is reasonably likely to cause degradation of surface water quality or of the water supply, is prohibited. It shall be an affirmative defense under this section that such discharge, or storage likely to lead to a discharge, is either permitted or not prohibited under federal law, and is either permitted or not prohibited under state law.

§ 18-32. Hazardous Substances and Hazardous Wastes

Open this section

(a) Unless otherwise permitted by these rules and regulations, a discharge, or storage which is reasonably likely to lead to a discharge, of hazardous substances or hazardous wastes into the environment (including into groundwater), and which is reasonably likely to cause degradation of surface water quality or of the water supply, is prohibited. It shall be an affirmative defense under this subsection that such discharge, or storage likely to lead to a discharge, is either permitted or not prohibited under federal law, and is either permitted or not prohibited under state law.

(b) New storage facilities or new tanks at an existing facility for the storage of hazardous substances regulated under 6 NYCRR Part 596, and new process tanks, as defined in 6 NYCRR § 596.1(c)(35), which would be regulated under 6 NYCRR Part 596 if not for the exemption of process tanks under 6 NYCRR § 596.1(b)(3)(i), are prohibited within the limiting distance of 100 feet of a watercourse or wetland, or within the limiting distance of 500 feet of a reservoir, reservoir stem, or controlled lake, except as provided in subdivision (d) of this section.

(c) The owner or operator of a new facility, or a new or substantially modified tank at an existing facility, for the storage of hazardous substances which is regulated under 6 NYCRR Part 596 and which is located between the limiting distance of 100 and 250 feet of a watercourse or wetland, must comply with the following conditions:

(1) The owner or operator shall submit to the Department a copy of any registration forms required by 6 NYCRR § 596.2(d) and (e) and any notification forms required by 6 NYCRR § 596.2(f) at the time such forms are submitted to the New York State Department of Environmental Conservation. When, on an emergency basis, new storage tanks are installed or existing storage tanks are substantially modified in order to protect public health, safety or the environment, the owner or operator shall notify the Department no later than two hours after the decision is made by the owner or operator to install or substantially modify the tank.

(2) The owner or operator shall submit to the Department a copy of any spill prevention report required to be prepared or updated by 6 NYCRR § 598.1(k), within thirty (30) days of preparing or updating such report.

(3) Failure to comply with the provisions of 6 NYCRR § 596.6 (spill response, investigation and corrective action) is a violation of these rules and regulations.

(4) Failure to comply with 6 NYCRR Part 599 (Standards for New or Modified Hazardous Substance Storage Facilities) is a violation of these rules and regulations.

(d) Subdivision (b) of this section shall not apply to:

(1) The storage of any hazardous substance that is a noncomplying regulated activity, including the replacement in kind of an existing storage tank provided that the replacement tank is designed and installed in compliance with Federal, State and local law. To the extent practicable, the new tank shall be located outside of the limiting distances of 100 feet of a watercourse or wetland, or outside of the limiting distance of 500 feet of a reservoir, reservoir stem, or controlled lake;

(2) The storage of hazardous substances where such storage is necessary to operate a wastewater treatment plant approved by the Department; and

(3) The storage of hazardous substances where such storage is made necessary by construction of a new facility or the alteration or modification of an existing facility used in connection with the operation of a public water supply system.

(e) [Repealed.]

§ 18-33. Radioactive Materials

Open this section

Unless otherwise permitted by these rules and regulations, a discharge, or storage which is reasonably likely to lead to a discharge, of radioactive materials into the environment (including into groundwater), and which is reasonably likely to cause degradation of surface water quality or of the water supply, is prohibited. It shall be an affirmative defense under this section that such discharge, or storage likely to lead to a discharge, is either permitted or not prohibited under federal law, and is either permitted or not prohibited under state law.

§ 18-34. Petroleum Products

Open this section

(a) Unless otherwise permitted by these rules and regulations, a discharge, or storage which is reasonably likely to lead to a discharge, of petroleum products into the environment (including into groundwater), and which is reasonably likely to cause degradation of surface water quality or of the water supply, is prohibited. It shall be an affirmative defense under this subsection that such discharge, or storage likely to lead to a discharge, is either permitted or not prohibited under federal law, and is either permitted or not prohibited under state law.

