NYC Administrative Code Title 28, Chapter 7 New York City Building Code, part 25 of 33

Section BC 3302 to Section BC 3305: 4 sections.

Section BC 3302. Definitions

Open this section

3302.1 Definitions.

The following terms are defined in Chapter 2:

100-HOUR TRAINING PROGRAM.

ACTIVELY PROCTORED ONLINE TRAINING.

ADJUSTMENT (SCAFFOLD).

ARTICULATING BOOM CRANE.

AXIS OF ROTATION.

AXLE.

BASE (MOUNTING).

BEARER (PUTLOG).

BOOM (CRANE OR DERRICK).

BOOM POINT.

BRAKE.

BUCKET HOIST.

CABLEWAY.

CEMENTED SOIL (CHAPTER 33).

CERTIFICATE OF APPROVAL.

CERTIFICATE OF OPERATION.

CERTIFICATE OF ON-SITE INSPECTION.

CLAMSHELL.

CLIMBER CRANE.

COHESIVE SOIL (CHAPTER 33).

COMMERCIAL TRUCK MOUNTED CRANE (BOOM TRUCK).

COMPETENT PERSON.

COMPLETED STEEL FLOOR (CHAPTER 33).

CONCRETE WASHOUT WATER.

CONSTRUCTION.

CORNER SCAFFOLD (ANGLE SCAFFOLD).

COUNTERWEIGHT.

CRANE.

CRAWLER CRANE.

CRITICAL PICK.

CURB LEVEL.

DEBRIS.

DEBRIS NET or NETTING.

DEDICATED PILE DRIVER.

DEMOLITION.

Full demolition.

Partial demolition.

DERRICK.

DEWATERING.

DIRECT AND CONTINUING SUPERVISION.

DIRECT EMPLOY.

DISMANTLING.

DRUM.

DRY (SOIL, CHAPTER 33).

EQUIPMENT.

ERECTION.

EXCAVATION.

FISSURED (SOIL, CHAPTER 33).

GRANULAR SOIL (CHAPTER 33).

GUARDRAIL SYSTEM (SCAFFOLD).

GUY.

HANDHELD DEVICE (DEMOLITION).

HEAVY DUTY SCAFFOLD.

HEAVY DUTY SIDEWALK SHED.

HISTORIC STRUCTURE.

HOISTING EQUIPMENT.

HOISTING MACHINE.

HOISTING MECHANISM.

INDUSTRIAL ROPE ACCESS.

INCIDENT.

INSTALLING/INSTALLATION/INSTALL (SCAFFOLD).

Initial installation (scaffold).

Reinstallation (scaffold).

JIB.

JUMP (JUMPING or CLIMBING).

LAYERED (SOIL, CHAPTER 33).

LIGHT DUTY SCAFFOLD.

LIGHT DUTY SIDEWALK SHED.

LIMITED SITE SAFETY TRAINING (SST) CARD.

LOAD BLOCK, LOWER.

LOAD BLOCK, UPPER.

LOAD RATINGS.

LOAD RATING CHART.

LOAD (WORKING).

MAINTENANCE (SCAFFOLD).

MAJOR BUILDING.

MANUFACTURE DATE (CRANE).

MAST CLIMBER.

MATERIAL HANDLING EQUIPMENT.

MATERIAL HOIST (MATERIAL HOISTING EQUIPMENT).

MECHANICAL DEMOLITION EQUIPMENT.

MEDIUM DUTY SCAFFOLD.

MOBILE CRANE.

MOBILE SCAFFOLD.

MOIST (SOIL, CHAPTER 33).

MULTIPOINT ADJUSTABLE SUSPENDED SCAFFOLD.

ORDINARY REPAIRS.

OSHA.

OSHA 10-HOUR CLASS.

OSHA 30-HOUR CLASS.

OUTRIGGER (CRANE).

OUTRIGGER (SCAFFOLD).

OUTRIGGER BEAM (THRUSTOUT).

OUTRIGGER SCAFFOLD.

PERSONNEL HOIST.

PILE DRIVER.

PLASTIC (SOIL, CHAPTER 33).

PLATFORM.

POWER BUGGIES.

QUALIFIED PERSON.

REMOVING/REMOVAL/REMOVE (SCAFFOLD).

REPAIR (SCAFFOLD).

REPLACEMENT (SCAFFOLD).

ROPE.

ROTATING TELEHANDLER.

RUNBACK STRUCTURE.

SAFETY NETTING SYSTEM (SAFETY NETTING).

Horizontal safety netting.

Vertical safety netting.

SCAFFOLD.

SCAFFOLD CONTROLLING ENTITY.

SELF-ERECTING TOWER CRANE.

SHORE, MULTI-STAGE.

SINGLE-POINT ADJUSTABLE SUSPENDED SCAFFOLD.

SITE SAFETY TRAINING (SST) CARD.

SITE SAFETY TRAINING (SST) CREDIT.

SITE SAFETY TRAINING (SST) FULL COMPLIANCE DATE.

SITE SAFETY TRAINING (SST) PROVIDER.

SITE SAFETY TRAINING (SST) SECOND COMPLIANCE DATE.

SITE SAFETY TRAINING (SST) SUPERVISOR CARD.

SITE SAFETY TRAINING (SST) TASK FORCE.

SOIL AND FOUNDATION WORK (SOIL OR FOUNDATION WORK).

STABLE (ROCK, CHAPTER 33).

STAIR TOWER (SCAFFOLD STAIRWAY/TOWER).

STANDARD GUARDRAIL SYSTEM (SCAFFOLD).

STAND-OFF BRACKET (SUSPENDED SCAFFOLD).

STRIPPING OPERATIONS.

STRUCTURAL NET (STRUCTURAL NETTING).

SUBMERGED SOIL (CHAPTER 33).

SUPERSTRUCTURE.

SUPPORTED SCAFFOLD.

SUSPENDED SCAFFOLD.

SUSPENDED SCAFFOLD FOREMAN.

SWING.

TELEHANDLER.

TEMPORARY CONSTRUCTION INSTALLATIONS.

TEMPORARY SITE SAFETY TRAINING (SST) CARD.

TOOL.

TOWER CRANE.

TRANSIT.

TRAVEL.

TRENCH.

TWO-POINT SUSPENDED SCAFFOLD (SWING STAGE).

TYPE A SOIL (CHAPTER 33).

TYPE B SOIL (CHAPTER 33).

TYPE C SOIL (CHAPTER 33).

UNCONFINED COMPRESSIVE STRENGTH (SOIL, CHAPTER 33).

UNENCLOSED PERIMETER.

USE/USING (SCAFFOLD).

WALKABLE FLOOR (CONCRETE CONSTRUCTION).

WALKABLE FLOOR (PRECAST CONCRETE CONSTRUCTION).

WALKABLE FLOOR (STEEL CONSTRUCTION).

WHEEL MOUNTED CRANE (MULTIPLE CONTROL STATIONS).

WHEEL MOUNTED CRANE (SINGLE CONTROL STATION).

WORKING DECK (CONCRETE CONSTRUCTION).

WORKING DECK (DEMOLITION).

WORKING DECK (PRECAST CONCRETE CONSTRUCTION).

WORKING DECK (STEEL CONSTRUCTION).

(Am. L.L. 2017/196, 10/16/2017, eff. 10/16/2017; Am. L.L. 2018/003, 12/31/2017, eff. 1/1/2019; Am. L.L. 2019/119, 6/8/2019, eff. 6/8/2019; Am. L.L. 2019/219, 12/15/2019, retro. eff. 10/16/2017; Am. L.L. 2020/010, 12/27/2019, retro. eff. 12/15/2019; Am. L.L. 2020/096, 9/27/2020, retro. eff. 9/1/2020; Am. L.L. 2021/146, 12/11/2021, eff. 12/11/2021; Am. L.L. 2023/077, 6/11/2023, eff. 6/11/2023)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2023/077.

Section BC 3303. Safeguards and Maintenance of Site

Open this section

3303.1 Scope.

Sites shall be safeguarded and maintained in accordance with the provisions of this section to protect the public and property.

3303.2 Utilities.

Utilities at a site shall meet the requirements of Sections 3303.2.1 through 3303.2.6.

3303.2.1 Existing services.

The location of all existing utilities and service lines shall be determined and adequate measures taken, or devices provided, to safeguard the public and property before such utilities are disturbed.

3303.2.2 Maintaining essential services.

See Section 3303.9.

3303.2.3 Electrical work.

All temporary electrical equipment and wiring shall meet the requirements of the New York City Electrical Code, and shall be maintained in compliance with such requirements. Portions of permanent electrical installations may be used for temporary operations provided the requirements of the New York City Electrical Code are met.

3303.2.3.1 Temporary lighting for construction sites.

Temporary lighting for construction sites shall use high-efficacy lamps with the following minimum efficacies:

1. 60 lumens per watt for lamps over 40 watts;

2. 50 lumens per watt for lamps over 15 watts but less than or equal to 40 watts; and

3. 40 lumens per watt for lamps 15 watts or less.

3303.2.4 Sanitary facilities.

Sanitary facilities shall be provided during construction or demolition activities in accordance with the New York City Plumbing Code.

3303.2.5 Removing, relocating, or interrupting services.

If any utility is to be removed, relocated, or have its service interrupted, the utility company or city agency affected shall be notified at least 72 hours in advance.

3303.2.6 Disconnecting, capping, and certifications.

Prior to the removal of any service, the utility connection shall be discontinued and capped, and certifications to that effect issued by the representative utility company shall be filed with the department.

3303.3 Watchperson.

Where an individual building being constructed or demolished has a footprint of between 5,000 square feet (1524 m 2 ) and 40,000 square feet (12 192 m 2 ), a competent watchperson shall be on duty at the site during all hours when operations are not in progress, from the time when the foundation is poured to when all work has concluded and the certificate of occupancy or temporary certificate of occupancy has been issued. Where the building has a footprint of more than 40,000 square feet (12 192 m 2 ), at least one additional watchperson shall be on duty for each additional 40,000 square feet (12 192 m 2 ) of building footprint, or fraction thereof. The watchperson shall be familiar with emergency notification procedures to the Fire Department, shall possess a valid security guard registration with the State of New York, shall hold a valid watchperson certificate from the Fire Department, and shall have completed a course that is at least 10-hours in length and approved by OSHA in construction industry safety and health.

Exceptions:

1. Where the square footage of the building footprint requires two or more watchpersons, the number of watchpersons may be reduced, subject to the approval of the commissioner, where:

1.1 A video monitoring system is in place, or where the layout of the building allows a continuous line of sight across the entire building; and

1.2 At least one watchperson is provided.

2. The building is being actively monitored in accordance with a fire safety and evacuation plan approved by the Fire Department in accordance with the New York City Fire Code.

3303.4 Housekeeping.

Housekeeping at a site shall be in accordance with Sections 3303.4.1 through 3303.4.11.

3303.4.1 Slipping and tripping hazards.

Slipping and tripping hazards in areas used by the public shall be minimized in accordance with Sections 3303.4.1.1 and 3303.4.1.2.

3303.4.1.1 Maintenance of public areas.

All areas used by the public shall be maintained free from ice, snow, grease, debris, equipment, materials, projections, tools, or other items, substances, or conditions that may constitute a slipping, tripping, or other hazard.

3303.4.1.2 Location of hose lines, wires, ropes, pipes, chains, and conduits.

Hose lines, wires, ropes, pipes, chains, and conduits shall be located so that they will not constitute a tripping hazard to the public. Where it is necessary to carry such across sidewalks, or any public way, they shall either be suspended at least 8 feet (2438 mm) above ground or, if left on the ground, suitable chamfered planks or a pedestrian bridge shall be provided to cover such.

3303.4.2 Containers.

Sufficient containers, including but not limited to waste dumpsters, debris boxes, and skip boxes, shall be available for the storage of all debris or waste. Such containers shall comply with the following requirements:

1. Containers shall be made of metal, flame-retardant plastic, or other noncombustible material.

2. Containers with wheels shall be secured at the end of the workday by rope, cable, or chocking at the wheels in order to prevent movement.

3. Containers shall not be placed at the edge of an unenclosed perimeter at any time, except when being moved from the floor or building.

4. Containers holding debris or waste shall be covered at the end of the workday and at any time when full to near the rim. However, containers need not be covered when they are empty and not in use, or while stored in a fully enclosed space at the end of the workday and not full to near the rim.

Exception: Combustible debris shall not be permitted to accumulate and shall be removed from the site in accordance with Section 3303.5.1.

3303.4.3 Reserved.

3303.4.4 Control of debris.

Control of debris during construction and demolition work shall include the measures specified in Sections 3303.4.4.1 through 3303.4.4.3.

3303.4.4.1 Daily cleaning.

All areas of the construction or demolition site shall be cleaned of debris at least daily.

3303.4.4.2 Cleaning near unenclosed perimeters.

Areas that are at least 10 feet (3048 mm) from an unenclosed perimeter, as measured in all directions from the unenclosed perimeter, shall be cleaned of debris periodically throughout the day.

Exception: In locations where unenclosed perimeter protection has been temporarily removed, the requirements of Section 3308.10 shall apply.

3303.4.4.3 Securing debris that cannot be removed by the end of the shift.

Debris that cannot be removed from the site by the end of the shift shall be:

1. Placed in containers meeting the requirements of Section 3303.4.2; or

2. Secured overnight to protect the public and property and shall be removed from the site or placed in containers meeting the requirements of Section 3303.4.2 at the beginning of the next shift. For demolition operations, debris stored overnight on grade or earth, and neatly piled to prevent dislodgement, tipping, or spillage, shall be considered to be in compliance with this section.

Exception: Combustible debris shall not be permitted to accumulate and shall be removed from the site in accordance with Section 3303.5.1.

3303.4.5 Storage and safeguarding of materials and equipment during construction or demolition.

Material and equipment located at a site during construction or demolition operations shall comply with Sections 3303.4.5.1 and 3303.4.5.2.

3303.4.5.1 Open and exposed areas.

Material or equipment located on a working deck, unenclosed floor, roof, ground area, or similar exposed area shall be secured or otherwise safeguarded to prevent dislodgement by wind, vibration, accidental impact, or other means.

