NYC Administrative Code RS 10-3 ACI 318–1989 BUILDING CODE REQUIREMENTS FOR REINFORCED CONCRETE
Comments—The commentary on Building Code Requirements for Reinforced Concrete (ACI 318–89) may be used as a guide for interpreting this standard.
MODIFICATIONS—The provisions of ACI 318–89 shall be subject to the following modifications. The section and subdivision numbers are from that standard.
1.2.1—Delete this section and substitute the following:
"1.2.1—The applicable provisions of the building code of the city of New York shall apply."
1.2.2—Delete this section.
1.2.3—Delete this section.
1.3.1—Delete this section and substitute the following:
"1.3.1—The applicable provisions of the building code shall apply."
1.3.2—Delete this section.
1.3.4—Delete this section.
1.4—Delete this section and substitute the following:
"1.4—The provisions of the building code for equivalent systems of design shall apply."
3.1.3—Delete this section.
3.6.6—Delete this section and substitute the following:
"3.6.6—Fly Ash may be used in lieu of Chemical Admixtures (ASTM C 494) RS 10–44."
5.1.1—Delete "5.3.2" on the second line and insert the words "Section 5.6.1.6 as listed", and delete the last sentence.
5.1.2—Delete "5.6.2" on the second line and insert the words "the New York City Building Code".
5.2.1(c)—Delete "5.6" on the second line and insert the words "the New York City Building Code".
5.2.3—Delete this section.
5.3—Delete the words "and/or trial mixtures".
5.3.1—Delete the words "Standard deviation" and insert the words "Method II Proportioning on the basis of field experience".
5.3.1.1(c)—Delete the words "except as provided in 5.3.1.2".
5.3.1.2—Delete in its entirety, including Table 5.3.1.2.
5.3.2.1—Delete "or 5.3.1.2" at the end of the sentence.
5.3.2.2—Delete in its entirety, including Table 5.3.2.2.
5.3.3—Delete the words "several strength test records, or trial mixtures" at the end of the sentence.
5.3.3.1—Delete the third sentence starting with the words "For the purpose of" and ending with the words "less than 45 days".
5.3.3.2—Add a period on the third line after the word "mixtures", delete the remainder of the section, and add the following sentence:
"The Trial mixtures shall conform to the provisions of Section 27-605(a)(3) of the New York City Building Code."
5.4.1—Delete this section and substitute the following:
"Proportioning shall conform to New York City Building Code Section 27-605(a) Method I."
Table 5.4—Delete in its entirety.
5.4.2—Delete this section.
5.4.3—Delete this section.
5.5(b)—Delete this section.
5.6.1.1—Delete this section and substitute the following:
"5.6.1.1—Whenever strength tests of concrete specimens are required by the provisions of the building code of the city of New York, compression test samples shall be taken directly from the mixer in accordance with reference standard RS 10–51, cured in accordance with reference standard RS 10–52, and tested at the age of 28 days or as otherwise specified in accordance with reference standard RS 10–17."
5.6.1.2—Delete this section and substitute the following:
"5.6.1.2—Three test specimens shall be molded for each 50 cubic yards or fraction thereof for each class of concrete placed in any one day's concreting. In addition, concrete test specimens shall be made from concrete taken out of the bucket, hopper or forms as directed by the engineer designated for controlled inspection. These test specimens shall be separate and distinct from those made from the mixer and shall be made from the same batch and cured and tested in the same manner as described above for the samples taken from the mixer."
5.6.1.3—Delete this section and substitute the following:
"5.6.1.3—The number of test specimens made from the concrete taken out of the bucket, hopper or forms may be reduced to a minimum of one set of three (3) specimens for every 150 cubic yards, or fraction thereof, for each class of concrete placed in any one day's concreting. When the concrete is being placed directly from the mixer into the forms without any intermediate conveyance, the above additional specimens will not be required."
5.6.1.4—Delete this section and substitute the following:
"5.6.1.4—Additional specimens may be molded and tested where there is a question as to the required interval between placing of concrete and stripping forms or placing the structure into use."
Add the following section:
"5.6.1.5—The test specimens shall be tested by a licensed concrete testing laboratory. The testing of each batch of three specimens shall be considered one strength test. The strength of such test shall be the average of the breaking strengths of the three specimens comprising the test, except that if one of the specimens shall manifest evidence of improper sampling, molding, handling or testing, it shall be discarded and the remaining two averaged. If more than one specimen must be discarded, the entire strength test shall be voided."
Add the following section:
"5.6.1.6—The average of all sets of three consecutive strength tests representing each class of concrete shall be equal or greater than the specified strength (f'c) and not more than 10% of the strength tests shall have values less than the specified strength, but no test shall show an average strength less than 85% of the specified strength."