(b) New aboveground and underground petroleum storage facilities, which require registration under 6 NYCRR Part 613, or new tanks which expand the capacity of existing facilities which require registration under 6 NYCRR Part 613, are prohibited within the limiting distance of 100 feet of a watercourse or wetland, or within the limiting distance of 500 feet of a reservoir, reservoir stem, or controlled lake. If, however, the owner or operator of such facility demonstrates to the Department that the application of the limiting distances would preclude the continuation of an existing business, the facility may be expanded within the limiting distances set forth in this paragraph.

(c) New home heating oil tanks not requiring registration under 6 NYCRR Part 613, within the limiting distance of 100 feet of a watercourse or wetland, or within the limiting distance of 500 feet of a reservoir, reservoir stem, or controlled lake, are prohibited from being installed underground and shall be located either aboveground or contained in a basement with a concrete or other impervious floor.

(d) New aboveground and underground petroleum storage tanks of 185 gallons or more, which are neither home heating oil tanks regulated under subdivision (c) of this section nor located at facilities requiring registration under 6 NYCRR Part 613, are prohibited within the limiting distance of 25 feet of a watercourse or wetland, or within the limiting distance of 300 feet of a reservoir, reservoir stem, or controlled lake. If, however, the applicant demonstrates to the Department that application of the limiting distances would preclude the continuation of an existing business or the continued identical use of the existing facility, the facility may be expanded within the limiting distances set forth in this paragraph.

(e) Subdivisions (b), (c), and (d) shall not apply to:

(1) The storage of any petroleum products that is a noncomplying regulated activity;

(2) The storage of petroleum products for agricultural purposes;

(3) The replacement in kind of existing petroleum storage facilities or tanks;

(4) The storage of petroleum products where such storage is necessary to operate a wastewater treatment plant approved by the Department; and

(5) The storage of petroleum products where such storage is made necessary by construction of a new facility or the alteration or modification of an existing facility used in connection with the operation of a public water supply system.

(Amended City Record 10/30/2019, eff. 11/29/2019)

§ 18-35. Human Excreta, Holding Tanks, and Portable Toilets

Open this section

(a) Unless otherwise permitted by these rules and regulations, a discharge, or storage which is reasonably likely to lead to a discharge, of human excreta, or a discharge, or storage which is reasonably likely to lead to a discharge, from a holding tank, into the environment (including into groundwater), and which is reasonably likely to cause degradation of surface water quality or of the water supply, is prohibited. It shall be an affirmative defense under this subsection that such discharge, or storage likely to lead to a discharge, is either permitted or not prohibited under federal law, and is either permitted or not prohibited under state law.

(b) Emptying, discharging or transferring the contents of a holding tank or other sewage receptacle into any watercourse, wetland, reservoir, reservoir stem, or controlled lake is prohibited.

(c) All new holding tanks and non-waterborne systems designed for sewage in quantities of less than 1,000 gallons per day from residential properties that are either permitted or not prohibited under 10 NYCRR Appendix 75-A may be used in the watershed provided that they are constructed and operated in accordance with the following standards:

(1) Such holding tanks must have a capacity equal to at least five (5) days' design flow, with a minimum capacity of 1,000 gallons.

(2) Such holding tanks must be equipped with an alarm (audible and visible) located in a conspicuous place to indicate when pump-out is necessary.

(3) Such holding tanks must be designed, installed and maintained in a manner to promote ease of access for pumping and cleanup.

(4) If such holding tanks will be used in the winter, the tanks must be protected from freezing.

(d) New holding tanks designed for sewage in quantities of 1,000 gallons per day or more, or from non-residential properties, that are either permitted or not prohibited under state law, may be used in the watershed provided that they are constructed and operated in accordance with the following standards:

(1) The owner of such a holding tank must have and maintain an agreement with a professional hauler for disposal of waste at a facility that is permitted to accept septage, as defined in 6 NYCRR Part 364.

(2) Such holding tanks must have a capacity equal to at least twice the volume of waste to be generated between anticipated removal dates, with a minimum capacity of 1,000 gallons.