3303.4.5.2 Storage near unenclosed perimeters.

When not being used, material or equipment shall be stored at least 10 feet (3048 mm) from all unenclosed perimeters, as measured in all directions from the unenclosed perimeter. Material or equipment shall also be secured or safeguarded in accordance with the requirements of Section 3303.4.5.1.

Exceptions: Provided the material or equipment is secured against dislodgement by wind, vibration, accidental impact, or other means, in lieu of the 10-foot (3048 mm) set back distance:

1. Material or equipment that weighs 750 pounds (340.2 kg) or more may be stored at least 5 feet (1524 mm) from the unenclosed perimeter.

2. Where the gross floor area is less than 1,000 square feet (93 m 2 ), material or equipment, regardless of weight, may be stored at least 5 feet (1524 mm) from the unenclosed perimeter.

3. Where located on a floor that is at or above the level of the horizontal safety netting in accordance with Section 3308, material or equipment may be stored at least 2 feet (610 mm) from the unenclosed perimeter.

4. Material related to concrete operations may overhang the unenclosed perimeter of the building or structure, provided:

4.1. The material is banded with a minimum of two equally spaced bands to prevent dislodgement;

4.2. The material is braced and secured in place by positive means as indicated on the site safety plan, or where there is no site safety plan, in accordance with drawings prepared by a registered design professional;

4.3. The material overhangs by no more than one-third of its length;

4.4. The material is stored in an area designated on the site safety plan, or where there is no site safety plan, in an area designated on drawings prepared by a registered design professional;

4.5. Such designated area is broom swept and cleared of all materials, equipment, and debris prior to the temporary removal of the vertical netting and placement of overhanging material in the designated area;

4.6. The perimeter of such designated area, except for the perimeter along the unenclosed perimeter, is protected by vertical netting meeting the requirements of Section 3308.5 or an alternative system acceptable to the commissioner;

4.7. Horizontal safety netting meeting the requirements of Section 3308.6 is provided at a level not more than two stories or 30 feet (9144 mm) below the overhanging material, whichever is less, with such nets in place for the full time the material is overhanging, except that the nets may be pulled in at the immediate time the material is being hoisted or lowered where such nets would conflict with the hosting or lowering operation; and

4.8. The material is relocated on the next workday.

3303.4.6 Storage of combustible material and equipment.

Storage of combustible material and other material and equipment that may present a fire hazard, shall comply with the New York City Fire Code.

3303.4.7 Storage near sidewalks, walkways, and pathways.

Material stored adjacent to a sidewalk, walkway, or pathway that remains open to the public shall not be piled higher than 3 feet (914 mm), or where a solid fence or barrier is provided, to within one foot (305 mm) of the top of such fence or barrier. For the purposes of this section, the term "adjacent to" shall be any area that is within a horizontal distance that is equal to or less than the vertical height of the piled material.

Exception: Material stored within a dumpster or similar solid container, provided such material is not piled above the top of such dumpster or container.

3303.4.8 Machinery.

All exposed, electrically charged, moving or otherwise dangerous parts of machines and construction or demolition equipment shall be located, guarded, shielded, or barricaded so as to prevent contact by the public.

3303.4.9 Internal combustion-powered equipment.

In addition to the requirements of this chapter, the use of internal combustion-powered equipment shall comply with the New York City Fire Code.

3303.4.10 Stairs, hallways, and other means of egress.

Stairs, hallways, pathways, and other means of egress, including but not limited to ladders used to facilitate access to a working level, shall not be encumbered by debris, material, or equipment.

3303.4.11 Daily inspection of housekeeping.

A daily inspection shall be made by a competent person to verify compliance with the housekeeping requirements of Sections 3303.4.1 through 3303.4.10. If the building is a major building, the occurrence of this inspection shall be noted in the site safety log. If the building is not a major building but requires a construction superintendent, the occurrence of this inspection shall be noted in the construction superintendent's log.

3303.5 Removal of material and debris.

Material and debris shall be removed in a manner that prevents injury or damage to the public or property.

3303.5.1 Removal of combustible debris.

Combustible debris shall not be permitted to accumulate, and shall be removed from the site at reasonable intervals in accordance with the requirements of the New York City Fire Code.

3303.5.2 Dropping or throwing prohibited.

No material, debris, or equipment shall be intentionally dropped or thrown from a building or structure.

3303.5.3 Clogging.

Precautions shall be taken to prevent concrete or mortar washings, sand, grit, or any other material that would cause clogging from entering a sewer, drain, vault, or subsurface structure. Concrete washout water shall also meet the requirements of Section 3303.15.

3303.5.4 Air pollution.

The provisions of the Air Pollution Control Code shall apply in order to prevent dust from becoming airborne.

(Am. L.L. 2015/038, 5/6/2015, eff. 5/6/2016)

3303.5.5 Chutes.

Chutes used in association with the removal of materials shall comply with Sections 3303.5.5.1 through 3303.5.5.5.

3303.5.5.1 Enclosures.

Chute enclosures shall comply with the following requirements:

1. Material chutes that are at an angle of more than 45 degrees (0.79 rad) with the horizontal shall be entirely enclosed on all sides, except for openings at the floor levels for the receiving of materials. Such openings shall not exceed 48 inches (1219 mm) in height, measured along the wall of the chute, and all openings, except the top opening, shall be closed and secured when not in use.

2. Chutes at an angle of less than 45 degrees (0.79 rad) with the horizontal may be open on the upper side.

3303.5.5.2 Chute construction.

Chute construction shall comply with the following requirements:

1. Every chute used to convey debris from a building or structure shall be rigidly supported and braced throughout its height.

2. Non-manufactured chutes less than 24 inches (610 mm) in maximum dimension shall be constructed of not less than 1-inch (25.4 mm) (nominal) wood, or 1/8-inch thick (3.18 mm) steel, or a material of equivalent strength and durability acceptable to the commissioner. Chutes more than 24 inches (610 mm) in maximum dimensions shall be constructed of not less than 2-inch (51 mm) (nominal) wood, or 3/16-inch thick (4.76 mm) steel, or a material of equivalent strength and durability acceptable to the commissioner.

3. Chutes shall be provided with a metal impact plate where material is forced to change direction while falling.

4. A gate shall be provided at the lower end of every chute to control the loading of material into trucks and to close the chute at all other times. Splash-boards or baffles shall be erected to prevent materials from rebounding into the street or under the sidewalk shed.

5. A bumper or curb at least 4 inches by 4 inches (102 by 102 mm) in section shall be provided at each chute opening where such opening is level with, or below, the floor or platform. Every space between the chute and the edge of the opening in the floor or platform shall be solidly planked.

6. Chutes that are over 75 feet (22 860 mm) in height, or utilized in Group I occupancy, shall also comply with the requirements of Section 3303.5.5.3.

3303.5.5.3 Chute construction where the chute is over 75 feet in height, or utilized in Group I occupancy.

Chutes that exceed 75 feet (22 860 mm) in height, or that are used in an occupied building where the main use or dominant occupancy is in Group I, shall either:

1. Be constructed of noncombustible material; or

2. Where constructed of combustible material, the combustible material of the chute shall be covered on the exterior of the chute with corrugated steel sheeting having a minimum thickness of 24 gauge through the entire height of the chute.

3303.5.5.4 Supports.

All structural supports of material chutes shall be of noncombustible material.

3303.5.5.5 Design and permit.

No chute shall be installed until a permit has been issued by the commissioner on the basis of drawings prepared by a registered design professional.

Exception: Design and permit is not required for a chute that meets all of the following criteria:

1. The chute is installed on the exterior of a building or structure at a height of 40 feet (12 192 mm) or less above the level of the adjoining ground;

2. The chute is a manufactured product and is installed in accordance with the manufacturer's specifications; and

3. The chute does not attach to or impart a load on a scaffold.

3303.6 Escape hatches.

Where portable fuel fired heaters or other heating equipment are used to provide temporary heating during the placing of concrete for a floor, an escape hatch shall be provided. The escape hatch shall be located as near to the center of the building or structure as practical.

Exceptions:

1. An escape hatch is not required where either the concrete placement floor or heating floor is the ground floor.

2. An escape hatch is not required provided at least one permanent stairway is available for use on the floor where the concrete is being placed and the stair shaft is enclosed from the top of the floor where concrete is being placed to at least the top of the heating floor with either its permanent construction, a temporary smoke proof 1-hour fire rated assembly, or a 1-hour fireproof tarp wrapped tightly around the stair shaft so that no smoke can penetrate.

3303.6.1 Required ladders and shields.

The escape hatch shall be constructed with at least two fixed, vertical ladders enclosed in a solid non-combustible shield. The ladders shall extend from a distance of 3 feet (914 mm) above the floor where the concrete is being placed to at least the story below the heating floor, or to the ground floor, whichever is less. The solid non-combustible shield shall enclose the ladders on all sides from the top of the floor where the concrete is being placed to at least the top of the heating floor. The inside dimensions between faces of the shield shall be not less than 3 feet 8 inches (1118 mm).

Exception: Extension ladders may be utilized where the horizontal dimension between the faces of the shields is equal to or greater than one-quarter the height of the shaft.

3303.6.2 Shield space and decking.

Any gap between the shield and the perimeter of the opening in the floor under construction and also between the shield and the perimeter of the opening in the heating floor shall be decked over with 2-inch (51 mm) or heavier planking covered with plywood or sheet metal so as to make the decking smoke tight. At the termination of the ladders, the opening in the floor shall be covered completely with 2-inch (51 mm) planking or other material of equivalent strength.

3303.7 Fire prevention and fire protection.

Firefighting equipment, firefighting access at the construction or demolition site, and the conduct of all construction or demolition operations affecting fire prevention and firefighting shall comply with the New York City Fire Code and the provisions of Sections 3303.7.1 through 3303.7.7.

3303.7.1 Water supply.

A water supply for fire protection shall be provided in accordance with the New York City Fire Code.

3303.7.1.1 Large footprint construction.

For a building that has a footprint of 100,000 square feet (30 480 m 2 ) or more, regardless of the height of the building, and the building is substantially enclosed, permanent or temporary fire hydrants available for fire department use shall be provided during the course of construction:

1. Within 50 feet (15 240 mm) of the main entrance; and

2. Along the perimeter of the building, with the hydrants located so that there is at least one hydrant along every 250 feet (76 200 mm) of building perimeter, and with no hydrant more than 50 feet (15 240 mm) from the exterior wall.

3303.7.2 Fire extinguishers.

Fire extinguishers shall be provided in accordance with the New York City Fire Code.

3303.7.3 Smoking.

Smoking shall be prohibited at all construction and demolition sites. No smoking signs shall be posted at the site in accordance with the provisions of the New York City Fire Code.

3303.7.4 Sprinkler systems.

Existing sprinkler systems in buildings undergoing an alteration or demolition shall comply with the requirements of Sections 3303.7.4.1 through 3303.7.4.3.

3303.7.4.1 Sprinklers during alteration.

Existing sprinkler systems in buildings undergoing an alteration shall be maintained in accordance with Section 3303.9, except as provided in Section 3303.7.4.3. The red paint required pursuant to Section 903.6 shall be maintained during any alteration operation.

3303.7.4.2 Sprinklers during demolition.

When existing sprinkler systems with fire department hose connections are present in buildings undergoing full or partial demolition, such systems shall be maintained as a nonautomatic sprinkler system, except as provided in Section 3303.7.4.3. When demolition starts, the sprinkler risers shall be capped immediately below the floor being demolished so as to maintain the sprinkler system on all lower floors for Fire Department use. Cutting and capping of sprinklers during demolition work shall be performed only by a licensed master plumber or licensed master fire suppression piping contractor who has obtained a permit for such work. Fire department hose connections shall be kept free from obstruction and shall be marked by a metal sign reading "Sprinkler Connection" and by a red light at night. The red paint required pursuant to Section 903.6 shall be maintained during any demolition operations.

3303.7.4.3 Removal of damaged sprinklers.

Requests for a variance from the sprinkler requirements of this section shall be limited to requests to remove a damaged or inoperable sprinkler system or a portion of such system in connection with demolitions or gut rehabilitations. Applications for construction document approvals for such requests shall be filed with the department by a registered design professional in accordance with the following procedure:

1. The filed application shall include a complete report prepared by the professional describing the extent of the damage and attesting as to why the system cannot be restored; and

2. The variance shall not be approved by the department without the concurrence of the Fire Department as follows:

2.1. The applicant shall file the request for variance with the Fire Department;

2.2. The Fire Department shall review and recommend any necessary safety measures required as a condition of granting the variance; and

2.3. The applicant shall submit the Fire Department's recommendation to the department along with proof of satisfactory implementation of such safety measures.

3303.7.5 Standpipe systems.

Standpipe systems shall meet the requirements of Section 3303.8.

3303.7.6 Floor numbering and floor elevation.

During new building construction, a vertical or horizontal enlargement, or a demolition operation that results in the removal of one or more floors in a building that is greater than 420 feet (128 m) in height above grade, or in any building, regardless of height, with non-sequential floor numbers, the following shall be provided:

1. A sign at each hoistway landing prominently displaying the designated floor number and elevation above grade.

2. A sign at each stair landing prominently displaying the designated floor number and elevation above grade.

3. A sign or other acceptable marking immediately adjacent to the standpipe hose outlet on each floor indicating the elevation above grade of the standpipe hose outlet and, in multi-zone standpipe buildings, the zone of the riser (low, mid, high).

4. A chart of the entire building listing the designated floor number and the elevation above grade of the standpipe hose outlet on each floor. The chart shall be posted in each construction elevator or hoist, and at such ground floor locations as specified in the New York City Fire Code.

3303.7.7 Special provisions for Type IV construction.

In addition to the fire prevention and fire protection requirements imposed by this code, the New York City Fire Code, and other applicable law, the following provisions shall also apply during new building construction of structures categorized as Type IV construction by Chapter 6 of this code.

(Am. L.L. 2023/077, 6/11/2023, eff. 6/11/2023)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2023/077.