5.6.2.1—Delete this section.
5.6.2.2—Delete this section.
5.6.2.3—After the word "satisfactory" in the second line, delete the remainder of the section and add the words "if the provisions of Section 5.6.1.6 are met".
5.6.2.4—Delete this section.
5.6.3.1—Delete the words "Building Official" on the first line and insert the word "Commissioner".
5.6.4.1—Delete the first three lines through the words "[Section 5.6.2.3(b)]", and substitute the following: "If tests of laboratory cured specimens fail to conform to the requirements of Section 5.6.1.6 refer to Section 5.6.3.4."
5.6.4.2—Delete the words "strength test more than 500 psi below specified value of f'c" and insert the words "set of three specimen tests which fail to conform to the requirements of Section 5.6.1.6."
Add the following section:
"5.9.3—Conveying by pumping methods shall be in accordance with the applicable provisions of the Building Code."
5.10.4—Add a period on the second line after the word "used", delete the words "unless approved by the Engineer" and add the following sentence: "For additional requirements see applicable provisions of the Building Code Section 27-607(a)(2)."
Add the following sections:
"5.14—SPECIAL REQUIREMENTS FOR HIGH STRENGTH CONCRETE.
5.14.1—All high strength concrete (6000 PSI and higher) shall be proportioned and manufactured only in accordance with the provisions of Building Code Section 27-605(b) Method II Proportioning on the basis of field experience.
5.14.2—All high strength concrete specimens shall be made utilizing metal or plastic molds that comply with reference standard RS 10–52. Each test shall consist of eight specimens taken directly from the mixer. Two specimens shall be tested at seven days, three at 28 days and three at 56 days. These requirements are in addition to the hopper specimens as required by the Building Code.
5.14.3—At the time of placement of high strength concrete, two concrete production facilities shall be available. Said facilities shall have been previously approved by the architect or engineer designated for controlled inspection.
5.14.4—All high strength concrete for columns shall be of normal weight concrete.
5.14.5—The requirements of Section 10.13.4 shall be adhered to in all respects.
5.14.6—Where lightweight concrete is to be used for the floor system, the columns and the beam or slab "sandwich" immediately above the columns shall be stone concrete, placed in accordance with the requirements of Section 10.13.
5.14.7—The engineer will insure that there are no cold joints at the interface between the lightweight concrete and stone portions of the slabs or beams.
5.14.8—All data shall be submitted periodically to the Department of Buildings for review."
Add the following section:
"6.1.7—For additional form work requirements, see applicable provisions of Building Code Section 27-1035."
Add the following sections:
"6.3.13—Concrete cover over electrical cables and snow melting pipes in sidewalks shall meet the requirements of the Bureau of Highways of the Department of Transportation.
6.3.14—No conduits, pipes or other similar embedded items will be permitted in prestressed or post-tension concrete members other than as shown on the plans as filed with the Department of Buildings or on shop drawings reviewed by the engineer of record. Computations demonstrating the effects of such embedded items on the structural adequacy of prestressed or post-tensioned concrete shall be submitted."
Add the following section:
"10.13.4—When the specified compressive strength of concrete in a column is greater than 1.4 times that specified for a floor system, the following additional requirements shall be adhered to:
(a) All of the design provisions of Section 10.13 (unmodified) are adhered to.
(b) Application is made to the Borough Superintendent in each individual case.
(c) The concrete construction is supervised and inspected continuously by a full-time Professional Engineer responsible for controlled inspection of concrete and not in the regular employ of the owner or contractor. Such engineer shall perform no other work during the construction of the particular building nor shall he delegate his responsibility to any subordinates.
(d) The Professional Engineer referred to in subdivision (c) above, without incurring any personal liability, shall be authorized to stop construction, reject any concrete, direct that the concrete testing laboratory being used be dismissed and a new laboratory be retained.
(e) Affidavits by the parties involved shall be filed with and acceptable to the Borough Superintendent prior to approval of any plans."
Add the following section:
"12.1.3—Development (Section 12.2) and splice lengths (Section 12.5) computed based on the minimum requirements of the ACI 318–83 code are deemed equally applicable for usage."
16.4.2—Delete this section and substitute the following: "16.4.2—Lifting devices shall have a capacity sufficient to support four times the appropriate portion of the members dead weight. The inclination of the lifting force shall be considered."
16.4.2.1—Delete this section.
16.4.2.2—Delete this section.
16.4.2.3—Delete this section.
21.2.1.2—Add the following sentence to the beginning of this section: "New York City is to be considered in a region of moderate risk."
Editor's note: For related unconsolidated provisions, see Appendix A at L.L. 1995/017.