(3) Such holding tanks must have a high-level alarm positioned to allow storage of at least three days' volume of waste after activation.

(4) If such holding tanks will be used in the winter, the tanks must be protected from freezing.

(e) Portable toilets shall not be located within the limiting distance of 50 feet of a mapped stream, wetland, reservoir, reservoir stem, or controlled lake and, to the extent practicable, are not located within the limiting distance of 50 feet from a watercourse other than a mapped stream.

(Amended City Record 10/30/2019, eff. 11/29/2019)

§ 18-36. Wastewater Treatment Plants

Open this section

(a) Minimum requirements.

(1) Unless otherwise permitted by these rules and regulations, the design, construction, or operation of a wastewater treatment plant is prohibited where such design, construction, or operation causes a discharge, or storage which is reasonably likely to lead to a discharge, of sewage or sewage effluent into the environment (including into groundwater), and which is reasonably likely to cause degradation of surface water quality or of the water supply. It shall be an affirmative defense under this subsection that such discharge, or storage likely to lead to a discharge, is either permitted or not prohibited under federal law, and is either permitted or not prohibited under state law.

(2) The design of new wastewater treatment plants, and the plans and specifications resulting from that design, require the review and approval of the Department. New wastewater treatment plants must be constructed in accordance with the plans and specifications approved by the Department.

(3) The design for an expansion or an alteration or modification of wastewater treatment plants, and the plans and specifications resulting from that design, require the review and approval of the Department. Any expansion or alteration or modification of a wastewater treatment plant must be constructed in accordance with the plans and specifications approved by the Department.

(4) The owner or operator of a wastewater treatment plant shall operate and maintain the wastewater treatment plant in accordance with the operations and maintenance manual for the plant. Such manual shall be prepared by the owner and approved by the Department. Such manual shall be prepared or revised, and submitted to the Department for approval, within ninety (90) days after construction, expansion, alteration or modification of a wastewater treatment plant is completed.

(5) No new wastewater treatment plants with a surface discharge, or expansion or alteration or modification of wastewater treatment plants, shall cause a contravention of the water quality standards set forth in Subchapter D of these rules and regulations or the phosphorus water quality values set forth in the New York State Department of Environmental Conservation Technical and Operational Guidance Series (TOGS) 1.1.1, Ambient Water Quality Standards and Guidance Values and Groundwater Effluent Limitations (October 22, 1993, Reissue Date June 1998, as modified and supplemented by the January 1999 Errata Sheet and the April 2000 and June 2004 Addenda).

(6) No part of any seepage unit or absorption area for a subsurface discharge from a wastewater treatment plant shall be located within the limiting distance of 100 feet of a watercourse or wetland or within the limiting distance of 500 feet of a reservoir, reservoir stem, or controlled lake.

(7) Wastewater treatment plants with surface discharges into the watershed shall be capable of achieving 99.9 percent removal and/or inactivation of Giardia lamblia cysts and 99.99 percent removal and/or inactivation of enteric viruses.

(8) Wastewater treatment plants with either surface or subsurface discharges within the watershed shall provide phosphorus removal using the best treatment technology so that the wastewater treatment plant is designed to be operated and maintained to meet the following requirements:

SPDES Permitted Total Flow (Gallons/day) Total Phosphorus Limit (mg/l) £ 50,000 1.0 > 50,000 and < 500,000 0.5 ³ 500,000 0.2

(9) Wastewater treatment plants with surface discharges to intermittent streams in the watershed shall be operated and maintained to meet the intermittent stream effluent limits set forth in the New York State Department of Environmental Conservation Technical and Operational Guidance Series (TOGS) 1.3.1, Total Maximum Daily Loads and Water Quality-Based Effluent Limits (July 8, 1996, Revised February 1998), including Amendments A through E (July 8, 1996), and New York State Department of Environmental Conservation Technical and Operational Guidance Series (TOGS) 1.3.1B, Total Maximum Daily Loads and Water Quality-Based Effluent Limits, Amendments-Low and Intermittent Stream Standards (July 8, 1996), provided however, that the effluent limit for a discharge of a pollutant to an intermittent stream shall in no case be less stringent than the effluent limit which would apply to the same discharge of the pollutant to the first downstream perennial stream.