3303.7.7.1 Interior exit stair enclosures.

Notwithstanding the requirements of Section 3303.11, no wooden structural components shall be installed until the permanent stairs and interior exit stair enclosures have been constructed to a height of at least two floors above the topmost working deck, or to their full height, and enclosed with their permanent fire protected rated material. A temporary or permanent self-closing door that meets the requirements of Section 715 shall be installed at each level as soon as a walkable surface is in place at that floor level. Openings in the interior exit stair enclosures at levels where a walkable surface has not been placed shall be protected with guardrails that meet the requirements of Section 3308.7. The top of the interior exit stair enclosure, if not permanently enclosed, shall be covered with a tarp or other temporary weather protection. The stair shall be provided with temporary or permanent handrails. Permanent signs, markings, or anti-slip materials in the stairs are not required during construction.

3303.7.7.2 Standpipes.

A permanent or temporary standpipe system meeting the requirements of Sections 905 and 3303.8 shall be provided in each interior exit stair enclosure and kept in a state of readiness at all times for use by firefighting personnel, even if the site does not otherwise trigger the standpipe requirements of Section 3303.8, Item 1. The standpipe system shall be in place prior to the installation of wooden structural components and shall serve all levels where the interior exit stair enclosure has been constructed. No standpipe shall be considered to be in a state of readiness unless it is painted red in accordance with the provisions of Section 905.11. The standpipe system shall be maintained as a dry system and provided with an air pressurized alarm system in accordance with Section 3303.8.1. Where the building will not be provided with a permanent standpipe at the end of construction, the temporary standpipe system shall be removed once the sprinkler system for the building has been signed off.

3303.7.7.3 Progressive installation of enclosures and fire protection elements.

Fire-rated enclosures (e.g. corridors, fire compartmentalization, fire-rated doors), noncombustible exterior walls, heat detectors required by Section 3303.7.7.5, and sprinkler systems, if required for the building, shall be installed as soon as practical, and in no case shall they lag more than two floors below the topmost walkable surface. Sprinkler systems shall be temporary or permanent and shall be maintained as a dry system during construction. Openings in the facade for hoists or material loading platforms are permitted provided the opening is covered at the end of the shift with a flame resistant tarp made tight so that no smoke can penetrate.

3303.7.7.4 Temporary protection of structural connections.

Where a structural connection between a girder and column is not provided with its permanent fire-rated enclosure or protection, it shall be protected by a temporary 1-hour rated enclosure or protection. Such temporary enclosure or protection shall be installed as soon as practical after the connection has been made, and no later than by the end of the shift.

3303.7.7.5 Heat detectors.

Heat detectors shall be provided throughout the site. Such detectors shall send alerts to a dedicated monitoring location, either at the site or at a remote location that is monitored continuously, including days, nights, weekends, and holidays. The monitor shall be familiar with emergency contact procedures, the locations of heat detectors at the site, and shall be able to alert the New York City Fire Department as necessary and provide the fire department with the location of any heat detector that has been activated.

3303.7.7.6 Watchperson.

A watchperson meeting the requirements of Section 3303.3 shall be on duty during all times specified by Section 3303.3, even if the building has a footprint of less than 5,000 sq ft (1524 m 2 ).

3303.7.7.7 Site safety orientation and refresher.

The site safety orientation and refresher required by Section 3301.11 shall contain instruction on site specific fire hazards, fire safety safeguards, and fire safety procedures.

3303.7.7.8 Pre-shift safety meetings.

The pre-shift safety meetings required by Section 3301.12 shall contain instruction on fire hazards, fire safety safeguards, and fire safety procedures applicable to the individual worker.

3303.7.7.9 Chutes.

Chutes shall comply with the requirements of Section 3303.5.5.3 even if the building does not otherwise meet the trigger thresholds of Section 3303.5.5.3.

3303.7.7.10 Doors.

Except when required to facilitate the active passage of personnel, material, debris, or equipment, fire rated doors shall be kept closed at all times, and all other doors shall be closed during non-working hours.

3303.7.7.11 Control of saw dust and combustible debris.

Sawdust shall be vacuumed as operations proceed. Combustible debris, including but not limited to sawdust and scrap lumber, shall be removed from the site as required by Section 3303.5.1.

3303.7.7.12 Storage of lumber.

During non-working hours, lumber shall be stored on the ground or street, or shall be stored in a fully enclosed room meeting its permanent fire rating. No more than 1,920 cubic feet (54.37 m 3 ) of lumber shall be stored at the site at any one time.

Exception: Columns may be stored on the topmost working deck provided they are to be installed at the start of the next shift.

(Am. L.L. 2023/077, 6/11/2023, eff. 6/11/2023)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2023/077.

3303.8 Standpipe systems during construction, alteration or demolition.

During construction, alteration or demolition operations, standpipe systems shall comply with the following:

1. When, during the course of the construction of a new building, the topmost working deck reaches a height of 75 feet (22 860 mm) or greater above the ground in a building for which a standpipe system will be required, a permanent or temporary standpipe system meeting the requirements of Section 905 shall be kept in a state of readiness at all times for use by fire-fighting personnel. The standpipe system shall serve all floors that are at least 4 stories or 40 feet (12 192 mm) below the topmost working deck, whichever is less. No standpipe shall be considered to be in a state of readiness unless it is painted red in accordance with the provisions of Section 905.11. When freezing conditions may be encountered, the system in whole, or the part of the system subject to freezing conditions, shall be maintained as a dry system.

2. Existing standpipe systems in structures undergoing a full demolition shall be maintained as dry standpipes. At the commencement of demolition, the standpipe risers shall be capped above the outlet on the floor immediately below the floor being demolished so as to maintain the standpipe system on all lower floors for Fire Department use. Cutting and capping of standpipes during demolition work shall be performed only by a licensed master plumber or licensed master fire suppression piping contractor who has obtained a permit for such work. Standpipe hose, nozzles and spanners are not required to be maintained and may be removed at any time. The red paint required pursuant to Section 905.11 shall be maintained during any demolition operations. All existing house check valves shall remain in place until completion of the demolition work.

3. When, during the course of the construction of a new building which will have an occupiable space at a depth of 75 feet (22 860 mm) or greater below the level of the ground in a building for which a standpipe system will be required, a permanent or temporary standpipe system meeting the requirements of Section 905 shall be installed and shall be kept in a state of readiness at all times for use by firefighting personnel. The standpipe system shall serve all stories below grade and shall be installed as soon as the foundation is in place and the first elevated slab has been erected. No standpipe shall be considered to be in a state of readiness unless it is painted red in accordance with the provisions of Section 905.11. When freezing conditions may be encountered, the system in whole, or the part of the system subject to freezing conditions, shall be maintained as a dry system.

4. When, during the course of alteration or partial demolition operations in a building for which a standpipe system is required, the standpipe system shall be maintained in accordance with Section 3303.9. In an unoccupied building, an existing wet standpipe system may be maintained as a dry system subject to the approval of the commissioner and the commissioner of the fire department, and also provided the standpipe system is equipped with an air pressurized alarm system meeting the requirements of Section 3303.8.1. No standpipe shall be considered to be in a state of readiness unless it is painted red in accordance with the provisions of Section 905.11.

4.1. If the alteration work results in the addition of new stories to the structure at a height of 75 feet (22 860 mm) or greater above the level of the ground, the requirements of Item 1 of this section shall apply to such new stories during the course of the alteration operation.

4.2. If the alteration work results in the addition of new occupiable space at a depth of 75 feet (22 860 mm) or greater below the level of the ground, the requirements of Item 3 of this section shall apply to such new occupiable space below grade during the course of the alteration operation.

(Am. L.L. 2023/077, 6/11/2023, eff. 6/11/2023)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2023/077.

3303.8.1 Air pressurized alarm system for dry standpipe systems during construction or demolition operations.

Dry standpipe systems utilized during construction or demolition operations shall be provided with an air pressurized alarm system as set forth in Items 1 through 5 below. The provisions of NFPA 14, Chapter 12, as modified in Appendix Q, shall also apply.

1. Full demolitions. In buildings and structures undergoing a full demolition, all existing standpipes shall be maintained in a state of readiness as a dry system in accordance with Item 2 of Section 3303.8 and shall be provided with an air pressurized alarm system.

2. New construction, alteration, and partial demolition. Where a dry standpipe system is utilized during new construction, alteration, or partial demolition operations, such standpipe system shall be provided with an air pressurized alarm system.

3. Submission of application. An application to install an air pressurized alarm system shall be filed by a registered design professional and a permit obtained by a licensed master plumber or licensed master fire suppression piping contractor. A licensed electrician shall obtain all required electrical permits in accordance with Chapter 3 of Title 27 of the Administrative Code.

4. Specifications. The following provisions shall apply to the air pressurized alarm system:

4.1 Pressure. Pressure shall be maintained in the standpipe and cross connections at all times and shall not exceed 25 psig (172 kPag) by utilizing nitrogen or an air compressor with an air dryer. The supervisory pressure shall be as determined by a registered design professional.

4.2 Automatic air pressurized alarm activation. The alarm shall be automatically activated when the pressure drops below the supervisory pressure or rises above the maximum pressure of 25 psig (172 kPag). When the alarm is activated, notification shall be made to the Fire Department in accordance with the New York City Fire Code, all work at the site shall cease, except as provided in Item 4.2.1, and an investigation of the entire standpipe system and air compressor shall be immediately performed to determine the cause of the alarm. Unless authorized by the Fire Department, no construction or demolition work shall resume until the standpipe system is repaired and the appropriate pressure is restored, except that any repairs to the standpipe system needed to restore the required pressure shall be undertaken immediately and the standpipe system restored as soon as possible. There shall be compliance with the requirements of the New York City Fire Code while the standpipe system is out of service. Upon completion of repairs to the standpipe system, a full inspection of such system shall be performed, which shall include, among other things, visually tracing the standpipe, including risers, cross connections and fire department connections to verify that no breach exists and checking all gauges of the standpipe system to ensure the standpipe system has been restored to a state of readiness.

4.2.1 Notwithstanding the provisions of Item 4.2, the activation of the alarm shall not require the cessation of work necessary for the completion of concrete pouring operations in progress at the time of alarm activation, where such cessation would cause a cold joint that would impair the structural integrity of the finished construction. The continuation of such operations shall be permitted only until an orderly termination of such operations can be effectuated. The site safety manager or coordinator shall record the names and locations of any employees necessary for the completion of the concrete pouring operations and provide them to the Fire Department personnel who arrive on the scene.

4.3 Air compressor. The air compressor shall be designed to automatically cut in and cut out at the supervisory pressure and shall be tied into the standpipe system between the fire department connections and the house check valves. The air compressor shall utilize an air dryer during times when freezing conditions exist to condition the air entering the dry standpipe system.

4.4 Alarm. The standpipe alarm system shall utilize pressure switches and control equipment to annunciate a local audible alarm on site that can be heard during working and non-working hours. The audible signal of the horn shall be at least 15 dBA above the ambient noise level but no more than 110 dBA.

4.5 Power supply. The standpipe alarm system shall be connected to an active, dedicated power supply at all times.

4.6 Check valves. Check valves shall be installed to prevent water from entering the air compressor.

4.7 Locks and caps. All control valves shall be chained and locked in the appropriate position and shall be provided with capped outlets. All hose valves shall also be provided with capped outlets.

4.8 Fire Department connections. Three inch (76 mm) iron hose plugs with gaskets in Fire Department connection swivels shall be provided.

4.9 Drainage. Provisions shall be made to drain water in any trapped sections of the dry standpipe system that are subject to freezing.

4.10 Manual air release connection. A minimum 2.5-inch (64 mm) connection located immediately downstream of the fire department connection check valve shall be provided and piped to a location immediately adjacent to the fire department connections. This line shall be fitted with a 2.5-inch (64 mm) hose valve and shall allow for release of the pressurized air from the dry standpipe system. The number of air release valves provided shall be such that the air pressure shall be released in no more than 3 minutes, which shall be verifiable by an actual air release test performed at the time of the initial installation.

4.11 Construction documents. Plans shall identify all standpipe risers, cross connections, fire department connections, any intermediate check valves that have to be removed, proposed location of the air release connections, designation of the supervisory pressure, complete information regarding the alarm system, and procedures for the safe pressurization and depressurization of the system.

4.12 Signage. Signage shall be provided at all fire department connections indicating that the dry standpipe system is pressurized and showing the location of the manual air release.

4.13 Pressure gauges. A system of pressure gauges shall be installed at the compressor and at the most remote points of the system from the compressor.

5. Planned removal from service of standpipe system and standpipe air pressurized alarm. Whenever the standpipe system is to be placed out of service for the addition of a new section to the system, removal of an existing section as demolition operations progress, or other planned event, the standpipe alarm may be temporarily deactivated subject to compliance with the requirements of the New York City Fire Code. Where a site safety manager or coordinator is required by this code, all alarm activations, inspections, and repairs shall be logged into the log book maintained by such site safety manager or coordinator. If the standpipe system is not returned to a state of readiness and the alarm reactivated within 2 hours of such planned removal from service, all construction or demolition work at the site shall cease, unless otherwise approved by the Fire Department.

3303.8.2 Free from obstruction.

Fire department hose connections shall be kept free from obstruction and shall be marked by a metal sign reading, "Standpipe Connection" and by a red light at night.

3303.8.3 Use of standpipes for purposes other than supplying water for firefighting.

Standpipes may be used for a purpose other than to supply water for firefighting operations, including but not limited to supplying water or compressed air for construction or demolition operations, subject to the approval of the Fire Department and provided at least one standpipe riser is maintained at all times for firefighting operations. Where the standpipe is used to supply water for construction or demolition operations and freezing conditions may occur, the standpipe shall be completely drained after use to prevent freezing.

3303.9 Elements to be maintained in existing buildings.

Required means of egress, existing structural elements, fire protection devices, and sanitary safeguards shall be maintained at all times during construction or demolition operations in existing buildings. Required means of egress shall not be obstructed in any manner that would destroy the full effectiveness of such means of egress.

