15 RCNY G Common Sources of Delays for Reimbursements and Approvals

1. The NYC Licensed Plumber fails to return the completed sealed permit to the Borough Office from which it was issued or fails to include the meter number, final reading for the old meter, new meter make/models, or the set date of the new meter on the permit. Neither can the meter be set up on the water / wastewater account, nor can an inspection be scheduled until the sealed permit is properly returned. The permit must be returned within ten business days of completion of the work or the NYC Licensed Plumber will be issued a Notice of Violation.

2. The NYC Licensed Plumber fails to install wires from the meter register to the exterior of the building properly so that DEP can install the AMR device.

3. The NYC Licensed Plumber fails to drill holes in the flanges for seal wire (1 1/2” and larger).

4. Documents are mailed to a general DEP address, instead of a specific unit.

5. The NYC Licensed Plumber charges the customer sales tax. Meter installations are not subject to sales tax for the customer.

6. The reimbursement is requested for a meter that was illegally removed or for a meter that is being replaced only because the owner has increased the size of the water service. Neither of these replacements is eligible for the RMP, unless the water service is being replaced with a larger service and the original meter was not operating properly; if the original meter was not operating properly and the water service is replaced with a larger service, reimbursement for the original meter size can be issued.