(10) Within one year of the effective date of these rules and regulations, the owners of all existing wastewater treatment plants shall submit to the Department for review and approval an operations and maintenance plan and a schedule setting forth a plan for bringing the wastewater treatment plant into compliance with all of the requirements of this section. Any such plan that is disapproved by the Department shall be revised and resubmitted to the Department for review and approval within ninety (90) days after the initial disapproval. Owners of existing wastewater treatment plants must secure final Department approval of such operation and maintenance plans and such a schedule setting forth a plan for bringing the plant into compliance by no later than eighteen (18) months from the effective date of these rules and regulations, and must complete all work in order for such plants to be brought into compliance with the requirements of this section by no later than five (5) years from the effective date of these rules and regulations or any extended period of time approved by the Department upon good cause shown.

(11) Existing wastewater treatment plants with surface discharges are prohibited from expanding if they are located in an area where new wastewater treatment plants with surface discharges are prohibited by these rules and regulations. This paragraph shall not apply to existing wastewater treatment plants which discharge subsurface or the expansion of existing wastewater treatment plants where the expanded portion discharges subsurface.

(12) Existing wastewater treatment plants with surface discharges may expand if they are located in an area where new wastewater treatment plants with surface discharges are allowed by these rules and regulations. The plans submitted to expand the wastewater treatment plant shall meet all of the requirements of this section.

(13) Existing wastewater treatment plants with subsurface discharges may expand. The expanded portion of such wastewater treatment plants shall meet all of the design standards and other requirements of this section.

(14) Any approval of a new or expanded wastewater treatment plant issued by the Department shall expire and thereafter be null and void unless construction is completed within five (5) years of the date of issuance of such approval or any extended period of time approved by the Department upon good cause shown. Following expiration of the approval, the plans for the wastewater treatment plants may be resubmitted to the Department for consideration for a new approval.

(b) Requirements for wastewater treatment plants located within phosphorus restricted basins. No new wastewater treatment plants with surface discharges, or expansions of existing wastewater treatment plants with surface discharges, shall be allowed in a phosphorus restricted basin. A variance from this provision may be sought in accordance with the requirements set forth in 15 RCNY § 18-61(d).

(c) Requirements for wastewater treatment plants located in coliform restricted basins. No new wastewater treatment plants with surface discharges, or expansions of existing wastewater treatment plants with surface discharges, shall be allowed in a coliform restricted basin. A variance from this provision may be sought in accordance with the requirements set forth in 15 RCNY § 18-61(d)(1).

(d) Treatment requirements for wastewater treatment plants located within the 60 day travel time to intake.

(1) The map indicating the demarcation line for the watershed areas that are located within the 60 day travel time to intake appears in Appendix 18-A. Large detailed maps of such areas are available to be reviewed by the public during business hours at the regional offices listed in 15 RCNY § 18-15.

(2) Within the 60 day travel time to the intake the following requirements are applicable:

(i) New wastewater treatment plants with surface discharges, or expansions of existing wastewater treatment plants with surface discharges, are prohibited except as provided in 15 RCNY § 18-82(e). A variance from this provision may be sought in accordance with the requirements set forth in 15 RCNY § 18-61(e);

(ii) Existing wastewater treatment plants with SPDES permitted surface discharges may continue to operate provided the wastewater treatment plant provides sand filtration or a Department-approved alternative technology to sand filtration, disinfection, phosphorus removal, and microfiltration or a Department-approved equivalent technology to microfiltration, as required by these rules and regulations;

(iii) Wastewater treatment plants with subsurface discharges may commence or continue to operate provided that the wastewater treatment plant provides sand filtration or a Department-approved alternative technology to sand filtration and phosphorus removal, and for SPDES permitted discharges greater than 30,000 gallons per day (gpd), disinfection, as required by these rules and regulations.

(e) Treatment requirements for wastewater treatment plants located in the watershed and beyond the 60 day travel time to intake.