Exception: Where adequate alternate provisions are provided in accordance with the requirements of this code, or where the element is temporarily or permanently disconnected, removed, or demolished in accordance with the requirements of this code and of the agency or authority having jurisdiction to temporarily or permanently disconnect, remove, or demolish such element. Such alternative means, disconnection, removal, or demolition shall be shown on the approved plans. Fire protection systems, including but not limited to sprinklers, standpipes, and fire alarms, shall only be taken out of service in accordance with the requirements of the New York City Fire Code.

3303.10 Operations in occupied buildings.

When construction or demolition activity occurs in an occupied building, barricades, signs, drop cloths, and other protective means shall be installed and maintained as necessary to provide reasonable protection for the occupants against hazard and nuisance. Such protective means shall be indicated on an occupant protection plan, or where a tenant protection plan is required by Section 3303.10.1, on a tenant protection plan.

3303.10.1 Tenant protection plan.

In buildings containing any occupied dwelling units, including newly constructed buildings that are partially occupied where work is still ongoing within the building, all alteration, construction, or partial demolition work shall be performed in accordance with a tenant protection plan as required by Article 120 of Title 28 of the Administrative Code.

(Am. L.L. 2019/106, 6/8/2019, eff. 3/8/2020)

3303.10.2 Inspections of tenant protection plan.

The owner shall notify the department in writing not more than 72 hours, but not less than 24 hours prior to the commencement of any work requiring a tenant protection plan. The department shall conduct an inspection of 10 percent of such sites within seven days after the commencement of such work to verify compliance with the tenant protection plan. The department shall conduct follow up inspections of such sites every 180 days until such construction is completed to verify compliance with the building code and tenant protection plan. Thereafter, the department shall conduct an inspection within 10 days of receipt of a complaint concerning such work. Where the department receives a complaint alleging that dust is not being contained or controlled in accordance with a tenant protection plan, it shall conduct an inspection within 24 hours. The department shall, in collaboration with the department of health and mental hygiene, develop a procedure to complete a lead-contaminated dust test upon a determination that dust is not being contained or controlled during such tenant protection plan inspections or an inspection conducted in response to a complaint, and take any appropriate enforcement action, including the issuance of an order pursuant to Section 28-207.2 of the Administrative Code. The department of health and mental hygiene shall assist the department to implement such procedure, including submitting dust samples collected by the department to a laboratory for analysis. The department shall refer the result of any such inspection to the department of health and mental hygiene for review and further inspection in accordance with the New York city health code.

(Am. L.L. 2019/116, 6/8/2019, eff. 3/8/2020; Am. L.L. 2021/040, 4/18/2021, eff. 4/18/2022; Am. L.L. 2023/077, 6/11/2023, eff. 6/11/2023)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2023/077.

3303.10.3 Enforcement of tenant protection plan.

If work is not being performed in accordance with the tenant protection plan, the commissioner may issue a stop work order pursuant to Section 28-207.2 of the Administrative Code.

(Am. L.L. 2017/154, 8/30/2017, eff. 12/28/2017)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2017/154.

3303.11 Stairs during construction or demolition.

Stairs shall meet the requirements of Section 3303.11.1 through 3303.11.3 during construction or demolition work.

3303.11.1 Existing stairs.

Stairs in an existing building undergoing alteration or a partial demolition shall be maintained in accordance with Section 3303.9. Stairs in a building undergoing a full demolition shall comply with Section 3306.9.9.

3303.11.2 Stairs during building construction or enlargements.

During new building construction or the enlargement of an existing building, stairs shall be provided at all locations where a permanent stair will be required and shall serve all floors. At least one of the provided stairs must be of permanent construction for its full length; in all other locations, the stairs may be of temporary or permanent construction.

Exceptions:

1. Where a floor is open to the public, all stairs required for egress from the floor must be of their permanent construction from that floor to the ground level.

2. Stairs are not required where the floor is closed to the public and the floor is less than 4 stories or 40 feet (12 192 mm) below the topmost working deck, whichever is less.

3. During the construction or enlargement of a building whose primary structural system consists of structural steel, where it is not feasible to provide one or more permanent stairs to serve all floors that are at least 4 stories or 40 feet (12 192 mm) below the topmost working deck, whichever is less, all stairs shall be of their permanent construction up to the level of the topmost completed steel floor, and temporary stairs, acceptable to the commissioner, shall be brought up in all locations to serve all remaining floors that are at least 4 stories or 40 feet (12 192 mm) below the topmost working deck, whichever is less. At a minimum, the temporary stairs shall be made of non-combustible material, be equipped with adequate handrails, be provided with landings that are level with the adjoining floor, and have riser height and tread depths that are uniform, within 1/4 inch (6 mm), for each flight of stairs.

3303.11.3 Lighted and kept free of obstructions.

All stairs in a building undergoing construction or demolition shall be lighted at all times, and shall be kept free of equipment, debris, and material in accordance with Section 3303.4.10.

3303.12 Elevators and hoists during construction or demolition.

Elevators and hoists shall meet the requirements of Sections 3303.12.1 through 3303.12.5 during construction or demolition work.

3303.12.1 Publicly accessible floors.

Existing elevators serving publicly accessible floors in a building undergoing construction or demolition work shall be maintained in accordance with Section 3303.9.

3303.12.2 Floors closed to the public.

When required by Sections 3303.12.2.1 through 3303.12.2.4, floors closed to the public in a new or existing building undergoing construction or demolition work shall be served by, at least, either:

1. An elevator provided with Phase I and Phase II recall meeting the requirements of Chapter 30, which shall be kept in readiness at all times for Fire Department use; or

2. A hoist meeting the requirements of Section 3318, which shall be available at all times for Fire Department use.

Exception: An elevator or hoist is not required during the course of construction or demolition of a building that does not require a permanent elevator.

3303.12.2.1 Initial installation of an elevator or hoist during the construction or enlargement of a building whose height will exceed 75 feet.

During the construction or enlargement of a building, once the topmost working deck exceeds 75 feet (22 860 mm) in height above the lowest level of the ground, all floors that are closed to the public and within 40 feet (12 192 mm) above the lowest level of the ground shall be served by an elevator or hoist meeting the requirements of this section. Where this measurement lands between floors, the measurement shall be rounded such that the elevator or hoist is brought up to serve the higher floor.

3303.12.2.2 Increasing the height of the elevator or hoist during the construction or enlargement of a building.

During the construction or enlargement of a building, when the topmost working deck exceeds 75 feet (22 860 mm) in height above the lowest level of the ground and subsequent to complying with Section 3303.12.2.1, all floors that are closed to the public and that are at least 4 stories or 48 feet (14 630 mm) below the topmost working deck, whichever is less, or for a building whose primary structural system consists of structural steel, at least 4 stories or 64 feet (19 507 mm) below the topmost working deck, whichever is less, shall be served by an elevator or hoist meeting the requirements of this section. However, no more than two weeks after the topmost working deck has become a walkable floor, a hoist or elevator meeting the requirements of this section shall be brought up to serve all remaining floors in the building that are closed to the public.

3303.12.2.3 During demolition.

During the demolition of a building where one or more floors are removed from the building, all floors in the building that are closed to the public and that are more than 7 stories or 75 feet (22 860 mm) below the topmost working deck, whichever is less, shall be served by an elevator or hoist meeting the requirements of this section.

3303.12.2.4 Other instances.

During the alteration of a building that would require a permanent elevator and where the scope of work does not constitute an enlargement or involve the removal of one or more floors from the building, all floors in the building that are closed to the public shall be served by an elevator or hoist meeting the requirements of this section.

3303.12.3 Deep excavations.

Where the proposed lowest level of a building with a footprint of 10,000 square feet (929 m 2 ) or greater is constructed at a depth greater than 75 feet (22 860 mm), a hoist meeting the requirements of Section 3318 shall be available at all times for Fire Department use once the foundation is in place and the first elevated slab has been erected. The hoist shall serve the level at grade and all stories below grade.

Exception: Subject to the approval of the commissioner, alternate means available at all times for Fire Department use, including but not limited to a vehicular ramp, shall be provided.

3303.12.4 Converting elevators.

Where an existing elevator is converted from passenger or freight use the department shall be notified in accordance with the requirements of Chapter 30.

3303.12.5 Hoist travel.

If the travel of the hoist cannot be increased or decreased to fulfill the requirements of this section due to inclement weather, it shall be increased by the end of the next working day.

3303.12.6 Stretcher accommodation.

Where a hoist is provided, it must be capable of accommodating two standing individuals and a stretcher that is 84 inches in length by 24 inches in width (2134 mm by 610 mm).

3303.13 Interrupted or abandoned and discontinued operations.

Where construction or demolition work has been interrupted or abandoned and discontinued, the owner of the site shall ensure the site is secured, protected, and maintained to safeguard the public and property, and that the site is in compliance with the requirements of Sections 3303.13.1 through 3303.13.3.

3303.13.1 Fencing.

A fence meeting the requirements of Section 3307.7 shall be maintained throughout the duration of time that operations at the site are interrupted or abandoned and discontinued.

3303.13.2 Safety monitoring plan.

Where work has been interrupted or abandoned and discontinued for a period of at least three months, a safety monitoring plan satisfactory to the commissioner shall be prepared by a qualified person on behalf of the owner of the property and submitted to the department by the owner. Such safety monitoring plan shall be specific to the site, shall identify safeguards to be instituted and maintained to secure the site, and shall specify monitoring to be performed during the duration of suspension of work. The owner of the property shall be responsible for ensuring compliance with such plan.

3303.13.3 Filling and grading.

Where work has been interrupted or abandoned and discontinued for a period of at least three months, all open excavations shall be filled and graded to eliminate all steep slopes, holes, obstructions or similar sources of hazard. Fill shall consist of clean, noncombustible material. The final surface shall be graded in such a manner as to drain the lot, eliminate pockets in the fill, and prevent the accumulation of water without damaging any foundations on the premises or on adjoining property.

Exception: Filling and grading is not required for abandoned, discontinued, or interrupted excavations that are:

1. Secured in accordance with Section 3303.13.2, and

2. Inspected periodically by an engineer to verify continued stability of the excavation, with a record of such inspections signed, sealed, and dated by the engineer.

3303.14 Water conditions.

The requirements of Sections 3303.14.1 through 3303.14.5 shall be followed to control the accumulation of water.

3303.14.1 Drainage.

No condition shall be created as a result of construction or demolition operations that will interfere with natural surface drainage. Water courses, drainage ditches, etc., shall not be obstructed by debris, refuse, waste building materials, earth, stones, tree stumps, branches, or other objects that may interfere with surface drainage or cause the impoundment of surface waters.

3303.14.2 Protection of foundations.

Provision shall be made to prevent the accumulation of water or water damage to any foundations on the premises or to adjoining property.

3303.14.3 Drainage of excavations.

All excavations shall be drained, and the drainage shall be maintained as long as the excavation continues or remains. Where necessary, pumping shall be used, provided proper permits are obtained from the New York City Department of Environmental Protection.

3303.14.4 Clogging.

The requirements of Section 3303.5.3 shall apply.

3303.14.5 Dewatering.

The contractor or other entity performing the soil or foundation work shall dewater the site, as needed, for the progress of the work, and shall take all necessary measures to prevent settlement, slope failure, and damage to buildings, structures, and property affected by the dewatering operations.

3303.14.5.1 Dewatering plan.

Where dewatering is performed to drawdown or control the level of the water table, the dewatering operation shall proceed in accordance with a site specific plan developed by a registered design professional. The dewatering plan must incorporate all the conditions and findings identified in the geotechnical report required by Section 1803.6, the evaluation analysis required by Section 1817, and the preconstruction survey required by Section 3309.4.3. At a minimum, the plan shall indicate:

1. Height of the water table, including all seasonal fluctuations;

2. Anticipated schedule of dewatering operations;

3. The location of wells, settlement tanks, observation points, and dewatering equipment;

4. Maximum discharge;

5. Permissible drawdown outside of the limits of the excavation;

6. Thresholds for anticipated settlement;

7. Thresholds for anticipated lateral movement; and

8. The program to monitor and control water table drawdown and settlement/movement of affected structures, property, and temporary construction installations. Program criteria to be specified shall include, but not be limited to, the monitoring frequency, plan to periodically test the discharge from the pumps to determine if the water being extracted contains unanticipated fine grain soil or sand, plan to account for fluctuations in the water table (due to seasonal conditions, weather, or other factors), reporting requirements for the monitoring program, and procedures to be implemented when thresholds are exceeded.

3303.15 Concrete washout water.

Concrete washout water shall not be allowed to enter any sewer, catch basin, drain, or body of water or to leach into the ground.

3303.15.1 Collection and containment.

All concrete washout water shall be collected and contained in or on the concrete mixer truck or in pre-manufactured watertight containers specifically designed and fabricated for the purpose of collecting and containing concrete washout water on-site. Such containers shall be of sufficient quantity and size to accommodate all rinsing operations required on-site so as not to delay the timely return of concrete ready mix trucks to the concrete plant and shall be protected from breach or overflow at all times.

3303.15.2 Location.

Rinsing operations and concrete washout water containers shall not be located less than 30 feet from any sewer, drain, catch basin, or body of water without the written approval of the commissioner.

3303.15.3 Disposal.

Collected concrete washout water shall be transported off site for treatment and disposal or contained on site until completely evaporated. Any hardened concrete remaining after evaporation shall be disposed of, reused or recycled.

3303.16 Worker sheds, contractor sheds, contractor offices, and similar structures.

Worker sheds, contractor sheds, contractor offices, and similar structures shall:

1. Be provided with a hardwire or battery powered smoke detector that meets the requirements of this code and the New York City Fire Code;

2. Be equipped with an automatic sprinkler system or a non-water automatic fire-extinguishing system, including a dry-chemical extinguishing system, that meets the requirements of this code and the New York City Fire Code, when the shed or office is installed or predominantly used to facilitate work at a building that requires an automatic sprinkler system;

3. Meet the door width, travel distances, and occupancy load requirements of Chapter 10 of the building code; and

4. Be constructed to comply with either 4.1, 4.2, or 4.3:

4.1. Meet the requirements of this code for Types I or II fire-resistance-rated construction where:

4.1.1. Located within a building or structure; or

4.1.2. Located 30 feet (9144 mm) or less from another building or structure within the fire district.

4.2. Meet the requirements of this code for Type III fire-resistance-rated construction where:

4.2.1. Located outside of a building or structure; and

4.2.2. Located more than 30 feet (9144 mm) from another building or structure within the fire district.

4.3. Meet the requirements of this code for Type III fire-resistance-rated construction where:

4.3.1. Located outside of a building or structure; and

4.3.2. Located outside of the fire district.

3303.16.1 Permit required.

No worker shed, contractor shed, contractor office, or similar structure shall be installed until a permit for the shed or office has been issued by the commissioner in accordance with the requirements of Chapter 1 of Title 28 of the Administrative Code.