(1) The map indicating the demarcation line for the watershed areas that are located beyond the 60 day travel time to intake appears in Appendix 18-A. Large detailed maps of such areas are available to be reviewed by the public during business hours at the regional offices listed in 15 RCNY § 18-15.

(2) Beyond the 60 day travel time to the intake the following requirements are applicable:

(i) New wastewater treatment plants with surface discharges into a reservoir, reservoir stem, controlled lake, or wetland are prohibited;

(ii) All new surface discharges into a watercourse, and any existing wastewater treatment plants with SPDES permitted surface discharges may commence or continue to operate, provided that the wastewater treatment plant provides sand filtration or a Department-approved alternative technology to sand filtration, disinfection, phosphorus removal, and microfiltration or a Department-approved equivalent technology to microfiltration, as required by these rules and regulations;

(iii) Wastewater treatment plants with subsurface discharges may commence or continue to operate, provided that the wastewater treatment plant provides sand filtration or a Department-approved alternative technology to sand filtration and phosphorus removal, and for SPDES permitted discharges greater than 30,000 gallons per day (gpd), disinfection, as required by these rules and regulations.

(f) Design, operation and maintenance requirements.

(1) This subdivision (f) shall apply to wastewater treatment plants.

(2) The criteria used by the Department to approve the design for any new wastewater treatment plant or the portion of any wastewater treatment plant which is being expanded or altered or modified shall be all applicable requirements of law, including the standards set forth in the following documents:

(i) "New York State Design Standards for Intermediate Sized Wastewater Treatment Systems" New York State Department of Environmental Conservation (2014); and

(ii) "Recommended Standards for Wastewater Facilities," Great Lakes – Upper Mississippi River Board of State and Provincial Public Health and Environmental Managers (2014).

(3) The Department shall not approve a wastewater treatment plant, or any proposed expansion of a wastewater treatment plant, which discharges within the watershed, if there is inflow or infiltration into a sewer system connected to such wastewater treatment plant which causes either:

(i) The State authorized flow limit of the wastewater treatment plant to be exceeded; or

(ii) The strength of the sewage influent to the wastewater treatment plant to be diluted to a level that adversely affects the efficacy of the State permitted and Department approved treatment process.

(4) The Department shall not approve a wastewater treatment plant, or any proposed expansion of a wastewater treatment plant, if there is an indication of exfiltration from a sewer system connected to such wastewater treatment plant.

(5) All wastewater treatment plants shall meet the following requirements to insure uninterrupted reliable operation:

(i) All wastewater treatment plants shall provide standby power units sufficient to run the entire plant in order to ensure uninterrupted reliable operation in the event of utility power failure and these units shall be equipped with an alarm and automatic start-up capability.

(ii) All vital plant structures, mechanical and electrical equipment of wastewater treatment plants located or designed within the 100-year flood plain shall be protected from damage from a 100-year flood that may affect or disrupt its function or general performance. Such structures and equipment shall remain fully operational in a 25-year flood.

(iii) The disinfection system shall be provided with backup units, an alarm and equipment that will insure processing of the plant flow without interruption and the backup electrical and/or mechanical equipment shall be equipped with automatic start-up capability.

(iv) Sand filtration or a Department-approved alternative technology to sand filtration shall be implemented in units of sufficient number and size to ensure that the flow they are designed to accommodate, consistent with the "New York State Design Standards for Intermediate Sized Wastewater Treatment Systems," New York State Department of Environmental Conservation (2014) and/or the "Recommended Standards for Wastewater Facilities," Great Lakes-Upper Mississippi River Board of State and Provincial Public Health and Environmental Managers (2014), can be processed in the event that the largest such unit is off line;

(v) All wastewater treatment plants must be equipped with a flow meter that includes a recording device; and

(vi) All alarm systems shall require telemetering to a central location with around the clock operator presence or, in the alternative, to an operator's residence so that a response shall be initiated immediately.