Exception: A permit is not required for a worker shed, contractor shed, contractor office, or similar structure that does not exceed 1 story in height and 120 square feet (36.58 m 2 ) in area, and further provided that the shed, office, or similar structure is located more than 30 feet (9144 mm) from another shed, or office, or similar structure.

(Am. L.L. 2023/077, 6/11/2023, eff. 6/11/2023)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2023/077.

3303.16.2 Utility hookups.

No electrical, plumbing, or other utility hook up shall be made to a worker shed, contractor shed, contractor office, or similar structure until a permit for the hookup has been issued by the commissioner in accordance with the requirements of Chapter 1 of Title 28 of the Administrative Code. Where required by Chapter 4 of Title 28 of the Administrative Code, the utility hookup must be made by or under the direct and continuing supervision of a licensed individual.

Section BC 3304. Soil and Foundation Work

Open this section

3304.1 Scope.

The provisions of this section shall apply to all soil and foundation work, including but not limited to drilling or excavations made for the purposes of taking earth, sand, gravel, rock, or other material, as well as to soil and foundation work related to accessory uses such as garages, pools, and decks, and also to the underpinning or bracing of buildings or structures, in order to safeguard the public and property from such work. In addition to the requirements of this section, the applicable sections of Chapter 18 shall also apply to soil and foundation work.

Exceptions: This section shall not apply to:

1. Soil or foundation work not related to the underpinning or bracing of an existing building or structure, and which is performed in connection with utility or infrastructure work occurring within a public right of way, including but not limited to the construction, alteration, maintenance, repair, or demolition of bridges, streets, sidewalks, highways, railroads, subways, water tunnels, or utility lines.

2. Soil or foundation work on cemetery grounds for burials.

3. Soil or foundation work performed within an industrial or commercial quarry, plant, or yard and not related to the construction or demolition of a building or structure on the property of such quarry, plant, or yard.

3304.1.1 Measurements.

The depth of all soil and foundation work shall be measured from the level of the adjacent ground surface to the lowest point of the soil and foundation work. The height of all soil and foundation work shall be measured from the level of the adjacent ground surface to the highest point of the soil and foundation work. Where soil and foundation work occurs within a basement or cellar, the soil and foundation work shall be measured from the level of the adjacent slab.

3304.1.2 Safety of the public and property.

Soil and foundation work shall be performed and, as necessary, supported, in a manner to prevent injury to the public, damage to property, or collapse, subsidence, or uncontrolled loss of earth or rock.

3304.2 Permit.

A permit shall be obtained prior to the commencement of soil or foundation work when required by Chapter 1 of Title 28 of the Administrative Code.

3304.3 Notification.

Prior to the commencement of soil or foundation work, notification shall be provided as follows.

3304.3.1 Notification of the department.

No soil or foundation work within the property line shall commence unless the permit holder, or where there is no permit holder the person causing the soil or foundation work to be made, notifies the department, via phone or electronically, at least 24 hours, but no more than 48 hours prior to the commencement of such work. The notification shall state the date that such soil or foundation work is to commence and include a "Call before you dig" confirmation number verifying compliance with the notification requirements of Section 3304.3.7. Should the notification date fall on a weekend or official holiday, the permit holder, or where there is no permit holder the person causing the soil or foundation work to be made, shall notify the department on the last business day before the commencement date.

In the event that the soil or foundation work does not begin on the date provided in the notification to the department, the permit holder, or where there is no permit holder the person causing the soil or foundation work to be made, shall notify the department of its cancellation not more than 24 hours prior to but no later than the date for which the soil or foundation work was scheduled. Should the cancellation date fall on a weekend or an official holiday, the permit holder, or where there is no permit holder the person causing the soil or foundation work to be made, shall notify the department on the next business day after the intended commencement date. The permit holder, or where there is no permit holder the person causing the soil or foundation work to be made, shall notify the department of a new intended commencement date pursuant to the provisions above.

Exceptions: Notification to the department is not required for the following:

1. Hand excavation work that extends less than 5 feet (1524 mm) in depth and is 2 feet (610 mm) or more from an existing footing or foundation. This exception shall not apply to any hand excavation work performed anywhere in existing or demolished basements or cellars that adjoin existing foundations.

2. Excavations for a geotechnical investigation that do not exceed 10 feet (3048 mm) in length, width, or diameter, and that are conducted under the supervision of a registered design professional.

3. Emergency work performed by the Department of Housing Preservation and Development (HPD) or other agency as directed by the commissioner or work on unsafe buildings performed by HPD or other agency pursuant to a precept.

4. Soil or foundation work related to gardening or landscaping work, provided no excavation occurs to a depth of 5 feet (1524 mm) or greater; and either:

4.1 The excavation occurs more than 5 feet (1524 mm) from all footings and foundations; or

4.2 Where the excavation occurs within 5 feet (1524 mm) or less from a footing or foundation, such excavation does not occur below the level of the footing or foundation.

5. Soil or foundation work related to the pouring of a slab or pavement, provided no excavation to a depth greater than 2 feet (610 mm) occurs in conjunction with such work.

6. Where notification is required by Section 3306.3, separate notification for the removal of a foundation is not required.

3304.3.2 Notification of adjoining property owners.

When an excavation to a depth of 5 feet to 10 feet (1524 mm to 3048 mm) is to be made within 10 feet (3048 mm) of an adjacent footing or foundation, or when any excavation over 10 feet (3048 mm) is to be made anywhere on a site, the person causing the excavation to be made shall provide written notice to the owners of the adjoining property not less than 10 days prior to the scheduled starting date of the excavation. The written notice shall provide a description of the work to be performed, the timeframe and schedule, the contact information of the person causing the excavation to be made, and the contact information of the department.

Exception: Notification is not required where the excavation is set back from the edge of the adjacent footing or foundation or adjoining property by a ratio of 2 horizontal to 1 vertical, as measured from the deepest point of the excavation.

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2008/026.

3304.3.3 Notification to the Department of Environmental Protection.

Whenever soil or foundation work, for any purpose, is proposed to a depth greater than 50 feet (15 240 mm) in the borough of the Bronx or on or north of 135th Street in the borough of Manhattan, or greater than 100 feet (30 480 mm) in the borough of Brooklyn, Queens, or Staten Island or south of 135th Street in the borough of Manhattan, the owner of the premises, engineer, architect or contractor shall notify the New York City Department of Environmental Protection prior to commencement of such activity in accordance with Section 24-367 of the Administrative Code and any rules promulgated thereunder. The issuance of any permit or approval by the department shall not relieve the applicant, owner, engineer, architect or contractor of the obligation to comply with any notification or permitting requirements of the New York City Department of Environmental Protection. Whether or not a permit is required from the department for work, including but not limited to drilling for borings or geothermal wells, the owner of the premises, engineer, architect or contractor shall still comply with the notification and permitting requirements of the New York City Department of Environmental Protection.

(Am. L.L. 2018/065, 1/19/2018, eff. 1/19/2019)

3304.3.4 Excavations requiring permit from the New York State Department of Environmental Conservation.

Whenever soil or foundation work is planned deeper than 500 feet (152 m) below grade, a permit may be required from the New York State Department of Environmental Conservation. The issuance of any permit or approval by the department shall not relieve the applicant of the obligation to comply with any approval or permitting requirements of the New York State Department of Environmental Conservation. Whenever any drilling for borings or geothermal wells is planned, the owner of the premises or the contractor shall notify the New York State Department of Environmental Conservation prior to commencement of such activity to determine if a permit is necessary.

3304.3.5 Notification and approval of the New York City Transit Authority, the Metropolitan Transportation Authority, and the Port Authority of New York and New Jersey.

Whenever an excavation of any depth is proposed within 200 feet (60 960 mm) of any facility, infrastructure, or property under the jurisdiction of the New York City Transit Authority, the Metropolitan Transportation Authority, or the Port Authority of New York and New Jersey, including but not limited to rail and subway lines, stations, station entrance and access points, bridges, tunnels, bus depots, access roads, fan plants, pump rooms, substations, shops and yards, duct lines, and easements, an approval shall be obtained from such authority having jurisdiction. The owner of the premises or the contractor shall notify the authority having jurisdiction prior to commencement of any such activity. The issuance of any permit or approval by the department shall not relieve the applicant of the obligation to comply with any approval requirements of the New York City Transit Authority, the Metropolitan Transportation Authority, or the Port Authority of New York and New Jersey.

3304.3.6 Notification and permit requirements of the New York City Fire Department.

Soil or foundation work that is to be done with the use of explosives shall also be subject to the notification and permit requirements set forth in the New York City Fire Code.

3304.3.7 Call before you dig notification.

"Call before you dig" notification shall be provided in accordance with the requirements of 16 NYCRR Part 753. The notification must address all street frontages associated with the soil and foundation work.

3304.4 Protection of sides of excavations.

The sides of excavations shall be protected in accordance with the requirements of Sections 3304.4.1 through 3304.4.6.

3304.4.1 Support of excavation construction documents.

Means of supporting excavations, including related or resulting embankments, rock faces, and soil slopes, shall be indicated on construction documents. Such means of supporting excavations shall be installed and maintained in accordance with the construction documents. The construction documents shall be prepared by a registered design professional who has demonstrated knowledge or experience in the design of retaining structures or bracing systems for the support of excavation. Where the excavation exceeds 20 feet (6096 mm) in depth, the registered design professional shall be a New York State licensed professional engineer.

Exceptions: Construction documents indicating the means of supporting the excavation are not required if:

1. The excavation meets the conditions specified in Items 1.1 through 1.4:

1.1. Is less than 5 feet (1524 mm) in depth;

1.2. Occurs above the level of the water table;

1.3. Occurs more than 5 feet (1524 mm) from all streets, sidewalks, tunnels, railroad tracks, public right of ways, and retaining walls; and

1.4. Occurs either:

1.4.1. More than 5 feet (1524 mm) from all footings and foundations; or

1.4.2. When within 5 feet (1524 mm) or less from a footing or foundation, does not extend below the level of the footing or foundation.

2. The excavation meets the conditions specified in Items 2.1 through 2.3:

2.1. Occurs more than 5 feet (1524 mm) from all footings, foundations, streets, sidewalks, tunnels, railroad tracks, public right of ways, and retaining walls;

2.2. Does not exceed 20 feet (6096 mm) in depth; and

2.3. Either:

2.3.1. The slope of the excavation does not exceed 1.5 horizontal to 1 vertical (34 degrees measured from the horizontal), with no benching allowed; or

2.3.2. A registered design professional determines the soil type, and the excavation is properly sloped or benched for the soil type in accordance with the requirements of Section 3304.4.2. Determination of the soil type shall be based upon a site specific evaluation, and documentation of the determination, signed and sealed by the registered design professional, shall be kept at the site.

3. A trench box is utilized in accordance with the manufacturer's specifications, provided a physical copy of the manufacturer specifications are available onsite.

4. It is a trench that complies with Table 3304.4.1, including all notes to the table.

5. The excavation is performed in conjunction with the installation or removal of an exterior in-ground pool, provided such pool is an accessory to a one-or two-family home, is limited to 400 square feet (121.92 m 2 ) in area, and further provided that the distance from the edge of the pool to any building, structure, or lot line is greater than the depth of the deepest portion of the pool.

6. Where demolition drawings are required by Section 3306.5, separate support of excavation construction documents for the removal of the foundation are not required, provided the details required for a support of excavation drawing are instead shown on the demolition drawings.

Table 3304.4.1 Minimum Sizes of Timber Bracing and Timber Sheet Piling for Trenches Not Exceeding 10 Feet (3048 mm) in Depth and 15 Feet (4572 mm) in Width

Depth of trench Width of trench Nominal size of cross bracing at 6 feet (1829 mm) horizontal spacing Shoring Up to 10 ft (3048 mm) Up to 9 ft (2743 mm) 6 in x 8 in (152 mm x 203 mm) Sheet Piling, 2 in x 6 in (51 mm x 152 mm), spaced tight, and Wales, 12 in x 12 in (305 mm x 305 mm), with 5 ft (1524 mm) maximum vertical spacing Up to 15 ft (4572 mm) 8 in x 8 in (203 mm x 203 mm)

Notes to Table 3304.4.1:

1. All timber or equivalent substitute to have bending strength of 850 psi or above.

2. The depth of the trench shall be considered the depth from top of grade, not top of shoring structure should a portion of the support of excavation be by benching or sloping methods.

3. Table shall not be utilized if any of the following are met:

a. Trench exceeds the specified dimensions.

b. Stored material or structures are present within a distance equal to the depth of the trench.

c. Equipment surcharge loading exceeds 20,000 lb (9071.85 kg).

d. Surcharge load exceeds 2 ft (610 mm).

e. Cross bracing is subject to any vertical load that meets or exceeds a load equivalent to a 240-lb (109 kg) gravity load distributed over a 12 in (305 mm) section of the center of the bracing member.

(Am. L.L. 2023/077, 6/11/2023, eff. 6/11/2023)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2023/077.

3304.4.1.1 Content of support of excavation construction documents.

Support of excavation construction documents shall, at a minimum:

1. Be specific to the site;

2. Be fully dimensioned;

3. Account for the entire scope of work;

4. Indicate all items required by Section 107.8;

5. Indicate soil or rock type and bearing capacity;

6. Indicate the water table elevation;

7. Indicate if dewatering is needed, and if a dewatering plan is required by Section 3303.14.5, note that a dewatering plan is required and the depth at which the dewatering plan must be put into effect. Further, where a dewatering plan is required by Section 3303.14.5, note the depth at which work must stop if a dewatering plan has not been provided; such depth must be equal to or shallower than the depth specified for the dewatering plan to be put into effect;

8. Indicate the support of excavation, including but not limited to sloping, benching, sheeting, shoring, and bracing;

9. For an excavation in rock, any supplemental support of the rock face;

10. Indicate all structures, utilities, infrastructure, and subsurface structures impacted by the soil or foundation work;

11. Indicate the design load imposed for temporary construction installations, material, and equipment, including but limited to sidewalk sheds, scaffolds, runback structures, cranes, excavators, and stored or piled material, and note that all temporary construction installations or equipment that will impose a load on the support of excavation in excess of the design load imposed must be reviewed for acceptability by the designer of the support of excavation;

12. Indicate the sequence of the excavation operation and the installation and removal of the support of excavation, including all relevant phasing, and including the depth at which support of excavation must be installed;

13. Account for the provisions of Section 3304.4.5;

14. Reference the monitoring plan, where a monitoring plan is required;

15. Specify required inspections and inspection intervals for the support of excavation, including special inspections; and

16. Where slurry is utilized to support the excavation, the information required by Section 3304.12 shall also be indicated.

3304.4.1.2 Geotechnical analysis and relevant reports.

The support of excavation construction documents shall be developed based upon site specific testing and analysis performed by a registered design professional who has demonstrated knowledge or experience in geotechnical evaluation. The support of excavation construction documents must incorporate all the conditions and findings identified in the geotechnical report required by Section 1803.6, the evaluation analysis required by Section 1817, and the preconstruction survey required by Section 3309.4.3.

3304.4.2 Limitation on sloping and benching.

Where sloping or benching is utilized to support an excavation, the slope or bench step shall be appropriate for conditions at the site, including but not limited to soil type, environmental conditions, and surcharge loads. In no case shall the maximum slope or bench step for an excavation that is 5 feet (1524 mm) or greater in depth exceed the values specified in Table 3304.4.2. For layered soil conditions, the most restrictive value among the soil types present at the excavation location shall be utilized unless otherwise specified by the registered design professional and indicated on the construction documents required by Section 3304.4.1.

Exception: The limitations of Table 3304.4.2 shall not apply to excavations made in Class 1a, 1b, or 1c rock, as classified by Chapter 18, provided the geotechnical report required by Section 1803.6 substantiates the safety of the proposed slope, cut, or bench step, and further provided that the resulting slope, cut, or bench step, as well as any supplemental support of the rock face, is indicated on the construction documents required by Section 3304.4.1.

Table 3304.4.2 Maximum Allowable Slopes and Steps

Soil Type Maximum Allowable Slopes (Horizontal: Vertical) Maximum Allowable Bench Step Type A soil 1:1 (45º) 5 feet (1524 mm) Type B soil 1:1 (45º) 4 feet (1219 mm) Type C soil 1 1/2:1 (34º) Not allowed

3304.4.3 Fence.

Every site with an excavation shall be enclosed with a fence that meets the requirements of Section 3307.7.

3304.4.4 Guardrail system.

All open edges of an excavation that are 6 feet (1829 mm) or greater in depth shall be protected by a guardrail system meeting the requirements of Sections 3308.7.1 through 3308.7.5, or by a solid enclosure at least 3 feet 6 inches (1067 mm) high. For the purpose of a guardrail system installed in accordance with this section to protect the open edge of an excavation, the term "floor" in Sections 3308.7.1 through 3308.7.5 shall mean "ground."

Exceptions:

1. A toeboard is not required where the sheeting, shoring, bracing, or any other support of excavation extends at least 3 1/2 inches (89 mm) above the top of the excavation.

2. A guardrail system or a solid enclosure is not required where access to the adjoining area is precluded.

3. A guardrail system or a solid enclosure is not required where side slopes are three horizontal by one vertical (33-percent slope) or flatter.

4. In lieu of a guardrail system, wells, pits, excavation shafts, or similar excavations may be protected by an adequate cover capable of supporting, without failure, at least twice the weight of persons, equipment, and materials that may be imposed on the cover at any one time, or where located in roadways and vehicular aisles, at least twice the maximum axle load of the largest vehicle expected to cross over the cover. The cover shall be secured when installed so as to prevent accidental displacement by the wind, equipment, or persons, and shall be color coded or marked with the word "HOLE" or "COVER" to provide warning of the hazard.

5. The edges of ramps shall be protected in accordance with Section 3315.

(Am. L.L. 2023/077, 6/11/2023, eff. 6/11/2023)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2023/077.

3304.4.4.1 Openings.

To provide necessary openings for intermittent operations, one or more sections of the guardrail system or solid enclosure may be hinged or supported in sockets. When supported in sockets, rails shall be so constructed that they cannot be jolted out. A button or hook may be used to hold the guardrail system or solid enclosure in a fixed position. As an alternative to hinged or socketed sections, substantial chains or ropes may be used to guard such openings in such guardrail system or solid enclosure. Where so used, the chains or ropes shall meet the tautness and height requirements as the rails of a standard guardrail system.

3304.4.5 Placing of soil or foundation work equipment and excavated material.

Excavated material and superimposed loads, including but not limited to equipment and trucks used for soil or foundation work, shall not be placed closer to the edge of the excavation than a distance equal to one and one-half times the depth of such excavation unless the sides of the excavation have been sloped or sheet piled (or sheeted) and shored to withstand the lateral force imposed by such superimposed loads, or the registered design professional has determined the side of the excavation can adequately support the load imposed, with such support or determination shown on construction documents required by Section 3304.4.1. In the case of open excavations with side slopes, the edge of excavation shall be taken as the top of the slope.

3304.4.6 Installation of protection.

Required protection for the sides of the excavation shall be installed as the excavation advances. The placement of permanent structures or fill in areas requiring support of excavation shall not begin until the support of excavation has been completed for such areas.

3304.5 Inspections.

Soil and foundation work shall be inspected in accordance with the requirements of Sections 3304.5.1 and 3304.5.2.

3304.5.1 Rainstorms.

All sides or slopes of excavations or embankments shall be inspected after rainstorms, or any other hazard-increasing event, and safe conditions shall be restored.

3304.5.2 Special inspections.

Special inspections shall be performed in accordance with Chapter 17.

3304.6 Retaining walls.

The requirements of Article 305 of Title 28 of the Administrative Code, as well as Sections 1806 and 3309 of the building code shall apply as applicable.

3304.7 Access.

Every excavation shall be provided with at least one safe means of ingress and egress that is kept available at all times. For a trench that has a depth of 4 feet (1219 mm) or greater, and with a width of 15 feet (4572 mm) or less, as measured between the soil, forms, or structure at the bottom of the trench, one or more stairways, ladders, ramps, or other safe means of ingress and egress shall be located in the trench so as to require no more than 25 feet (7620 mm) of lateral travel.

3304.8 Drainage.

The requirements of Section 3303.14 shall apply.

3304.9 Utilities.

The requirements of Section 3303.2 shall apply.

3304.10 Dewatering.

The requirements of Section 3303.14 shall apply.

3304.11 Underpinning requirements.

The requirements of Section 1814 and Section 3309 shall apply.

3304.12 Slurry.

Where slurry is utilized to support an excavation, trench, or drilled or bored hole, slurry mix proportions and installation procedures shall be provided by a registered design professional on signed and sealed design and installation procedures. The installation procedures shall account for all imposed loads, including those from the earth, adjacent structures, and adjacent equipment. Where construction documents are required for the support of excavation by Section 3304.4.1, slurry mix proportions, slurry installation procedures, and slurry parameters necessary for stability, including but not limited to viscosity, unit weight, fluid loss, sand content, and pH, shall be indicated on such construction documents. The use of slurry to support excavations shall be subject to special inspection in accordance with Chapter 17.

Section BC 3305. Material Placement and Installation

Open this section

3305.1 Scope.

Materials shall be placed and installed in accordance with the requirements of this section and in a manner such that the safety of the public and property will not be endangered.

3305.1.1 Handling and storing materials.

Materials to be placed or installed shall be handled and stored in such a manner as to prevent damage to the material, including but not limited to:

1. Being shipped and handled in a manner to avoid permanent deformation to the material or damage to protective coatings;

2. Being protected against corrosion that results in a loss of structural integrity; and

3. Not being dropped, thrown, or dragged.

3305.1.2 Rigging.

The requirements of Section 3316.9 and rules promulgated by the commissioner shall apply to the conduct of all rigging operations.

3305.2 Structural steel assembly.

Structural steel assembly shall be in accordance with the requirements of AISC 360 and the requirements of Chapter 22 and Sections 3305.2.1 through 3305.2.8 of this code.

3305.2.1 Shop drawings.

The requirements of Section 2205.3.1 shall apply.

3305.2.2 Field connections.

The requirements of Section 2205.3.2 shall apply.

3305.2.3 Repair of damage.

Any damage to protective coatings shall be repaired prior to the application of fireproofing, the placement of concrete around the steel, or any other action that would otherwise conceal the steel. Any loss of section, bends, crimps or other evidence of permanent deformations shall be repaired by methods approved by the registered design professional of record or the piece shall be rejected.

3305.2.4 Open web steel joists.

The placement and installation of open web steel joists shall comply with the requirements of Sections 3305.2.4.1 through 3305.2.4.3.

3305.2.4.1 Attached to support structure.

Open web steel joists shall be attached to the support structure, at least at one end on both sides of the seat, immediately upon placement in the final erection position and before additional joists are placed.

Exception: Open web steel joists that have been pre-assembled into panels with bridging shall be attached to the structure at each panel corner with sufficient bolted or welded connections before the hoisting cables are released.

3305.2.4.2 Connection to bays.

Connections of individual open web steel joists to steel structures in bays of 40 feet (12 192 mm) or more shall be fabricated to allow for field bolting of connections during erection.

Exception: Open web steel-joists that have been pre-assembled into panels.

3305.2.4.3 Landing and placing loads.

The landing and placing of loads on open web steel joists shall be in accordance with the following requirements:

1. No load shall be placed on open web steel joists until they are permanently fastened in place or otherwise secured in accordance with methods approved by the registered design professional of record, and the special inspector responsible for the open web steel joists has signed and dated a report indicating compliance with the requirements of this item.

2. During the construction period, the contractor shall ensure that all loads placed on the steel are distributed so as not to exceed the carrying capacity of any open web steel joist.

3. Except as provided in item number 5, no construction loads are allowed on the steel joists until all bridging is installed and anchored and all joist-bearing ends are attached.

4. The weight of a bundle of joist bridging shall not exceed a total of 1,000 pounds (454 kg). A bundle of joist bridging shall be placed on a minimum of three steel joists that are secured at one end. The edge of the bridging bundle shall be positioned within 1 foot (305 mm) of the secured end.

5. No bundle of decking may be placed on steel joists until all bridging has been installed and anchored and all joist bearing ends attached, unless all of the following conditions are met:

5.1. The contractor has first determined from a qualified person and documented in a site-specific erection plan that the structure or portion of the structure is capable of supporting the load;

5.2. The bundle of decking is placed on a minimum of three steel joists;

5.3. The joists supporting the bundle of decking are attached at both ends;

5.4. At least one row of bridging is installed and anchored;

5.5. The total weight of the bundle of decking does not exceed 4,000 pounds (1816 kg); and

5.6. Placement of the bundle of decking shall be in accordance with item number 6.

6. The edge of the construction load shall be placed within 1 foot (305 mm) of the bearing surface of the joist end.

(Am. L.L. 2023/077, 6/11/2023, eff. 6/11/2023)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2023/077.

3305.2.5 Reserved.

3305.2.6 Erection of trusses.

Trusses shall be braced or guyed, as necessary, for the safety of the structure.

3305.2.7 Erection of frames.

Structural frames shall be properly braced with shores, guyed cables, turnbuckles, or other devices, as necessary, for the safety of the structure.

3305.2.8 Permanent flooring and steel erection in tiered buildings.

The permanent floors of such buildings or other structures shall be installed as soon as possible as the erection of structural steel members progresses. In no case shall there be more than eight stories, floors or equivalent levels or 120 feet (36 576 mm), whichever is less, between the working deck and the uppermost permanent floor.

Exception: Where otherwise designed, in accordance with the approved construction documents, by the registered design professional of record.

3305.3 Concrete formwork.

Concrete formwork shall be in accordance with the requirements of Sections 3305.3.1 through 3305.3.7.

3305.3.1 General requirements.

The design, fabrication and erection of forms shall comply with the requirements of Sections 3305.3.1.1 through 3305.3.1.6.

3305.3.1.1 Safe support of loads.

Formwork, including all related braces, shoring, framing, and auxiliary construction, shall be proportioned, erected, supported, braced, and maintained so that it will safely support all vertical and lateral loads that might be applied until such loads can be supported by the permanent construction.

3305.3.1.2 Vertical and lateral loads.

Vertical and lateral loads shall be carried to the ground by the formwork system, by the new construction after it has attained adequate strength for that purpose, or by existing structures. Forms and their supports shall be designed so as not to damage previously placed structures.

3305.3.1.2.1 Use of existing structures to support vertical or lateral loads.

The use of existing structures to support vertical or lateral loads imposed by concrete construction operations shall require an evaluation by a registered design professional of the adequacy of the existing structure to support the loads to be imposed. The registered design professional shall prepare design drawings documenting the findings of the evaluation, indicate the location of formwork elements, and the interface between the formwork and the existing structure. The placement of concrete against a stay form adjacent to an existing structure, against insulation in a seismic gap, or against other elements that have the potential to transfer loads to an existing structure shall be assumed to impose a load on an existing structure, and shall always require an evaluation by a registered design professional in accordance with the requirements of this section. Where the evaluation determines the use of such elements does not impose a load, as documented on design drawings in accordance with this section, the requirement set forth in Item 8 of Section 3305.3.2.1 shall not apply.

(Am. L.L. 2023/077, 6/11/2023, eff. 6/11/2023)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2023/077.

3305.3.1.3 Bracing.

Forms shall be properly braced or tied together so as to maintain position and shape, and shall conform to the sizes and shapes of members as shown on the design drawings.