(6) The following requirements shall apply to all wastewater treatment plants with subsurface discharges or absorption areas located in the watershed:

(i) The loading rate to the absorption trench may be 25 percent greater than that required under the design standards listed in subdivision (f)(2) of this section;

(ii) An additional area of at least 50 percent of the absorption area shall be set aside as a reserve area;

(iii) At a minimum, one percolation and one deep hole test shall be performed in both the primary absorption area and in the reserve absorption area. An applicant shall notify the Department in writing at least 7 business days prior to performance of such tests, and specify the location and the time of the tests. At the option of the Department, a Department representative may witness these tests; and

(iv) The use of pumping, mechanical dosing or other mechanical devices requires a pump chamber equipped with an alarm to indicate malfunction, a backup pump, and any other safety features required by the Department to prevent overflow.

(7) (i) All owners or operators of Department approved wastewater treatment plants in the watershed shall, prior to commencement of construction of such wastewater treatment plants, deposit with the Department a performance bond for the completion of the construction of the wastewater treatment plant and an additional bond or other guaranty for the payment of labor and material furnished in the course of such construction. Upon completion of construction and payment of labor and materials, such bonds or other guaranties shall be released. Additionally, prior to commencement of operation of the approved wastewater treatment plant, the owners or operators of the approved wastewater treatment plant shall provide a surety bond, or a reasonable guaranty, that they shall continue to maintain and operate the system for a period of five years. The surety bond or guaranty shall be in an amount sufficient to insure the full and faithful performance by the owners or operators of the wastewater treatment plants, and their successors and assigns, with regard to their obligation to properly maintain and operate the wastewater treatment plants in accordance with all requirements of law and according to the conditions set by the Department in its approval; provided, however, that such surety bond or guaranty shall not be required by the Department where the owners or operators of the wastewater treatment plant have provided a surety bond or guaranty for the maintenance and operation of the wastewater treatment plant to the local governing body, in an amount necessary to insure the full and faithful performance of the operation and maintenance of the wastewater treatment plant; provided further, that such surety bond or guaranty shall not be required where the owner or operator of the wastewater treatment plant is a village, town, county or city. The Commissioner may, at his or her discretion, increase the amount of such surety bond or guaranty, but not to exceed an amount necessary to insure the full and faithful performance of the operation of the wastewater treatment plant. All such bonds shall be prepared on the forms of bonds authorized by the City of New York and shall have as a surety such company or companies that shall be approved by the City of New York and are authorized to do business in the State of New York.

(ii) The Commissioner may authorize the provision of other security, including cash, if the Commissioner finds that compliance with the bond requirement is not reasonably possible and the public interest would be served by such authorization. The alternative security shall be deposited with the Comptroller of the City of New York.

(iii) Whenever an owner or operator of a wastewater treatment plant deposits securities or other obligations with the City of New York, in lieu of a performance bond, it shall be with the understanding that the Comptroller of the City of New York, or his or her successors, may sell and use the proceeds thereof for any purpose for which the principal or surety on such bond would be liable under the terms of the approval. If money is deposited with the Comptroller, the owner or operator of the wastewater treatment plant shall not be entitled to receive interest on such money from the City of New York.

(8) The transfer of any approval or permit issued by the Department for the construction and/or operation of any wastewater treatment plant shall require Department approval. The Department shall approve such transfer provided that the transferee demonstrates sufficient financial, technical, and professional capability to construct, operate and/or maintain the subject wastewater treatment plant in compliance with applicable laws, as cited in 15 RCNY § 18-36(a)(1), the provisions of these rules and regulations, and the terms and conditions of any approval or permit granted by the Department.

(g) Application requirements.

(1) An application for review and approval of a new wastewater treatment plant shall include the following information:

(i) A Department application form and an Environmental Assessment Form (EAF Long Form);

(ii) A facility plan which shall include: a description of the project, flow and waste load estimations, site characteristics, evaluation of existing system, if applicable, and existing local or related facilities, including any related water quality problems, examination of the project service area, estimation of growth, examination of alternative solutions and explanation of why the proposed option was chosen, analysis of potential impacts, analysis of hydraulic and organic capacities (including Waste Assimilation Capacity analysis), description of unit processes and explanation of sizing, operation under emergency conditions, and sludge processing, storage and disposal methods, estimation of costs, proposed financing methods and anticipated user fees, outline of operation and maintenance requirements (including cost projections), and regulatory review and permitting requirements;

(iii) An engineering plan which shall include: location plan, site plan, schematic of plant hydraulic profile, piping schematic, location, dimension and elevations of plant process units and appurtenances, mechanical system layout, electrical system layout, and erosion and sediment control and stormwater management plan.