3305.3.1.4 Ramps, runways and platforms.

Ramps, runways, and platforms utilized in connection with concrete placement shall comply with Section 3315.

3305.3.1.5 Design.

Concrete formwork shall be designed in accordance with Section 3305.3.2.

3305.3.1.6 Forms for prestressed and post-tensioned concrete.

Forms for prestressed and post-tensioned concrete members shall be designed and constructed to permit movement of the member without damage during application of the prestressing or post-tensioning forces, or during installation of the prestressing steel.

3305.3.2 Design of concrete formwork.

Design of formwork, including but not limited to forms, proprietary formwork products, shores, and shoring foundations, shall comply with ACI 318, Section 26.11, and the requirements of Sections 3305.3.2.1 through 3305.3.2.8 of this code.

3305.3.2.1 Design drawings.

Site-specific formwork design drawings prepared by a registered design professional shall be required in the following cases:

1. For concrete formwork in a structure classified as a major building;

2. Wherever the shore or form height exceeds 14 feet (4267 mm);

3. Wherever the total vertical load on the forms exceeds 150 pounds per square foot (732 kg/m 2 );

4. Wherever power buggies are used;

5. Wherever multi-stage shores are used;

6. Wherever the slab thicknesses or beam heights equal or exceed 10 inches (254 mm);

7. Wherever there are concentrated loads exceeding 2,000 pounds (907 kg) imposed on the formwork; or

8. Wherever there are loads are imposed on existing structures in accordance with Section 3305.3.1.2.1.

Exception: Design drawings prepared by a registered design professional are not required for formwork installed in conjunction with slabs supported directly on grade or footings where such slab or footing does not impart any load on an adjacent structure.

3305.3.2.2 Vertical loads.

Vertical loads shall include the total dead and live loads. Dead load shall include the weight of the formwork plus the weight of the reinforcement and fresh concrete. Live load shall allow for the weight of the workers and equipment, with allowance for impact, but in no case shall be less than 20 pounds per square foot (98 kg/m 2 ).

3305.3.2.3 Lateral concrete pressure.

Design of forms, ties and bracing shall satisfy the minimum lateral pressures of fresh concrete specified in Table 3305.3.2.3. Maximum rate of placement shall be shown on the design drawings.

Table 3305.3.2.3 Minimum Lateral Pressures to be Assumed for Fresh Concrete Weighing 150 Pounds Per Cubic Foot a, b, c

Type of Work Minimum Lateral Pressure Assumed (psf) Limitations Columns: Ordinary work with normal internal vibration p = 150 + (9000R/T) Maximum 3,000 psf or 150h, whichever is less Walls: Rate of placement at 7 feet per hour or less p = 150 + (9000R/T) Maximum 2,000 psf or 150h, whichever is less Walls: Rate of placement at greater than 7 feet per hour p = 150 + (43400/T) + (2800R/T) Maximum 2,000 psf or 150h, whichever is less Slabs p = 150h None

For SI: 1 inch = 25.4 mm, 1 foot per second = 0.305 m/s, 1 pound per cubic foot = 16.02 kg/m 3 , 1 pound per square foot = 4.882 kg/m 2 , °C = (°F-32)/1.8.

where:

R = rate of placement, feet per hour.

T = temperature of concrete in the forms, °F.

h = height of fresh concrete above point considered, feet.

a. Allowances for change in lateral pressure shall be made for concrete weighing other than 150 pcf; for concrete containing pozzolanic additions or cements other than Type I, for concrete having slumps greater than 6 inches, or for concrete consolidated by revibration or external vibration of forms.

b. Where retarding admixtures are employed under hot weather conditions, an effective value of temperature less than that of the concrete in the forms shall be used in the above formula.

c. If retarding admixtures are used in cold weather, the lateral pressure may be assumed as that exerted by a fluid weighing 150 pcf.

3305.3.2.4 External loads.

Braces and shores shall be designed to resist all external loads, including, but not limited to, wind, cable tensions, inclined supports, dumping of concrete, and starting and stopping of equipment. In no case shall the assumed value of lateral load acting in any direction at each floorline be less than 100 plf applied along the edge or 2 percent of total dead load of the floor, whichever is greater. Except for foundation walls that are poured against a rigid backing, wall forms shall be designed for a minimum lateral load of 10 pounds per square foot (49 kg/m 2 ), and bracing for wall forms shall be designed for a lateral load of at least 100 pounds per linear foot (148.8 kilograms per linear meter) of wall, applied at the top. The lateral load acting on walls greater than 14 feet (4267 mm) high shall be determined by analysis of conditions applicable to the site and building.

3305.3.2.5 Special loads.

The formwork shall be designed for any special conditions of construction likely to occur, such as unsymmetrical placement of concrete, impact of machine-delivered concrete, uplift and concentrated loads.

3305.3.2.6 Shoring and bracing.

Shoring and bracing shall comply with Sections 3305.3.2.6.1 through 3305.3.2.6.4.

3305.3.2.6.1 Approval.

When patented or commercial devices that are not susceptible to design are used for shoring, bracing, or splicing, they shall be approved by the commissioner.

3305.3.2.6.2 Splices.

Splices shall develop the full strength of the spliced members.

3305.3.2.6.3 Bracing.

Where shore height exceeds 10 feet (3048 mm), or when necessary to provide structural stability, diagonal bracing shall be provided. Struts, anchored into masonry or to panel joints of adjacent braced bays may be used to prevent buckling of individual members not supported by the diagonal bracing, but bracing an entire tier of shores with struts without diagonal bracing shall be prohibited unless the system can be demonstrated to be braced by other rigid construction.

3305.3.2.6.4 Unbraced length of shores.

The unbraced length of shores shall not exceed the maximum length determined in accordance with the requirements of this code for the structural material used.

3305.3.2.7 Foundations.

Foundations for shores more than 10 feet (3048 mm) high and supported on the ground shall be designed by a registered design professional.

3305.3.2.8 Settlement.

Formwork shall be so constructed that vertical adjustments can be made to compensate for take-up and settlements. Wedges, jacks or other positive means shall be provided for this purpose.

3305.3.3 Formwork inspection and observation.

Formwork shall be inspected and observed in accordance with the requirements of Sections 3305.3.3.1 through 3305.3.3.3.

3305.3.3.1 Inspection by contractor.

Formwork, including shores, reshores, braces and other supports, shall be inspected prior to placement of reinforcing steel to verify the adequacy and proper installation of the formwork, and where construction documents and form design drawings are provided, that the formwork conforms to the construction documents and form design drawings. Subsequently, during and after concreting, periodic inspections shall be performed to detect incipient problems, and the elevations, camber, and vertical alignment of formwork systems shall be inspected using tell-tale devices. Such inspections shall be performed by a qualified person designated by the contractor; nothing shall prohibit the concrete safety manager from performing such inspection where so designated. The results of such inspections shall be documented in an inspection report signed and dated by the qualified person who performed the inspection. The names of the persons responsible for such inspections and the foreman in charge of the formwork shall be posted in the field office.

3305.3.3.2 Formwork observation.

In addition to the inspections by the contractor required pursuant to Section 3305.3.3.1, visual observations of the formwork for the general conformance with the design intent shall be performed by:

1. The formwork designer;

2. An employee of the formwork designer under his or her direct supervision;

3. A registered design professional retained by the formwork designer; or

4. An employee of such retained registered design professional under the direct supervision of such retained registered design professional.

Exceptions: Formwork observation pursuant to Section 3305.3.3.2 shall not be required for:

1. Formwork that does not require design drawings pursuant to Section 3305.3.2.1; and

2. One- two- and three-family dwellings and accessory uses to such buildings.

3305.3.3.2.1 Intervals.

Formwork shall be observed at intervals permitting observation of representative configurations throughout the project duration. The formwork designer shall maintain a log of such observations at the construction site. At a minimum, observations shall be made:

1. Immediately after formwork related incidents or violations are issued; and

2. When concrete construction operations are significantly modified such as changes to form materials, concrete placement cycle, or form and support layout prior to use of the change.

3305.3.3.2.2 Discrepancies from the formwork design.

Where the individual performing the formwork observation pursuant to Section 3305.3.3.2 discovers a discrepancy from the formwork design, such discrepancy shall be immediately brought to the attention of the concrete contractor. The concrete contractor shall be responsible for correcting the discrepancy. In addition, the site safety manager, site safety coordinator, and concrete safety manager, as applicable, shall be notified of discrepancies from the formwork design that relate to site safety. Follow-up observations to confirm corrective action has been taken shall be made by the formwork designer or his or her qualified designee pursuant to Section 3305.3.3.2.

3305.3.3.2.3 Hazardous formwork conditions.

Where an observed formwork condition hazardous to life, safety, or health is not immediately corrected by the responsible contractor, the formwork designer or his or her qualified designee pursuant to Section 3305.3.3.2 shall immediately report such hazardous formwork condition and such failure to correct the hazardous formwork condition to the commissioner.

3305.3.3.3 Special inspection.

The requirements of Chapter 17 shall apply.

3305.3.4 Construction.

Concrete formwork, including but not limited to forms, shores, and shoring foundations, shall be constructed in conformance with the design drawings, where such drawings are required by Section 3305.3.2.1, and shall also be constructed to comply with the requirements of Sections 3305.3.4.1 through 3305.3.4.5.

3305.3.4.1 Field-constructed lap splices.

Field-constructed lap splices, other than approved devices, shall not be used more often than for every other shore under slabs or for every third shore under beams and shall develop the full strength of the members. Such spliced shores shall be uniformly distributed throughout the work. Splices shall not be located near the midheight of the shores unless lateral support is provided, nor midway between points of lateral support.

3305.3.4.2 Vertical shores.

Vertical shores incorporated in multi-stage shores shall be set plumb and in alignment with lower tiers so that loads from upper tiers are transferred directly to the lower tiers, or adequate transfer members shall be provided. Provision shall be made to transfer the lateral loads to the ground or to completed construction of adequate strength. Vertical shores shall be so erected that they cannot tilt, and shall have firm bearing. Inclined shores and the bearing ends of all shores shall be braced against slipping or sliding. The bearing surfaces shall be cut square and have a tight fit at splices.

3305.3.4.3 Runways.

Runways for moving equipment shall be provided with struts or legs as required and shall be supported directly on the formwork or structural member and not on the reinforcement.

3305.3.4.4 Unsafe conditions.

Any unsafe condition or necessary adjustment revealed by inspection shall be remedied immediately. If, during construction, any weakness develops and the formwork shows any undue settlement or distortion, the work shall be stopped, the affected construction removed if permanently damaged, and the formwork strengthened.

3305.3.4.5 Formwork interconnection.

Horizontal formwork deck panels and beam formwork shall be positively connected to all formwork support systems. Connections located within 16 feet (4877 mm) from the building perimeter shall be installed continuously throughout the day as the formwork is installed and shall be in place prior to the end of the shift.

3305.3.5 Removal of forms and shoring.

The removal of forms and shoring shall comply with the requirements of Sections 3305.3.5.1 through 3305.3.5.6.

3305.3.5.1 Removal schedule.

Before starting construction, the contractor shall develop a procedure and schedule for removal of shores and installation of reshores and for calculating the loads transferred to the structure during the process.

3305.3.5.1.1 Data and analysis.

The structural analysis and concrete strength data used in planning and implementing form removal and reshoring shall be furnished by the registered design professional responsible for the removal schedule to the commissioner when so requested.

3305.3.5.1.2 Support and removal.

No construction loads shall be supported on, nor any shoring removed from, any part of the structure under construction except when that portion of the structure in combination with the remaining forming and shoring system has sufficient strength to support safely its weight and the loads placed thereon.

3305.3.5.1.3 Concrete strength.

Sufficient strength shall be demonstrated by structural analysis of the proposed loads, the strength of the forming and shoring system, and concrete strength data. Concrete strength data shall be based on tests of field-cured cylinders. As an alternative, the concrete strength is permitted to be estimated using the maturity method performed in accordance with ASTM C 1074, provided that the strength is at least 500 psi (3447.38 kPa) higher than the specified compressive strength necessary for formwork or shoring removal, as applicable. Other procedures for evaluating concrete strength are also permitted when approved by the commissioner.

3305.3.5.2 Construction loads.

No construction loads exceeding the combination of superimposed dead load plus specified live load shall be supported on any unshored portion of the structure under construction, unless analysis indicates adequate strength to support such additional loads.

3305.3.5.3 Prestressed members.

Form supports for pre-stressed concrete members shall not be removed until sufficient prestressing has been applied to prestressed members to carry their dead load, anticipated construction loads, and prestress transfer forces.

3305.3.5.4 Manner of removal.

Forms shall be removed in such a manner as to ensure the complete safety of the public and property.

3305.3.5.5 Shores support.

Where the structure as a whole is supported on shores, beam and girder sides, columns and similar vertical forms may be removed after the concrete is sufficiently hard to withstand damage from the removal. In no case shall the supporting forms or shoring be removed until the members have acquired sufficient strength to safely support their weight and the load thereon.

3305.3.5.6 Control tests.

The results of control tests, including concrete cylinder specimens prepared in accordance with ASTM C 31, cast-in-place cores, or other device that will produce test specimens representative of the condition of the concrete in place, of suitable size and proportions, and approved by the registered design professional of record shall be evidence that the concrete has attained sufficient strength or the strength as may be specified on the drawings.

3305.3.6 Reshoring.

Reshoring shall be provided to support the construction where forms and shores are stripped before the concrete has attained sufficient strength to support the superimposed loads due to construction above. Reshoring shall comply with Sections 3305.3.6.1 through 3305.3.6.8.

3305.3.6.1 Reshores limitations.

Reshores shall comply with the requirements of Sections 3305.3.6.1.1 through 3305.3.6.1.7.

3305.3.6.1.1 Secureness of reshores.

Reshores of wood or metal shall be screw adjusted or jacked and locked and wedged to make them secure. Reshores shall not be jacked or screwed so tightly that they preload the floor below or remove the normal deflection of the slab above.

3305.3.6.1.2 Reshores in proximity to unenclosed perimeters.

Reshores within 10 feet (3048 mm) of an unenclosed perimeter of a building shall be secured to prevent them from falling off the building.