(iv) Construction specifications, including material and equipment specifications;

(v) Construction schedule;

(vi) In cases where a draft environmental impact statement ("DEIS") is to be prepared for an activity and the DEIS complies with the requirements of Article 8 of the Environmental Conservation Law and the regulations promulgated thereunder, and includes the information required in this part, the DEIS may constitute all or part of the application for review and approval under this part. In such case the applicant will provide the Department with notice and a copy of the DEIS; however, no approval shall be issued by the Department prior to review of the FEIS and issuance of a finding to approve; and

(vii) A copy of the draft SPDES permit, if any, and, when issued, a copy of the final SPDES permit. Copies of any revisions to the draft SPDES permit shall also be provided to the Department as they become available to the applicant.

(2) An application for review and approval of an expansion or of an alteration or modification of a wastewater treatment plant shall include all of the information required in subdivision (g)(1) of this section where applicable, and shall either:

(i) Certify that the wastewater treatment plant is in compliance with all of the requirements of this section, and all requirements of its SPDES permit; or

(ii) Certify that a schedule for the wastewater treatment plant to come into compliance with the requirements of this section and with the requirements of its SPDES permit has been submitted to the Department for approval. A copy of such compliance schedule shall be attached to the application.

(3) All approvals for new or expansion of existing wastewater treatment plants are conditioned on the applicant's submission of record drawings once construction is complete.

(Amended City Record 10/30/2019, eff. 11/29/2019)

§ 18-37. Sewer Systems, Sewer Connections and Discharges to Sewer Systems

Open this section

(a) Combined sewer systems are prohibited from discharging within the watershed.

(b) A new sewer connection or sewer extension to a sewer system is prohibited where the wastewater treatment plant to which the sewer system has been connected and which discharges within the watershed has had a SPDES flow parameter violation in the prior twelve months, or where the additional flow from the new sewer connection or sewer extension will cause or can be expected to cause such wastewater treatment plant to have a SPDES flow parameter violation as defined herein.

(c) Sewer Connections.

(1) The owner of any individual residence that will be served by a new sewer connection, or by an alteration or modification of a sewer connection, shall notify the Department 48 hours prior to the installation of such sewer connection or of such alteration or modification, and provide an opportunity to the Department to observe the work. If specifically requested by the Department, the owner shall submit to the Department all plans or designs for such sewer connection or for such alteration or modification.

(2) The owner of a structure other than an individual residence that will be served by a new sewer connection, or by an alteration or modification of a sewer connection, to a sewer system that is subject to a qualifying municipal sewer use law shall:

(i) provide to the Department, at least 48 hours prior to the installation of such sewer connection or of such alteration or modification, a written permit from the superintendent of the sewer system authorizing such connection; and

(ii) notify the Department 48 hours prior to the installation of such sewer connection or of such alteration or modification, and provide an opportunity to the Department to observe the work.

(3) The plans for a new sewer connection, or for an alteration or modification of a sewer connection, to a sewer system for a treatment facility with a SPDES permit, which is not subject to a qualifying municipal sewer use law, from a structure other than an individual residence, require review and approval of the Department. As a condition of approval, the Department will require the applicant to notify the Department 48 hours prior to the installation of such sewer connection or of such alteration or modification, and provide an opportunity to the Department to observe the work. An application for review and approval of such a new sewer connection or alteration or modification of a sewer connection must include:

(i) A written statement from the owner or operator of the treatment facility certifying that the new sewer connection or alteration or modification of a sewer connection will not require a modification of the treatment facility's SPDES permit, and

(ii) Plans and specifications for the sewer connection.

(4) New sewer connections, or alterations or modifications of sewer connections, to treatment facilities that do not have SPDES permits shall be reviewed in accordance with 15 RCNY § 18-37.