3305.3.6.1.3 Wedges.

Wedges shall not be used within 10 feet (3048 mm) of the facade or at such other locations as determined by the commissioner.

3305.3.6.1.4 Stresses.

In no case shall shores be so located as to alter the pattern of stresses determined in the original structural analysis or to induce tensile stresses where reinforcing bars are not provided.

3305.3.6.1.5 Angle to surface.

Reshores shall be perpendicular to the surface that they are supporting.

3305.3.6.1.6 Adjusting devices.

Adjusting devices shall not be used if heavily rusted, bent, dented, rewelded or having broken weldments or other defects.

3305.3.6.1.7 Metal shoring and accessory parts.

Metal shoring and accessory parts shall be fully operative when in use.

3305.3.6.2 Site safety provisions.

Reshoring shall comply with the requirements of Sections 3305.3.6.2.1 through 3305.3.6.2.3.

3305.3.6.2.1 Emergency.

Extra shores or material and equipment that might be needed in an emergency shall be furnished.

3305.3.6.2.2 Stripping.

Care shall be taken while stripping is underway to ensure that material does not fall off the building.

3305.3.6.2.3 Building materials.

Building materials shall be properly piled and tied or contained.

3305.3.6.3 Bracing.

Lateral bracing shall be provided during reshoring operations, and reshores shall be located as close as practical to the same position on each floor to provide continuous support from floor to floor.

3305.3.6.4 Reshoring beam and girder construction.

Where reshoring of beam and girder construction is required, the forms shall not be removed from more than one girder at a time, and the girder shall be reshored before any other supports are removed. After the supporting girders are reshored, the form shall be removed from one beam with its adjacent slabs and the beam shall be reshored before any other supports are removed. Slabs spanning 10 feet (3048 mm) or more shall be reshored along the centerline of the span.

3305.3.6.5 Reshoring flat slabs.

Where reshoring of flat-slab construction is required, the formwork cannot be stripped until the concrete has acquired sufficient strength to safely support its weight and the load thereon, or temporary preshores are provided supporting the slab at intervals of no more than 8 feet (2438 mm) on center to be replaced by reshores prior to placing concrete on the floor above. Reshores must be installed and remain in place until the concrete reaches full or sufficient strength to sustain the superimposed loads to which the concrete will be subjected.

3305.3.6.6 Stripping operation.

Debris generated as a result of stripping operations shall be immediately contained and removed at reasonable intervals. Stripping operations on concrete structures shall not be performed more than three stories below the story being formed.

3305.3.6.7 Prestressed construction.

Solid safety shields shall be provided at end anchorages of prestressing beds, or where necessary, for protection against breakage of prestressing strands, cables, or other assemblies during prestressing or casting operations.

3305.3.6.8 Reshoring Schedule.

A signed and sealed reshoring schedule shall be provided and maintained at the construction site whenever reshoring is employed.

Exception: A separate reshoring schedule is not required when the required reshoring information is covered on the approved construction documents prepared by the applicant of record.

3305.3.7 Alternate methods.

The contractor may submit alternate methods of stripping, shoring, reshoring, and strength control for approval by the registered design professional of record, subject to review by the commissioner.

3305.4 Precast concrete construction.

Precast concrete members shall be adequately braced and supported during erection to ensure proper alignment and structural integrity until permanent connections are completed.

3305.4.1 Cracking or deflections.

Any cracking or deflections inconsistent with the design drawings observed during handling shall be subject to assessment by a registered design professional prior to erection.

3305.4.2 Design of temporary shores.

Temporary shores shall be designed by a registered design professional.

3305.5 Aluminum erection.

In addition to the requirements of Section 2002, the erection of aluminum used for structural purposes shall comply with the requirements of Sections 3305.5.1 through 3305.5.4.

3305.5.1 Reserved.

3305.5.2 Temporary bracing.

Temporary bracing shall be provided to support all loads imposed upon the framework during construction that are in excess of those for which the framework was designed.

3305.5.3 Temporary connections.

As erection progresses, the work shall be securely bolted or welded to resist all dead loads, wind, and erection stresses.

3305.5.4 Alignment.

The structure shall be properly aligned before riveting, permanent bolting, or welding is performed.

3305.6 Masonry erection.

The requirements of Section 2104.5 shall apply.

3305.7 Wood construction.

The requirements of Section 2304 shall apply.

3305.8 Cold-formed steel light-frame construction.

The installation of cold-formed steel light-frame construction, the installation of decking on cold-formed steel light-frame construction, as well as the use of such framing and decking during construction or demolition operations shall be in accordance with the requirements of AISI S240 and the following sections. The design of cold-formed steel light-frame construction and decking on cold-formed steel light-frame construction shall meet the requirements of Chapter 22.

3305.8.1 Cutting, notching, and splicing.

Cutting, notching, and splicing of cold-formed steel structural members shall be performed only in accordance with specifications as indicated on drawings, including but not limited to erection drawings, approved by a registered design professional.

3305.8.2 Uniform bearing surface.

A uniform bearing surface shall be provided under cold-formed steel structural members. In no case shall the gap between the bottom track and the uniform bearing surface exceed 1/4 of an inch (6.4 mm). Leveling shall be subject to the approval of a registered design professional and shall be achieved through the use of either load bearing shims or grout.

3305.8.3 Corrosion protection.

The following precautions shall be taken to prevent corrosion of cold-formed steel structural members:

1. Dissimilar metals shall not be used in direct contact with cold-formed steel framing members unless approved for that application by the registered design professional of record for the cold-formed steel framing system.

2. Cold-formed steel framing members shall not be embedded in concrete unless approved for that application by the registered design professional of record for the cold-formed steel framing system.

3. Fasteners shall have a corrosion-resistant treatment, or be manufactured from material not susceptible to corrosion.

4. Welded connections shall be protected with a treatment, approved by the registered design professional of record for the cold-formed steel framing system, to retain corrosion resistance of the welded area.

3305.8.4 Screw connections.

Screw fasteners in cold-formed steel structural members shall extend through the steel connection with a minimum of three exposed threads.

3305.8.4.1 Stripped screws in direct tension prohibited.

Stripped screws in direct tension shall not be permitted.

3305.8.4.2 Stripped screws in shear connections.

Stripped screws in shear connections shall only be permitted if the number of stripped screw fasteners does not exceed 25 percent of the total number of fasteners in the connection.

(Am. L.L. 2023/077, 6/11/2023, eff. 6/11/2023)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2023/077.

3305.8.5 In-line framing.

Each joist, rafter, truss, and structural wall stud (above or below) shall be aligned vertically in accordance with the limits depicted in Figure B1.2.3-1 of AISI S240.

Exception: The alignment tolerance depicted in Figure B1.2.3-1 of AISI S240 shall not be required to be met when a structural load distribution member is specified in accordance with the approved construction documents.

3305.8.6 Joists, decking, and shoring and bracing.

Joists, temporary decking, permanent decking, and shoring and bracing for joists and decking shall be installed in accordance with the requirements of Section 3305.8.6.1 through 3305.8.6.9.

3305.8.6.1 Installed as indicated on drawings.

Joists, temporary decking, permanent decking, and shoring and bracing for joists and decking shall be installed as indicated on drawings, including but not limited to erection drawings, approved by a registered design professional. Such drawings shall be specific to the site and shall, at a minimum, indicate the following details:

1. Joists;

2. Permanent decking material;

3. Allowable temporary decking material;

4. Members and fasteners, including bridging, strapping, stiffeners, and placement of diaphragm;

5. Shoring and bracing, whether permanent or temporary, for joists, trusses, and decking, through all phases of work, including interim sequences;

6. Allowable designated temporary loading areas, or if no designated temporary loading areas are specified, a note that no temporary loading is allowed;

7. Types of materials and maximum loads allowed in each temporary loading area;

8. The permissible live and construction loads of the decking (temporary and permanent) and structure outside of temporary loading areas;

9. The minimum spacing of deck screws required for loading of the deck (temporary and permanent) during construction; and

10. Conditions to be satisfied before temporary shoring and bracing can be removed.

3305.8.6.2 Lateral bracing of floor joists.

Floor joists shall be laterally braced. Types of bracing to maintain structural integrity include but are not limited to steel straps screwed to top and bottom flanges, bridging between joists, web reinforcement, cross bracing, diagonal strap bracing, wall anchorage or any other details as specified on the approved drawings.

3305.8.6.3 Ceiling joists and roof trusses.

Ceiling joists and roof trusses shall be installed in accordance with one of the following:

1. With full bearing over the width of the bearing wall beneath;

2. Minimum 1 1/2 inch (38 mm) bearing end condition; or

3. In accordance with design drawings approved by a registered design professional.

3305.8.6.4 Account for all loads during construction.

Framing and decking, whether temporary or permanent, shall be designed to sustain all anticipated loads to be imposed by construction activity, including construction loads, concentrated loading caused by material delivery and loads generated by the movement of material and equipment.

3305.8.6.5 Bracing and shoring for temporary loading areas.

Bracing and shoring shall be provided for all temporary loading areas and shall be designed to support the maximum load allowed in the temporary loading area. In no case shall the required shoring be designed for a construction load of less than 100 psf. Bracing and shoring shall ultimately bear upon permanent structure or earth capable of sustaining the loads transmitted. The design shall also specify the criteria for the removal of any temporary bracing or shoring.

3305.8.6.6 Floor joists to be braced prior to installation of decking.

No decking or section of decking shall be placed on a joist until the joist has been fully installed and braced in accordance with Sections 3305.8.5 and 3305.8.6.

3305.8.6.7 Placing loads on cold-formed steel.

Loads shall be placed on cold-formed steel in accordance with section 3305.8.7.

3305.8.6.8 Removal or modification of temporary shoring and bracing.

No temporary shoring or bracing shall be removed until the cold-formed steel special inspector required by Chapter 17 has verified the shoring or bracing is no longer required in accordance with Item 10 of Section 3305.8.6.1. Modifications to temporary shoring or bracing shall be verified by the special inspector. In addition to the documentation required by Chapter 17, the special inspector shall document the verification in accordance with the checklist required by Section 3305.8.8.

(Am. L.L. 2023/077, 6/11/2023, eff. 6/11/2023)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2023/077.

3305.8.6.9 Deviations.

Deviations from the drawings required by Section 3305.8.6.1 that are not immediately corrected shall be brought to the attention of the registered design professional who prepared the drawings.

3305.8.7 Placing loads on cold-formed steel.

The placing of loads during construction or demolition work on cold-formed steel framing or on decking on cold-formed steel framing shall be in accordance with the requirements of Sections 3305.8.7.1 through 3305.8.7.6.

3305.8.7.1 System in place.

No person, material, or equipment shall be permitted on any joist, temporary decking or permanent decking, until all members, fasteners, shoring and bracing have been installed as indicated on the drawings required by Section 3305.8.6.1.

3305.8.7.2 Maximum loads.

Loading shall not exceed that as indicated on the drawings required by Section 3305.8.6.1.

3305.8.7.3 Placed as indicated on plans.

Construction loads shall only be placed in areas and to the extent as indicated on the drawings required by Section 3305.8.6.1.

3305.8.7.4 Marking the temporary loading area.

Temporary loading areas shall be clearly marked on the deck by spray paint or equivalent means. The markings shall indicate the boundaries of the loading area and the maximum loads allowed in the temporary loading area as specified in the drawings required by Section 3305.8.6.1.

3305.8.7.5 Verification by special inspector.

No construction load shall be placed on a floor or portion of a floor until the temporary or permanent decking for the floor or such portion is in place and the cold-formed steel special inspector required by Chapter 17 has verified compliance with Section 3305.8.6, including but not limited to the drawings required by Section 3305.8.6.1. At a minimum, this special inspection shall be performed at least once for each floor. In addition to the documentation required by Chapter 17, the special inspector shall document the verification in accordance with the checklist required by Section 3305.8.8.

(Am. L.L. 2023/077, 6/11/2023, eff. 6/11/2023)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2023/077.

3305.8.7.6 Verification inspection by a competent person.

Immediately prior to the placement of any person, material or equipment on a section of cold-formed steel framing for the first time, or on a section of decking on cold-formed steel framing for the first time, a competent person designated by the construction superintendent, or where the project does not require a construction superintendent, a competent person designated by the permit holder, shall determine that the structure is ready to receive the person, material or equipment by performing an inspection that:

1. Verifies compliance with applicable drawings, specifications, and regulations, including but not limited to the approved construction documents, the erection drawings, the manufacturer specifications, and the requirements of Section 3305.8;

2. Ascertains the weight of the material or equipment to be placed, and determines it does not exceed that specified in the drawings required by Section 3305.8.6.1;

3. Confirms that any special inspections for the cold-formed steel required by Chapter 17 and Section 3305.8 have been successfully completed; and

4. Verifies compliance with the requirements of Sections 3305.8.7.1 through 3305.8.7.4.

3305.8.7.6.1 Record of designation of competent person.

The designation of the competent person required by Section 3305.8.7.6 shall be recorded in the construction superintendent's log required by Section 3301.13.13, or where the project does not require a construction superintendent, the designation of the competent person shall be documented in the form of a notarized letter on the letterhead of the permit holder. The record letter shall state the name and contact information of the competent person, the date of designation and shall be signed and dated by the permit holder, the competent person and the person who designated the competent person.

3305.8.7.6.2 Record of inspection.

The results of the inspection shall be documented in accordance with the checklist required by Section 3305.8.8.

3305.8.7.6.3 Does not diminish responsibility.

The designation of a competent person does not alter or diminish any obligation imposed upon the construction superintendent or the permit holder to maintain a safe site and ensure compliance with the requirements of this code.

3305.8.8 Inspection checklist.

The results of the verification inspections required by Sections 3305.8.6.8, 3305.8.7.5 and 3305.8.7.6 shall be documented on a verification inspection checklist signed and dated by the person who performed the inspection. The verification inspection checklist shall be developed by the designer who prepared the drawings required by Section 3305.8.6.1.

(Am. L.L. 2021/148, 12/11/2021, eff. 11/7/2022)

Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 2021/148.