(d) The design, construction and plans for a new sewer system or sewer extension shall require the review and approval of the Department. Any proposed alteration or modification of a sewer system shall require the review and approval of the Department.

(e) Any approval of a new or an alteration or modification of an existing sewer system, sewer extension, or sewer connection subject to Department approval pursuant to 15 RCNY § 18-37(c)(3), issued by the Department expires and is null and void unless construction is completed within five (5) years of the date of issuance. Following expiration of the approval, the plans for the sewer system may be resubmitted to the Department for consideration for a new approval.

(f) The criteria used by the Department to approve any new sewer system, sewer extension, or sewer connection subject to Department approval pursuant to 15 RCNY § 18-37(c)(3) or the portion of any sewer system or such sewer connection which is being altered or modified, shall be all applicable requirements of law, including the standards set forth in the following documents:

(1) "New York State Design Standards for Intermediate Sized Wastewater Treatment Systems," New York State Department of Environmental Conservation (2014);

(2) "Recommended Standards for Wastewater Facilities," Great Lakes-Upper Mississippi River Board of State and Provincial Public Health and Environmental Managers (2014);

(3) 19 NYCRR Part 1222 (Plumbing Code of New York State).

(g) All sewer systems and sewer extensions connected to a wastewater treatment plant which discharges within the watershed shall be designed, operated and maintained in such manner as to prevent inflow or infiltration which causes one or more of the following:

(1) The SPDES authorized flow limit of the wastewater treatment plans to be exceeded;

(2) The strength of the sewage influent to the wastewater treatment plant to be diluted to a level that adversely affects the efficacy of the SPDES permitted and Department approved treatment process; or

(3) A bypass of any portion of a treatment facility that would be prohibited pursuant to 6 NYCRR Subpart 750-2.

(h) All sewer systems and sewer extensions shall be designed, operated and maintained to prevent exfiltration from such systems.

(i) The owner or operator of a facility which disposes of wastes regulated pursuant to the Federal Categorical Pretreatment Standards, 40 C.F.R. Part 403, shall submit three copies of the engineering report, plans and specifications, prepared by a licensed design professional, in compliance with 40 C.F.R. Parts 403, 406-471 and any applicable local regulations, to the Department for its review and approval.

(j) Application Requirements for Sewer Systems and Sewer Extensions. An application for review and approval of any sewer system or sewer extension shall include the following information:

(1) Tax map number and, where available, building permit number, for each property to be served by the proposed sewer system or sewer extension;

(2) Letter of flow acceptance from the owner of the receiving wastewater treatment plant, when available;

(3) An engineering report presenting the proposed flow and supporting design calculations; and

(4) Four (4) sets of plans showing:

(i) site location in relation to established sewer district;

(ii) distances to wells, watercourses, rock outcroppings, wetlands, controlled lakes and reservoirs;

(iii) system profile including all connections, manholes and required pump stations;

(iv) design details and specifications of system components including pipe sizes and pump capacities;

(v) where applicable, a copy of the application for modification of the SPDES permit for the receiving wastewater treatment plant and, if available, any draft revisions to such SPDES permit; and

(vi) construction phasing.

(5) An application for review and approval of a sewer system must include an operation and maintenance plan for the sewer system, which may be a component of the operation and maintenance plan for the treatment facility served by the sewer system; and

(6) An Environmental Assessment form and State Environmental Quality Review Act determination, if applicable.

(k) All approvals for sewer systems and extensions are conditioned on the applicant's submission of as-built drawings, prepared by a design professional, once construction is complete.

(l) As a condition of approval the Department may require evidence of financial security prior to construction, from any owner or operator of a new sewer system or sewer extension or a substantial alteration or modification to an existing sewer system. Such financial security shall consist of a bond, or an equivalent guaranty, to be deposited with the Department, covering the full cost of the construction of such facility and an additional bond or an equivalent guaranty for the payment of labor and material furnished in the course of such construction. Upon completion of construction and payment of labor and materials, such bonds or other guaranties shall be released. Additionally, a bond or equivalent guaranty may be required for the maintenance and operation of the facility for a period of five years post-construction. No bond or guaranty is required where the owner or operator of such a facility is a village, town, county or city.